ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Marvel Selva Ridge Villa Phase 01

Completed No litigation declared Residential / Group Housing project

Marvel Selva Ridge Villa Phase 01

By MARVEL OMEGA BUILDERS PVT LTD

RG-MH-11465 · RERA P52100011640 · Last updated on MahaRERA portal: 7 May 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2018Possession promisedregistration recorded completed
27 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 35%
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

Marvel Selva Ridge Villa Phase 01 is a Residential / Group Housing project by MARVEL OMEGA BUILDERS PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100011640 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2018.

At a glance

Project

  • NameMarvel Selva Ridge Villa Phase 01
  • TypeResidential / Group Housing
  • Location
    • Bavdhan Kh.
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011640
  • ReraGenie IDRG-MH-11465

Builder

  • NameMARVEL OMEGA BUILDERS PVT LTD
  • Entity typeCompany
  • DirectorVISHWAJEET SUBHASH JHAVAR
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017PromisedDec 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2018
  • Revised completionNone
  • Buildings3 building records
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EMRALD 3NA50000
EMRALD 7NA30000
JADE 8NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 May 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 35%.

EMRALD 355%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EMRALD 7100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
JADE 8100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 May 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes55%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes25%
Street LightingYes10%
Community BuildingsYes30%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes30%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26
BuildingClosed/CoveredTotal
EMRALD 32020
EMRALD 733
JADE 833

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,328 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2048.35
Proposed, not sanctioned1,848 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL MALWADKAR
EngineerRAJESH VASUDEV MANKANI
PartnerRole in project
MARVEL OMEGA BUILDERS PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 May 2021

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Selva Completion Certi Villa No 8 dated 29-09-2020.pdf7 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Comlpetion Emrald Villa 7.pdf17 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: VILLA 7 FORM 4.pdf17 Jan 2020
Layout approvalFile: Layout selva ridge.pdf10 Jan 2020
Copy of Layout Approval (in case of layout)File: Layout selva ridge.pdf10 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Selva Villa Phase I.pdf8 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SELVARIDGE VILLA PH01.pdf1 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SELVA VILLA.pdf31 Mar 2018
Layout approvalFile: LAYOUT FOR VILLA.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT FOR VILLA.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Villa.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Villa.pdf30 Jul 2017
Certificates of CA (Form 3)File: C A Certificate Villa.pdf30 Jul 2017
Building plan approvalFile: Sheet No11 Jade Villa 8 12.PDF25 Jul 2017
Building plan approvalFile: Sheet No14 Emerald 7.PDF25 Jul 2017
Building plan approvalFile: Sheet No19 Villa 3 4.PDF25 Jul 2017
Layout approvalFile: LAYOUT.PDF25 Jul 2017
PAN CardFile: Pan Card.pdf25 Jul 2017
Copy of the legal title reportFile: Title Report.pdf25 Jul 2017
Details of encumbrancesFile: Mortgage Deed Index II.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.PDF25 Jul 2017
Building Plan Approval (IOD)File: Sheet No11 Jade Villa 8 12.PDF25 Jul 2017
Building Plan Approval (IOD)File: Sheet No14 Emerald 7.PDF25 Jul 2017
Building Plan Approval (IOD)File: Sheet No19 Villa 3 4.PDF25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commecement Certificate.pdf25 Jul 2017
Declaration in FORM BFile: Affidevit Villa Phase 01.pdf25 Jul 2017
Proforma of Allotment letterFile: Allotment and Unit Agreement Phase 01 Villa.pdf25 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MARVEL SELVA RIDGE ESTATESR NO 46 BAVDHAN KHURD PUNE28CompletedDec 2014Late, Sep 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Marvel Selva Ridge Villa Phase 01 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavdhan Kh.13,700+ in Pune

2 kmMarvel Selva Ridge VillaCompleted 48Lapsed / revoked 37Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: MARVEL OMEGA BUILDERS PVT LTD

MARVEL OMEGA BUILDERS PVT LTD has 3 registrations on MahaRERA, including Marvel Selva Ridge A,B Building and Marvel Selva Ridge Villa Phase 01. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Marvel Selva Ridge Villa Phase 01 is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Marvel Selva Ridge Villa Phase 01?

The registered promoter entity is MARVEL OMEGA BUILDERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Marvel Selva Ridge Villa Phase 01?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Marvel Selva Ridge Villa Phase 01?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Marvel Selva Ridge Villa Phase 01?

The professionals named in the filing: Architect: RAHUL MALWADKAR; Engineer: RAJESH VASUDEV MANKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Marvel Selva Ridge Villa Phase 01?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Marvel Selva Ridge Villa Phase 01. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Marvel Selva Ridge Villa Phase 01 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.