Red flags
- Registration lapsed
- Possession 54 months past the filed date
- 31 complaints at MahaRERA
- Completion date moved by 16 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mantri Vantage is a Residential / Group Housing project by SHORE DWELLINGS PRIVATE LIMITED in Kharadi, 411014, registered with MahaRERA as P52100008390 on 18 Aug 2017. Possession was promised by 29 Apr 2022 and is now 54 months past that date. The completion date has moved by 16 months from the original filing. 31 complaints are on record with the regulator.
At a glance
Project
- NameMantri Vantage
- TypeResidential / Group Housing
- Location
- Behind Zensar IT Park
- Kharadi
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100008390
- ReraGenie IDRG-MH-20279
Builder
- NameSHORE DWELLINGS PRIVATE LIMITED
- Entity typeCompany
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion29 Apr 2022
- Revised completionRevised to 29 Apr 2022 (originally 30 Dec 2020)
- Buildings3 building records
- Documents filed98 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 21 | 0 | 0 | 0 | 0 |
| B | NA | 22 | 0 | 0 | 0 | 0 |
| C | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 1 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 94%.
A49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 94% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 48% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 32% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 13% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 27% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 43% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 4% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 60% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed85
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A | 2 | 79 | 81 |
| B | 2 | 0 | 2 |
| C | 2 | 0 | 2 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Synergy Developers | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Amit Kembhavi |
| Engineer | Satish Marathe Consulting Engineers |
| Partner | Role in project |
|---|---|
| SHORE DWELLINGS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid-19 and labour charges.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 597/2015 | District Court Shivajinagar Pune | Return of Summon |
Complaints filed with MahaRERA31
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000000205 | Mantri Developers | Mantri Developers | 25/09/2017 |
| CC005000000000230 | MR PRAFUL KULARKAR | Mantri Dwellings Private Limited | 26/09/2017 |
| CC005000000011201 | Ansari Mohammad Anas Mohammad Afzal | Mantri Dwellings Pvt. Ltd. | 16/03/2018 |
| CC005000000011205 | Ansari Mohammad Ovais Mohammad Afzal | Mantri Dwellings Pvt. Ltd. | 17/03/2018 |
| CC005000000011047 | TASNEEM MOMIN | MANTRI DWELLINGS PVT. LTD. | 26/02/2018 |
| CC005000000011058 | Praful Kularkar and Neha Makdey | Mantri Dwellings Pvt Ltd through its Authorized Signatory Girish HS Gupta | 28/03/2018 |
| CC005000000011276 | RAJESH SAXENA AND SMRITI SAXENA | Mantri Dwellings Pvt Ltd | 28/03/2018 |
| CC005000000011283 | MR RAVENDRA KUMAR SAXENA AND MRS SANTOSH SAXENA | MANTRI DWELLINGS PVT LTD | 28/03/2018 |
| CC005000000022270 | Mr Syed Javed Hussain and Mrs Rizwana Hussain | mantri dwellings | 19/11/2018 |
| CC005000000022410 | SUBHASIS ROY | Mantri Dwelling Pvt Ltd | 03/01/2019 |
| CC005000000022707 | Kranti Uday Bhujbal | Mantri Dwellings Private Limited | 02/03/2019 |
| CC005000000023307 | Argha Dasgupta | Mantri Dwellings Pvt. Ltd. | 14/10/2019 |
| CC005000000054070 | Mr Ravi Bhosale and Mrs Poonam Bhosale | Mantri Dwellings Pvt Ltd | 28/02/2020 |
| CC005000000064579 | Rita Ranikhetwalla | Mantri Developers | 02/09/2020 |
| CC005000000064798 | Rahul Anup Jayakar and Baizu Rahul Jayakar | Mantri dwellings pvt ltd | 03/11/2020 |
| CC005000000064800 | Rahul Anup Jayakar and Baizu Rahul Jayakar | Mantri dwellings pvt ltd | 03/11/2020 |
| CC005000000075034 | Sumeet Vijay Bhalerao | Mantri Dwellings Private Limited | 04/01/2021 |
| CC005000000085341 | ABHA ELECTROMECH PVT. LTD. | MANTRI DWELLING PRIVATE LIMITED | 17/03/2021 |
| CC005000000085358 | SUSMITA SUSANTA MANDAL | MANTRI DWELLINGS PVT LTD | 18/03/2021 |
| CC005000000085488 | Gaurav Prakashrao Karale | Mantri Dwelling Pvt ltd | 23/04/2021 |
| CC005000000085659 | MAHENDRA SINGH RAJENDRA VERMA | MANTRI DWELLING PRIVATE LIMITED | 29/06/2021 |
| CC005000000095891 | Manoj Gobind Kotwani | Manoj Kotwani | 15/08/2021 |
| CC005000000095903 | Yugandhara Sagar Nirmalkar | Mantri Vantage | 28/08/2021 |
| CC005000000106361 | SANKET S DESHPANDE | Shore Dwellings Pvt ltd | 09/12/2021 |
| CC005000000106492 | Parth Acharya and Siddhi Acharya | Mantri Dwellings Pvt. Ltd. | 16/01/2022 |
| CC005000000106493 | Sanal Kumar Somasundaran | SHORE DWELLINGS PRIVATE LIMITED | 16/01/2022 |
| CC005000000106635 | SUHAS PATIL | SNEHAL MANTRI | 15/02/2022 |
| CC005000000258821 | PRETHEWSH JOY | MANTRI DWELLINGS PVT LTD | 05/05/2023 |
| CC005000000258949 | Mahesh Premnath Jaikhedkar | Sushil Mantri | 14/06/2023 |
| CC005000000310358 | SABITA GOSAIN | Mantri Dwellings Pvt Ltd | 11/02/2024 |
| CC12400889 | Milind Laxman Khandare | SHORE DWELLINGS PRIVATE LIMITED | 26/11/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vantage - Architect Certificate.pdf | 1 Mar 2025 |
| Certificates of CA (Form 3)File: Vantage CA Certificate_compressed.pdf | 1 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vantage - Engineer Certificate.pdf | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Vantage - Sold and Unsold_compressed.pdf | 1 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Mantri Vantage - Form 5 - FY 2021-22.pdf | 1 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Mantri Vantage - Form 5 - FY 2022-23.pdf | 1 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Mantri Vantage - Form 5 - FY 2023-24.pdf | 1 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Dec 2023.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate June 2021.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Sep 2024.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate June 2024.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate March 2024.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Sep 2023.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate June 2023.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate March 2023.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Dec 2022.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Sep 2022.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate June 2022.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate March 2022.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Dec 2021.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Sep 2021.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate March 2023_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Sep 2024_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2024_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate March 2024_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Dec 2023_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Sep 2023_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2023_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Sep 2022_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2022_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate March 2022_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA certificate Dec 2021_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Sep 2021_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2021_compressed.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Dec 2022_compressed.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Sep 2024.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate June 2024.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate March 2024.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 2023.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Sep 2023.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate June 2023.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate March 2023.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 2022.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Sep 2022.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate June 2022.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate march 2022.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 2021.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Sep 2021.pdf | 29 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate June 2021.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vantage- Architect Certificate March 2020.pdf | 19 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate 06-2020.pdf | 19 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate 09-2020.pdf | 19 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate 12-2020.pdf | 19 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate 03-2021.pdf | 19 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engg Certificate 06-2020.pdf | 19 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engg Certificate 09-2020.pdf | 19 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engg Certificate 12-2020.pdf | 19 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engg Certificate 03-2021.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Form-3 CA Certificate 06-2020.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Form-3 CA Certificate 09-2020.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Form-3 CA Certificate Dec-2020.pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Form-3 CAA Mar-2021.pdf | 19 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SDwPL_Vantage_RERA Form 5 Annual Audit Report 2019-20.pdf | 12 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SDwPL_Vantage_RERA Form 5 Annual Audit Report 2020-21.pdf | 12 Jul 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 6 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance(Form 2A FY 2020-21).pdf | 6 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory_compressed.pdf | 6 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form - 5 - MV.pdf | 20 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf | 23 Jun 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: M Vantage Quality Cert Form 2A 30092019.pdf | 12 Feb 2020 |
| Certificates of CA (Form 3)File: Mantri Vantage-CA Rera Certificate 30092019.pdf | 12 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mantri Vantage Architect Certificate 21032019.pdf | 4 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mantri Vantage RERA Engineer Certificate 21032019.pdf | 4 May 2019 |
| Certificates of CA (Form 3)File: M Vantage CA Certificate 21032019.pdf | 4 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: M Vantage Architects Certificate 21102018.pdf | 14 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: M Vantage Engineers Certificate 21102018.pdf | 14 Nov 2018 |
| Certificates of CA (Form 3)File: M Vantage CA Certificate 21102018.pdf | 14 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mantri Vantage-Architect's Certificate dated 06 08 2018.pdf | 20 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mantri Vantage-Engineer's Certificate dated 06 08 2018.pdf | 20 Sep 2018 |
| Declaration in FORM BFile: Form B Girish Gupta MDwPL.pdf | 4 May 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Mantri Vantage on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kharadi
Filed coordinates, straight-line distance. 123 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: SHORE DWELLINGS PRIVATE LIMITED
SHORE DWELLINGS PRIVATE LIMITED has 2 registrations on MahaRERA, including Mantri Vantage and Mantri Emporio. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that Mantri Vantage shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Mantri Vantage is delayed beyond 29 Apr 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mantri Vantage?
The registered promoter entity is SHORE DWELLINGS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mantri Vantage?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mantri Vantage?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mantri Vantage?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mantri Vantage?
The professionals named in the filing: Architect: Amit Kembhavi; Engineer: Satish Marathe Consulting Engineers. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mantri Vantage?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback