ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / MANTRA 24WEST PHASE 4

Completed No litigation declared Residential / Group Housing project

MANTRA 24WEST PHASE 4

By MANTRA ERECTORS AND BUILDERS LLP

RG-MH-10262 · RERA P52100001260 · Last updated on MahaRERA portal: 10 Oct 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

MANTRA 24WEST PHASE 4 is a Residential / Group Housing project by MANTRA ERECTORS AND BUILDERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100001260 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2022. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMANTRA 24WEST PHASE 4
  • TypeResidential / Group Housing
  • Location
    • Gahunje
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001260
  • ReraGenie IDRG-MH-10262

Builder

  • NameMANTRA ERECTORS AND BUILDERS LLP
  • Entity typePartnership
  • PartnerASHISH SATISH GUPTA
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2017First promiseJun 2021Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

BUILDING A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,455 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
LOPAMUDRA HANUMANT BALWADKARBanerPune
SHAILA MARUTI BALWADKARBanerPune

Approvals and building plan

Permissible FSI4121.72
Proposed, not sanctioned4,122 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSB ROAD

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMITESH SIDHPURA
PartnerRole in project
MANTRA ERECTORS AND BUILDERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009589Jun 2021 → Jun 2022

Reason as filed by the promoterDUE TO COVID PANDAMIC DELAY IN GETTING THE OC FROM THE AUTHORITY

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000157260AJIT GHANSHYAM AGARWALKIRAN WISHRAM AHER07/07/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Mar 2023

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ERECTORS_PHASE 4_21-22.pdf10 Oct 2023
CERSAI detailsFile: CERSAI Search Report Mantra 24 West.pdf17 May 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_24 west_PH4_Part OC.pdf6 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ghaunje Gat No 204 A Building Complition 24 west a.pdf14 Mar 2023
Status of ConveyanceFile: Conveyance Deed Phase 4.pdf8 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Soc formation A and SHOP.pdf16 Feb 2023
Layout approvalFile: Layout Plan_compressed (3).pdf6 Aug 2022
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed (3).pdf6 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_PH3.pdf9 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG PH 4_compressed.pdf8 Jan 2022
CERSAI detailsFile: CERSAI_REPORT.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_BUIL A_compressed.pdf8 Jan 2022
Certificates of CA (Form 3)File: CA PH 4_compressed.pdf8 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: phase 4_compressed.pdf6 Oct 2021
Certificates of CA (Form 3)File: PHASE 4_compressed.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ERECTOR 4 FORM 5_2018.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: mantra erectors form 5 phase 4 1920.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: mantra erectors form 5 phase 4 2021.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: mantra Buildcraft phase 4 certificate 19-20.pdf5 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Mantra Buildcraft Phase 4 certificate 20-21.pdf5 Oct 2021
Declaration about Commencement CertificateFile: ERECTORS.pdf4 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 West Phase 4_compressed.pdf17 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate -24 West Phase 4_compressed.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: pHASE 4 FINAL_compressed.pdf17 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 West Phase 4_compressed.pdf9 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate -24 West Phase 4_compressed.pdf9 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: pHASE 3 FIANL_compressed.pdf9 Aug 2021
Disclosure of sold/ booked inventoryFile: 24 west Ph4_compressed.pdf27 Jul 2021
Disclosure of sold/ booked inventoryFile: 24 West Ph 4_compressed.pdf2 Jun 2021
Details of encumbrancesFile: Encumbrances.pdf3 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Art ph-4.pdf23 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Ph-4.pdf23 Nov 2020
Certificates of CA (Form 3)File: CA Certificate for RERA 24 West phase 4.pdf23 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MANTRA ERECTROS 4.pdf17 Dec 2019
Certificates of CA (Form 5)File: ERECTOR 4 FORM 5_2018.pdf23 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 4th Phase 24 West.pdf27 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase04 Eng.pdf27 Mar 2018
Certificates of CA (Form 3)File: 24 west phase 4.pdf27 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NEW Commencement Certificate Gahunje-ilovepdf-compressed (1).pdf12 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 4th Phase 24 West.pdf21 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PH4.pdf21 Dec 2017
Certificates of CA (Form 3)File: 24 west CA Certificate Phase 4.pdf21 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH TECH - A.pdf24 Jul 2017
Details of encumbrancesFile: 24 WEST ENCUM.PDF23 Jul 2017
Declaration in FORM BFile: 24 west phase IV-ilovepdf-compressed.pdf23 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PH4.pdf23 Jul 2017
Certificates of CA (Form 3)File: CA CERT - A.PDF23 Jul 2017
Proforma of Allotment letterFile: Agreement draft Phase II.pdf23 Jul 2017
Proforma of Allotment letterFile: Agreement draft Phase II.pdf23 Jul 2017
Layout approvalFile: PROPOSED SANCTION LAYOUT PLAN 24 WEST PLOT ACOMPM.pdf22 Jul 2017
Copy of Layout Approval (in case of layout)File: PROPOSED SANCTION LAYOUT PLAN 24 WEST PLOT ACOMPM.pdf22 Jul 2017
Building plan approvalFile: A WING 1.PDF20 Jul 2017
Building plan approvalFile: A WING 2.PDF20 Jul 2017
Layout approvalFile: LAYOUT AND SITE DEVELOPMENT PLAN.pdf20 Jul 2017
PAN CardFile: Mantra Erectors and Builders LLP.pdf20 Jul 2017
Copy of the legal title reportFile: search reports gahunje.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT AND SITE DEVELOPMENT PLAN.pdf20 Jul 2017
Building Plan Approval (IOD)File: A WING 1.PDF20 Jul 2017
Building Plan Approval (IOD)File: A WING 2.PDF20 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Gahunje plot a A C B.pdf20 Jul 2017
Proforma of Allotment letterFile: Allotment letter SP4.pdf20 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANTRA 24WEST PHASE 4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gahunje13,700+ in Pune

2 kmMANTRA 24WEST PHASE 4Completed 20Lapsed / revoked 12Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: MANTRA ERECTORS AND BUILDERS LLP

MANTRA ERECTORS AND BUILDERS LLP has 7 registrations on MahaRERA, including PHASE 1 OF MANTRA 24 WEST and MANTRA 24WEST PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MANTRA 24WEST PHASE 4 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANTRA 24WEST PHASE 4?

The registered promoter entity is MANTRA ERECTORS AND BUILDERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANTRA 24WEST PHASE 4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MANTRA 24WEST PHASE 4?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MANTRA 24WEST PHASE 4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANTRA 24WEST PHASE 4?

The professionals named in the filing: Architect: MITESH SIDHPURA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANTRA 24WEST PHASE 4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANTRA 24WEST PHASE 4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANTRA 24WEST PHASE 4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.