Home / Browse projects / Thane, Maharashtra / Manhattan Phase 2
Manhattan Phase 2
By SAI UMA CONSTRUCTION PRIVATE LIMITED
RG-MH-57063 · RERA P51700013323 · Last updated on MahaRERA portal: 23 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Litigation declared, 8 cases
- 7 complaints at MahaRERA
- Completion date moved by 27 months
- 3 extensions taken
- Rs 297.00 crore secured on the land, in favour of ECL FINANCE LTD, Swamih investment fund I
- The charge is held by Swamih investment fund I, a distressed-debt buyer or stressed-asset fund rather than an originating lender
Clear
- Separate project account declared
- Allotment letter follows the model form
8 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Manhattan Phase 2 is a Residential / Group Housing project by SAI UMA CONSTRUCTION PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700013323 on 22 Sep 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 27 months from the original filing. 199 of the 236 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.
At a glance
Project
- NameManhattan Phase 2
- TypeResidential / Group Housing
- Location
- Hiranandani Estate
- Patlipada
- Thane (M Corp.)
- Thane
- 400615
- Pincode400615
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700013323
- ReraGenie IDRG-MH-57063
Builder
- NameSAI UMA CONSTRUCTION PRIVATE LIMITED
- Entity typeCompany
- CINU45309MH2021PTC359109
- GSTIN27ABFCS9359B1Z3
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsMahir Jagdish Khetwani, Jagdish Kanayalal Khetwani, Shantilal Ravji Patel, Dhirajlal Govind Patel, ROHAN JAGDISH KHETWANI
- Other registrations2 more →
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Sep 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed159 files
Current status
Figures as on 23 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Brooklyn | NA | 46 | 41 | 236 | 0 | 236 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.
Brooklyn: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 23 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 99% |
| Electrical meter room, sub-station, receiving station | Yes | 96% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed266
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Brooklyn | NA | Rs 98.33 cr | Rs 95.50 cr |
| - | NA | Rs 16.68 cr | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ten Folds Architects and Consultants |
| Engineer | Sunil Dnyandev Patil |
| Engineer | VAIBHAV TANAJI MANE |
| Chartered Accountant | Vallabh V Joshi |
| Chartered Accountant | Ankit Pipara |
| Chartered Accountant | Chetan Joshi |
| Chartered Accountant | Vaishali P Patil |
| Chartered Accountant | Naina Jain |
| Partner | Role in project |
|---|---|
| SAI UMA CONSTRUCTION PRIVATE LIMITED | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe policy relating to the construction amenity was revised by the provisions of UDCPR and therefore promoter was constrained to purchase adjacent property for surrender of amenity space on land instead of previously sanctioned construction amenity. The project was delayed due to a delay in the procurement of adjacent property for municipal corporation and subsequent revision in the Building plan.
Reason as filed by the promoterThe Promoter was constrained to amend the layout and building plan in accordance with the revised rules after the implementation of UDCPR in December 2020. We are constrained to provide ground amenity space instead of originally sanctioned constructed amenity to be provided to the Thane Municipal Corporation. In order to facilitate the required compliance, we had to purchase adjacent land and revise the layout of the complex known as ‘Manhattan’. Considerable time was consumed in the process of acquisition of adjacent property and sanction of revised plans. We could obtain a revised sanction b
Reason as filed by the promoter1. The Project is 97% completed 2. 55.78 % consent of allottees are obtained for the extension 3. QPR till date are updated 4.PERT Chart uploaded 5. The 97% complete and the remaining works are minor and nearing finalization. We are also in the process of obtaining the full Occupancy Certificate, which is expected to be received shortly. In view of the above, we respectfully request that an extension be granted up to 31/03/2026 for obtaining the Occupancy Certificate and handing over units to allottees
Litigation declared8
| Case | Court | Status |
|---|---|---|
| 184/2016 | THANE COURT | PENDING INTERIM ORDER IN FAVOR OF PROMOTER |
| 51/2017 | THANE COURT | Disposed |
| 290/2016 | THANE COURT | Disposed |
| 6327/2018 | High Court | Pending |
| 11/2019 | Thane Court | Pending |
| 3444/2017 | High Court | Pending |
| 3250/2017 | High Court | Pending |
| 184/2016 | Thane Court | Ongoing |
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000429327 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 19/02/2024 |
| CC006000000429329 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 19/02/2024 |
| CC006000000429330 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 27/02/2024 |
| CC006000000429331 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 27/02/2024 |
| CC006000000429333 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 27/02/2024 |
| CC006000000429334 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 27/02/2024 |
| CC006000000429336 | Runwal Developers Private Limited | Sai Uma Constructions Pvt Ltd | 27/02/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed159
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Manhattan Phase II Dec 2025.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: FORM -2.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Manhatten Phase II Dec-2025.pdf | 23 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2a Phase II 2024-2025.pdf | 23 Jan 2026 |
| Form 5 (FY 2024-2025)File: CA FORM -5_Manhattan Ph- II 2024-25.pdf | 23 Jan 2026 |
| Form 1File: MANHATTEN Phase II Form 1 Sep 25.pdf | 14 Jan 2026 |
| Form 2File: MANHATTEN Phase II Form 2 Sep 25.pdf | 14 Jan 2026 |
| Form 3File: MANHATTEN Phase II FORM 3 Sep 2025.pdf | 14 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: MANHATTEN Phase II Disclosure of Sold Unsold Sep -2025.pdf | 14 Jan 2026 |
| Form 1File: Form 1 Phase II.pdf | 14 Nov 2025 |
| Form 2File: Form 2 Phase II_compressed (2).pdf | 14 Nov 2025 |
| Form 3File: form 3 p2 June 25 PDF DSC.pdf | 14 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: June 2025 Phase II.pdf | 14 Nov 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II March-25.pdf | 17 May 2025 |
| Certificates of CA (Form 3)File: Form 3 Phase II Dec-24.pdf | 15 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Dec-24.pdf | 6 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PHASE II.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Phase II Dec-24.pdf | 22 Jan 2025 |
| Declaration in FORM BFile: Declaration form B.pdf | 10 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 10 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Phase 2 23-24.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form-3 phase ii Sep-24.pdf | 12 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PHASE II SEP-24.pdf | 10 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Phase II 2023-2024.pdf | 10 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II Form 1 30-9-24.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Phase II Sep-24.pdf | 7 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 21 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II form 1 30-6-24.pdf | 14 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II June 24.pdf | 14 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Rera Sold Unsold June -24.pdf | 14 Aug 2024 |
| Declaration about Commencement CertificateFile: CC declaration.pdf | 30 Jul 2024 |
| Proforma of Agreement for saleFile: Brooklyn draft.pdf | 30 Jul 2024 |
| Building plan approvalFile: bld -2 typical and refuge plan upto 23rd.pdf | 24 Jul 2024 |
| Building plan approvalFile: bld-2 Typical and refuge upto 24 to 38th flooR.pdf | 24 Jul 2024 |
| Building plan approvalFile: bld-2 39th and 40th floor_compressed.pdf | 24 Jul 2024 |
| Building plan approvalFile: Bld-2 carpet area and parking statment.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: bld -2 typical and refuge plan upto 23rd.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: bld-2 Typical and refuge upto 24 to 38th flooR.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: bld-2 39th and 40th floor_compressed.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: Bld-2 carpet area and parking statment.pdf | 24 Jul 2024 |
| Layout approvalFile: T2 Layout 1 (2)_compressed.pdf | 9 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: T2 Layout 1 (2)_compressed.pdf | 9 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II Form-1 31-3-24.pdf | 6 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II March-24.pdf | 6 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold March-2024 Phase II.pdf | 6 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II 31-12-2023.pdf | 22 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Dec-23.pdf | 22 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 Phase II Dec-23.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Phase II 31-12-23.pdf | 30 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sai Uma Form 5 Ph 2-22-23.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2 a .pdf | 8 Dec 2023 |
| Certificates of CA (Form 3)File: PHASE II FORM 3.pdf | 8 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II June 2023.pdf | 5 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Sep- 2023.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA CERT 2A PHASE 2 2022-23.pdf | 5 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Phase II Sep-23.pdf | 5 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II Sep -23 Arc certificate.pdf | 21 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: phase ii Sep-23.pdf | 21 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 PH II Mar 23.pdf | 8 Sep 2023 |
| Certificates of CA (Form 3)File: form 3 Phase II 30-6-23.pdf | 5 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II March-2023.pdf | 23 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II June 2023.pdf | 23 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Phase II 31-12-2022.pdf | 21 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: RERA BROOKLYN sold unsold.pdf | 21 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: RERA Phase II.pdf | 28 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Brooklyn.pdf | 23 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 p2 Aug 22.pdf | 21 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 PH2.pdf | 13 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Uma Form 5 PH2 20-21.pdf | 13 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sai Uma Form 5 PH2 21-22.pdf | 13 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PH 2 FORM-1 30-9-2022.pdf | 16 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II brooklyn.pdf | 16 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: PH -2 Brooklyn.pdf | 16 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II.pdf | 27 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Phase II Brooklyn Sold Unsold.pdf | 24 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021-22 PH2.pdf | 5 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PHASE II 15-3-2022.pdf | 28 May 2022 |
| Details of encumbrancesFile: Encumbrance Phase II.pdf | 23 Mar 2022 |
| Declaration in FORM BFile: BROOKLYN Form B Compressed.pdf | 19 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: sold unsold NOV-21 Brooklyn.pdf | 19 Mar 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Rosa Royale | s no 127 opp crown bldg hiranandani estate patlipada ghodbunder road thane west 400615 | 159 | Completed | Jun 2015 | Late, Jul 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 8 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 159 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Manhattan Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Patlipada7,600+ in Thane
Filed coordinates, straight-line distance. 180 registered projects within 2 km.
Godrej Emerald Thane
Godrej Greenview Housing Private Limited
NORTH IMPERIAL GREENS -TOWER 2
Skylark Buildspace Private Limited
VIHANG MARINA
BALAJI ENTERPRISES
Puranik City Reserva Phase 1
Puranik Builders Limited
NORTH IMPERIAL GREENS - TOWER 1
Skylark Buildspace Private Limited
RAUNAK 108
UNNATHI ASSOCIATES
See every Thane project, with the district possession charts
Builder: SAI UMA CONSTRUCTION PRIVATE LIMITED
SAI UMA CONSTRUCTION PRIVATE LIMITED has 3 registrations on MahaRERA, including Manhattan Phase 1 and Manhattan Phase 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Manhattan Phase 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Manhattan Phase 2 is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Manhattan Phase 2?
The registered promoter entity is SAI UMA CONSTRUCTION PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2021PTC359109 and GSTIN 27ABFCS9359B1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Manhattan Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Manhattan Phase 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Manhattan Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Manhattan Phase 2?
The professionals named in the filing: Architect: Ten Folds Architects and Consultants; Engineer: Sunil Dnyandev Patil; Engineer: VAIBHAV TANAJI MANE; Chartered Accountant: Vallabh V Joshi; Chartered Accountant: Ankit Pipara; Chartered Accountant: Chetan Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Manhattan Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback