ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / Manav Residency

Completed No litigation declared Residential / Group Housing project

Manav Residency

By Manav Enterprises

RG-MH-39302 · RERA P99000018645 · Last updated on MahaRERA portal: 21 Apr 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 95%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

Manav Residency is a Residential / Group Housing project by Manav Enterprises in Palghar, Maharashtra, registered with MahaRERA as P99000018645 on 22 Nov 2018. The registration is recorded completed; possession was promised by 30 Dec 2023.

At a glance

Project

  • NameManav Residency
  • TypeResidential / Group Housing
  • Location
    • Sativali
    • Vasai
    • Vasai East
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000018645
  • ReraGenie IDRG-MH-39302

Builder

  • NameManav Enterprises
  • Entity typePartnership
  • PartnersTrupti Vishal Patil, Yunus Bhikhabhai Hala, Falguni Chetan Mehta, Sagar Kirit Kamdar, Manthan Sanjay Shah, Nitin Sudam Patil, Hinaben Yunusbhai Hala, Mehta Harshadraiy navneetraiy, Payal Manthan Shah

Key dates

this monthRegisteredNov 2018PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Nov 2018
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Manav ResidencyNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

Manav Residency: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Closed/Covered38
Open Space26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,999 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4747.54
Proposed, not sanctioned4,748 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAmbadi Road, Vasai Road West

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Sanjay Narang of Ms EnCon
EngineerDilip P Parekh
PartnerRole in project
Manav Enterprises-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Apr 2025

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Dt 30-06-2022.pdf21 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC (1).pdf30 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: CC (1).pdf30 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: CC (1).pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: IMG_0001.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: IMG_0002.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: IMG_0003.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IMG_0003.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IMG_0004.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IMG_0005.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IMG_0006.pdf30 Sep 2021
Building plan approvalFile: Second to Seventh Floor Plan.pdf10 Jul 2020
Building plan approvalFile: Second to Seventh Floor Plan.pdf10 Jul 2020
Building plan approvalFile: Eighth Floor Plan.pdf10 Jul 2020
Building plan approvalFile: Nineth Floor Plan.pdf10 Jul 2020
Building plan approvalFile: Ground Floor Plan.pdf10 Jul 2020
Building plan approvalFile: First Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: Second to Seventh Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: Second to Seventh Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: Eighth Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: Nineth Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: Ground Floor Plan.pdf10 Jul 2020
Building Plan Approval (IOD)File: First Floor Plan.pdf10 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Permission Pg 1.pdf10 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Permission Pg 2.pdf10 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Permission Pg 3.pdf10 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_compressed.pdf10 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate_compressed.pdf10 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar.pdf13 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer.pdf13 May 2019
OtherFile: Supplimentary deed.pdf13 May 2019
OtherFile: supplimentary_compressed.pdf13 May 2019
Proforma of Allotment letterFile: Rera Flat agr Sativali (nidhi).pdf10 May 2019
OtherFile: Supplimentary deed.pdf10 May 2019
Building plan approvalFile: building appoved plan.pdf5 Nov 2018
Layout approvalFile: layout plan.pdf5 Nov 2018
Copy of the legal title reportFile: legal.PDF5 Nov 2018
Details of encumbrancesFile: ecc.PDF5 Nov 2018
Copy of Layout Approval (in case of layout)File: layout plan.pdf5 Nov 2018
Building Plan Approval (IOD)File: building appoved plan.pdf5 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: CC Copy 1 (1).pdf5 Nov 2018
Declaration in FORM BFile: form b.PDF5 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.PDF5 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.PDF5 Nov 2018
Certificates of CA (Form 3)File: ca.PDF5 Nov 2018
Proforma of Allotment letterFile: Rera Flat agr Sativali NEW (1).pdf5 Nov 2018
Proforma of Allotment letterFile: Manav Entp_Allotment Letter_Rera Formatt.pdf5 Nov 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Manav Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai East3,200+ in Palghar

Builder: Manav Enterprises

Manav Enterprises has 1 registration on MahaRERA, including Manav Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Manav Residency is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Manav Residency?

The registered promoter entity is Manav Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Manav Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Manav Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Manav Residency?

The professionals named in the filing: Architect: Mr Sanjay Narang of Ms EnCon; Engineer: Dilip P Parekh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Manav Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Manav Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Manav Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.