Home / Browse projects / MARVEL CERISE BLDG B, C, D

Completed No litigation declared Residential / Group Housing project

MARVEL CERISE BLDG B, C, D

By MARVEL REALTORS AND DEVELOPERS LTD

RG-MH-09183 · RERA P52100002648 · Last updated on MahaRERA portal: 7 May 2021

Source: official MahaRERA filing

Red flags

  • 17 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 4 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Sep 2019Possession promisedregistration recorded completed
27 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 90%
17Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

MARVEL CERISE BLDG B, C, D is a Residential / Group Housing project by MARVEL REALTORS AND DEVELOPERS LTD in 411014, registered with MahaRERA as P52100002648 on 2 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2019. The completion date has moved by 12 months from the original filing. 17 complaints are on record with the regulator.

At a glance

Project

  • NameMARVEL CERISE BLDG B, C, D
  • TypeResidential / Group Housing
  • Location
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002648
  • ReraGenie IDRG-MH-09183

Builder

  • NameMARVEL REALTORS AND DEVELOPERS LTD
  • Entity typeCompany
  • Managing DirectorVISHWAJEET SUBHASH JHAVAR
  • Other registrations6 more →
  • Completed6 of 7
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseSep 2018Revised toSep 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Aug 2017
  • Promised completion30 Sep 2019
  • Revised completionRevised to 30 Sep 2019 (originally 30 Sep 2018)
  • Buildings3 building records
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA170000
CNA170000
DNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 May 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
D94%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 7 May 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes30%
Street LightingYes60%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes10%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes70%
Open ParkingNoNot applicable

Parking filed271

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots271
Closed/Covered271
BuildingClosed/CoveredTotal
B9292
C9292
D8787

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,890 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MARVEL OMEGA BUILDERS PVT LTDPune (M Corp.)Pune

Approvals and building plan

Permissible FSI20556.12
Proposed, not sanctioned17,643 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGHOLE ROAD,SHIVAJINAGAR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL MALWADKAR
EngineerRavindra Vasantrao Babhulay
PartnerRole in project
MARVEL REALTORS AND DEVELOPERS LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000796Sep 2018 → Sep 2019

Reason as filed by the promoterWe have completed B building and the completion certificate for B building was obtained on 13.3.2018. The work in C & D building are in progress and the delay is majorly due to installation of Lift & Fire systems. We are in the finalization of the work and after testing, Marvel will apply for completion certificate.

Complaints filed with MahaRERA17

Case no.ComplainantRespondentFiled
CC005000000011514SURYAKANT SAKERGAYENVISHWAJEET SUBHASH JHAWAR25/08/2018
CC005000000010441KAVIN P. TULSIANIMarvel Omega Builders Pvt. Ltd.20/10/2017
CC005000000010498Magnum Silk MIlls Pvt LtdMarvel Omega Builders Pvt Ltd01/11/2017
CC005000000011625Pradeep H. BhatiaMarvel Omega Builders Pvt Ltd11/06/2018
CC005000000053914Suchet P. PadhyeMarvel Omega Builders Pvt.Ltd.11/01/2020
CC005000000010802Sharda Sneh SIndhu SinghM/s. Marvel Realtors And Developers Limited03/01/2018
CC005000000010832Prakash NagraniVishwajeet Subhash Jhavar08/01/2018
CC005000000011149Prashant Pankaj MehtaVISHWAJEET JHAVAR12/03/2018
CC005000000011761SATISH JOSHIMarvel Realtors Developers or windshield developers pvt ltd or Marvel Promoters pvt ltd16/07/2018
CC0050000000119031. KIRTI BURAD 2. SUMIT BURADWindshield Developers Private Limited22/08/2018
CC005000000075072Kirti BuradMarvel Omega Builder Pvt. Ltd.27/01/2021
CC005000000085375Manish ChopraMarvel Realtors & Ors22/03/2021
CC005000000471625Magnum silk mills pvt ltd Through POA Parshotam TulsianiMarvel Omega Builders Pvt Ltd19/08/2024
CC005000000471627Kavin Parshotam TulsianiMarvel Omega Builders Pvt Ltd19/08/2024
CC12500070Naini Amar BellaraMARVEL REALTORS AND DEVELOPERS LTD08/01/2025
CC12500072Naini Amar BellaraMARVEL REALTORS AND DEVELOPERS LTD08/01/2025
CC12500806Hina Qausar ShaikhMARVEL REALTORS AND DEVELOPERS LTD09/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 May 2021

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Cerise Completion Certificate C and D 14-12-18.pdf7 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Cerise Wing B - Completion Certificate date 13-03-2018.pdf7 May 2021
Layout approvalFile: Cerise 1-18 layout.pdf10 Jan 2020
Copy of Layout Approval (in case of layout)File: Cerise 1-18 layout.pdf10 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERISE B C D.pdf30 Nov 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate.pdf13 Apr 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Bank Stetment.pdf13 Apr 2018
OtherFile: Cerise B building (form 4).pdf23 Mar 2018
Certificates of Architect (Form 4)File: Cerise B building (form 4).pdf21 Mar 2018
OtherFile: Cerise Wing B - Completion Certificate.pdf21 Mar 2018
Building plan approvalFile: B Building-4.pdf31 Aug 2017
Building plan approvalFile: C1.pdf31 Aug 2017
Building plan approvalFile: C2.pdf31 Aug 2017
Building plan approvalFile: C3.pdf31 Aug 2017
Building plan approvalFile: C4.pdf31 Aug 2017
Building plan approvalFile: D1.pdf31 Aug 2017
Building plan approvalFile: D2.pdf31 Aug 2017
Building plan approvalFile: D3.pdf31 Aug 2017
Building plan approvalFile: D4.PDF31 Aug 2017
Building plan approvalFile: Basement.pdf31 Aug 2017
Building Plan Approval (IOD)File: B Building-4.pdf31 Aug 2017
Building Plan Approval (IOD)File: C1.pdf31 Aug 2017
Building Plan Approval (IOD)File: C2.pdf31 Aug 2017
Building Plan Approval (IOD)File: C3.pdf31 Aug 2017
Building Plan Approval (IOD)File: C4.pdf31 Aug 2017
Building Plan Approval (IOD)File: D1.pdf31 Aug 2017
Building Plan Approval (IOD)File: D2.pdf31 Aug 2017
Building Plan Approval (IOD)File: D3.pdf31 Aug 2017
Building Plan Approval (IOD)File: D4.PDF31 Aug 2017
Building Plan Approval (IOD)File: Basement.pdf31 Aug 2017
Layout approvalFile: Layout.pdf30 Aug 2017
Building plan approvalFile: B Building-1.pdf30 Aug 2017
Building plan approvalFile: B Building-2.pdf30 Aug 2017
Building plan approvalFile: B Building-3.pdf30 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf30 Aug 2017
Building Plan Approval (IOD)File: B Building-1.pdf30 Aug 2017
Building Plan Approval (IOD)File: B Building-2.pdf30 Aug 2017
Building Plan Approval (IOD)File: B Building-3.pdf30 Aug 2017
Proforma of Allotment letterFile: UNIT-AGR-CERIES- B To D Building and Allotment Letter.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Ceries B C D Building.pdf23 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Ceries B C D Building.pdf23 Jul 2017
Certificates of CA (Form 3)File: C A Certificate Ceries B C D Building.pdf23 Jul 2017
Declaration in FORM BFile: Affidevit B C D Building.pdf20 Jul 2017
Declaration in FORM BFile: Affidevit B C D Co Pramoters.pdf20 Jul 2017
Building plan approvalFile: Sheet No B.pdf11 Jul 2017
Building plan approvalFile: Sheet No B1.pdf11 Jul 2017
Building plan approvalFile: Sheet No B3.pdf11 Jul 2017
Building plan approvalFile: Sheet No B4.pdf11 Jul 2017
Building plan approvalFile: Sheet No C.pdf11 Jul 2017
Building plan approvalFile: Sheet No C1.pdf11 Jul 2017
Building plan approvalFile: Sheet No C2.pdf11 Jul 2017
Building plan approvalFile: Sheet No C2.pdf11 Jul 2017
Building plan approvalFile: Sheet No C3.pdf11 Jul 2017
Building plan approvalFile: Sheet No D.pdf11 Jul 2017
Building plan approvalFile: Sheet No D1.pdf11 Jul 2017
Building plan approvalFile: Sheet No D2.pdf11 Jul 2017
Building plan approvalFile: Sheet No D3.pdf11 Jul 2017
Layout approvalFile: Sanction Layout.pdf11 Jul 2017
PAN CardFile: MRDL Pan.PDF11 Jul 2017
Copy of the legal title reportFile: Title Report.pdf11 Jul 2017
Details of encumbrancesFile: Mortgage Deed Index II.pdf11 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No B.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No B1.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No B3.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No B4.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No C.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No C1.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No C2.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No C2.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No C3.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No D.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No D1.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No D2.pdf11 Jul 2017
Building Plan Approval (IOD)File: Sheet No D3.pdf11 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - Cerise.pdf11 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
MARVEL SORRENTOSR NO 34 HISSA NO 2 BANER PUNE14CompletedMar 2016Mar 2016
MARVEL SONNETPLOT NO 105 A SR NO 199 LOHEGOAN PUNE6CompletedJan 2015Mar 2013
MARVEL CORONETFINAL PLOT 235 GHORPADI PUNE5CompletedJan 2012Dec 2011
MARVEL RITZSR NO 171 HISSA NO 1A HADAPSAR PUNE126CompletedJun 2011Dec 2010

Keep MARVEL CERISE BLDG B, C, D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

Builder: MARVEL REALTORS AND DEVELOPERS LTD

MARVEL REALTORS AND DEVELOPERS LTD has 7 registrations on MahaRERA, including MARVEL CERISE Bldg-A and MARVEL CERISE BLDG B, C, D. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record.

Frequently asked questions

What are my rights if MARVEL CERISE BLDG B, C, D is delayed beyond 30 Sep 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARVEL CERISE BLDG B, C, D?

The registered promoter entity is MARVEL REALTORS AND DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARVEL CERISE BLDG B, C, D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARVEL CERISE BLDG B, C, D?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARVEL CERISE BLDG B, C, D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARVEL CERISE BLDG B, C, D?

The professionals named in the filing: Architect: RAHUL MALWADKAR; Engineer: Ravindra Vasantrao Babhulay. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARVEL CERISE BLDG B, C, D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARVEL CERISE BLDG B, C, D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARVEL CERISE BLDG B, C, D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.