Home / Browse projects / Thane, Maharashtra / Manhattan Phase 2

Registration lapsed Litigation declared Residential / Group Housing project

Manhattan Phase 2

By SAI UMA CONSTRUCTION PRIVATE LIMITED

RG-MH-57063 · RERA P51700013323 · Last updated on MahaRERA portal: 23 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Litigation declared, 8 cases
  • 7 complaints at MahaRERA
  • Completion date moved by 27 months
  • 3 extensions taken
  • Rs 297.00 crore secured on the land, in favour of ECL FINANCE LTD, Swamih investment fund I
  • The charge is held by Swamih investment fund I, a distressed-debt buyer or stressed-asset fund rather than an originating lender

Clear

  • Separate project account declared
  • Allotment letter follows the model form

8 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 99%
37 of 236Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 159 documents Report an error

Manhattan Phase 2 is a Residential / Group Housing project by SAI UMA CONSTRUCTION PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700013323 on 22 Sep 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 27 months from the original filing. 199 of the 236 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameManhattan Phase 2
  • TypeResidential / Group Housing
  • Location
    • Hiranandani Estate
    • Patlipada
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013323
  • ReraGenie IDRG-MH-57063

Builder

  • NameSAI UMA CONSTRUCTION PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309MH2021PTC359109
  • GSTIN27ABFCS9359B1Z3
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsMahir Jagdish Khetwani, Jagdish Kanayalal Khetwani, Shantilal Ravji Patel, Dhirajlal Govind Patel, ROHAN JAGDISH KHETWANI
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

7 months past promisethis monthRegisteredSep 2017First promiseDec 2023Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Sep 2017
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed159 files

Current status

84%199 of 236 units booked
83.0%Work done, per cost certificate

Figures as on 23 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BrooklynNA46412360236

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.

Brooklyn: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 23 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes99%
Electrical meter room, sub-station, receiving stationYes96%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed266

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots266
Closed/Covered266

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,125 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofECL FINANCE LTD, Swamih investment fund I
Secured amountRs 297.00 crore
CERSAI search filedYes
Declared on10 Sep 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI22622.92
Proposed, not sanctioned22,623 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop 16/17, Next to CCD, Siddhachal Phase IV, Nr Vasant Vihar, Pokharan Rd 2, Thane West
Estimated costRs 115.00 cr
Cost incurredRs 95.50 cr
Work done83.05%
BuildingWingEstimatedIncurred
BrooklynNARs 98.33 crRs 95.50 cr
-NARs 16.68 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTen Folds Architects and Consultants
EngineerSunil Dnyandev Patil
EngineerVAIBHAV TANAJI MANE
Chartered AccountantVallabh V Joshi
Chartered AccountantAnkit Pipara
Chartered AccountantChetan Joshi
Chartered AccountantVaishali P Patil
Chartered AccountantNaina Jain
PartnerRole in project
SAI UMA CONSTRUCTION PRIVATE LIMITED-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018138Dec 2023 → Dec 2024

Reason as filed by the promoterThe policy relating to the construction amenity was revised by the provisions of UDCPR and therefore promoter was constrained to purchase adjacent property for surrender of amenity space on land instead of previously sanctioned construction amenity. The project was delayed due to a delay in the procurement of adjacent property for municipal corporation and subsequent revision in the Building plan.

EXT51700025471Dec 2023 → Dec 2025

Reason as filed by the promoterThe Promoter was constrained to amend the layout and building plan in accordance with the revised rules after the implementation of UDCPR in December 2020. We are constrained to provide ground amenity space instead of originally sanctioned constructed amenity to be provided to the Thane Municipal Corporation. In order to facilitate the required compliance, we had to purchase adjacent land and revise the layout of the complex known as ‘Manhattan’. Considerable time was consumed in the process of acquisition of adjacent property and sanction of revised plans. We could obtain a revised sanction b

EA23012619562Dec 2023 → Mar 2026

Reason as filed by the promoter1. The Project is 97% completed 2. 55.78 % consent of allottees are obtained for the extension 3. QPR till date are updated 4.PERT Chart uploaded 5. The 97% complete and the remaining works are minor and nearing finalization. We are also in the process of obtaining the full Occupancy Certificate, which is expected to be received shortly. In view of the above, we respectfully request that an extension be granted up to 31/03/2026 for obtaining the Occupancy Certificate and handing over units to allottees

Litigation declared8

CaseCourtStatus
184/2016THANE COURTPENDING INTERIM ORDER IN FAVOR OF PROMOTER
51/2017THANE COURTDisposed
290/2016THANE COURTDisposed
6327/2018High CourtPending
11/2019Thane CourtPending
3444/2017High CourtPending
3250/2017High CourtPending
184/2016Thane CourtOngoing

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000429327Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd19/02/2024
CC006000000429329Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd19/02/2024
CC006000000429330Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd27/02/2024
CC006000000429331Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd27/02/2024
CC006000000429333Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd27/02/2024
CC006000000429334Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd27/02/2024
CC006000000429336Runwal Developers Private LimitedSai Uma Constructions Pvt Ltd27/02/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed159

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Manhattan Phase II Dec 2025.pdf23 Jan 2026
Withdrawal Update Form 2File: FORM -2.pdf23 Jan 2026
Withdrawal Update Form 3File: Form 3 Manhatten Phase II Dec-2025.pdf23 Jan 2026
Form 2A (FY 2024-2025)File: Form 2a Phase II 2024-2025.pdf23 Jan 2026
Form 5 (FY 2024-2025)File: CA FORM -5_Manhattan Ph- II 2024-25.pdf23 Jan 2026
Form 1File: MANHATTEN Phase II Form 1 Sep 25.pdf14 Jan 2026
Form 2File: MANHATTEN Phase II Form 2 Sep 25.pdf14 Jan 2026
Form 3File: MANHATTEN Phase II FORM 3 Sep 2025.pdf14 Jan 2026
Disclosure of Sold and Booked InventoryFile: MANHATTEN Phase II Disclosure of Sold Unsold Sep -2025.pdf14 Jan 2026
Form 1File: Form 1 Phase II.pdf14 Nov 2025
Form 2File: Form 2 Phase II_compressed (2).pdf14 Nov 2025
Form 3File: form 3 p2 June 25 PDF DSC.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: June 2025 Phase II.pdf14 Nov 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II March-25.pdf17 May 2025
Certificates of CA (Form 3)File: Form 3 Phase II Dec-24.pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Dec-24.pdf6 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PHASE II.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Phase II Dec-24.pdf22 Jan 2025
Declaration in FORM BFile: Declaration form B.pdf10 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf10 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Phase 2 23-24.pdf29 Nov 2024
Certificates of CA (Form 3)File: Form-3 phase ii Sep-24.pdf12 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PHASE II SEP-24.pdf10 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Phase II 2023-2024.pdf10 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II Form 1 30-9-24.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Phase II Sep-24.pdf7 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II form 1 30-6-24.pdf14 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II June 24.pdf14 Aug 2024
Disclosure of sold/ booked inventoryFile: Rera Sold Unsold June -24.pdf14 Aug 2024
Declaration about Commencement CertificateFile: CC declaration.pdf30 Jul 2024
Proforma of Agreement for saleFile: Brooklyn draft.pdf30 Jul 2024
Building plan approvalFile: bld -2 typical and refuge plan upto 23rd.pdf24 Jul 2024
Building plan approvalFile: bld-2 Typical and refuge upto 24 to 38th flooR.pdf24 Jul 2024
Building plan approvalFile: bld-2 39th and 40th floor_compressed.pdf24 Jul 2024
Building plan approvalFile: Bld-2 carpet area and parking statment.pdf24 Jul 2024
Building Plan Approval (IOD)File: bld -2 typical and refuge plan upto 23rd.pdf24 Jul 2024
Building Plan Approval (IOD)File: bld-2 Typical and refuge upto 24 to 38th flooR.pdf24 Jul 2024
Building Plan Approval (IOD)File: bld-2 39th and 40th floor_compressed.pdf24 Jul 2024
Building Plan Approval (IOD)File: Bld-2 carpet area and parking statment.pdf24 Jul 2024
Layout approvalFile: T2 Layout 1 (2)_compressed.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: T2 Layout 1 (2)_compressed.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II Form-1 31-3-24.pdf6 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II March-24.pdf6 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold March-2024 Phase II.pdf6 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Phase II 31-12-2023.pdf22 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Dec-23.pdf22 Feb 2024
Certificates of CA (Form 3)File: Form 3 Phase II Dec-23.pdf22 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Phase II 31-12-23.pdf30 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sai Uma Form 5 Ph 2-22-23.pdf21 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2 a .pdf8 Dec 2023
Certificates of CA (Form 3)File: PHASE II FORM 3.pdf8 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II June 2023.pdf5 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera Phase II Sep- 2023.pdf5 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA CERT 2A PHASE 2 2022-23.pdf5 Dec 2023
Certificates of CA (Form 3)File: Form 3 Phase II Sep-23.pdf5 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II Sep -23 Arc certificate.pdf21 Nov 2023
Disclosure of sold/ booked inventoryFile: phase ii Sep-23.pdf21 Nov 2023
Certificates of CA (Form 3)File: Form 3 PH II Mar 23.pdf8 Sep 2023
Certificates of CA (Form 3)File: form 3 Phase II 30-6-23.pdf5 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II March-2023.pdf23 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II June 2023.pdf23 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Phase II 31-12-2022.pdf21 Aug 2023
Disclosure of sold/ booked inventoryFile: RERA BROOKLYN sold unsold.pdf21 Aug 2023
Disclosure of sold/ booked inventoryFile: RERA Phase II.pdf28 Apr 2023
Disclosure of sold/ booked inventoryFile: Brooklyn.pdf23 Jan 2023
Certificates of CA (Form 3)File: form 3 p2 Aug 22.pdf21 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 PH2.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Uma Form 5 PH2 20-21.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sai Uma Form 5 PH2 21-22.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PH 2 FORM-1 30-9-2022.pdf16 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II brooklyn.pdf16 Dec 2022
Disclosure of sold/ booked inventoryFile: PH -2 Brooklyn.pdf16 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Phase II.pdf27 Aug 2022
Disclosure of sold/ booked inventoryFile: Phase II Brooklyn Sold Unsold.pdf24 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021-22 PH2.pdf5 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PHASE II 15-3-2022.pdf28 May 2022
Details of encumbrancesFile: Encumbrance Phase II.pdf23 Mar 2022
Declaration in FORM BFile: BROOKLYN Form B Compressed.pdf19 Mar 2022
Disclosure of sold/ booked inventoryFile: sold unsold NOV-21 Brooklyn.pdf19 Mar 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Rosa Royales no 127 opp crown bldg hiranandani estate patlipada ghodbunder road thane west 400615159CompletedJun 2015Late, Jul 2015

How this compares with Thane

84%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 27 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Manhattan Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Patlipada7,600+ in Thane

2 kmManhattan Phase 2Completed 104Lapsed / revoked 21Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: SAI UMA CONSTRUCTION PRIVATE LIMITED

SAI UMA CONSTRUCTION PRIVATE LIMITED has 3 registrations on MahaRERA, including Manhattan Phase 1 and Manhattan Phase 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Manhattan Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Manhattan Phase 2 is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Manhattan Phase 2?

The registered promoter entity is SAI UMA CONSTRUCTION PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2021PTC359109 and GSTIN 27ABFCS9359B1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Manhattan Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Manhattan Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Manhattan Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Manhattan Phase 2?

The professionals named in the filing: Architect: Ten Folds Architects and Consultants; Engineer: Sunil Dnyandev Patil; Engineer: VAIBHAV TANAJI MANE; Chartered Accountant: Vallabh V Joshi; Chartered Accountant: Ankit Pipara; Chartered Accountant: Chetan Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Manhattan Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Manhattan Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Manhattan Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.