ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Majestique Rhythm County Phase III

Registered Litigation declared Residential / Group Housing project

Majestique Rhythm County Phase III

By MAJESTIQUE RISINGSUN LLP

RG-MH-22763 · RERA P52100032600 · Last updated on MahaRERA portal: 5 Feb 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
41 of 55Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 85%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

Majestique Rhythm County Phase III is a Residential / Group Housing project by MAJESTIQUE RISINGSUN LLP in Pune, Maharashtra, registered with MahaRERA as P52100032600 on 14 Jan 2022. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameMajestique Rhythm County Phase III
  • TypeResidential / Group Housing
  • Location
    • Autade Handewadi
    • Pune
    • OUATADE HANDEWADI
    • Haveli
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032600
  • ReraGenie IDRG-MH-22763

Builder

  • NameMAJESTIQUE RISINGSUN LLP
  • Entity typePartnership
  • GSTIN27ABHFM1323E1ZP
  • PartnersANKIT DINESH CHHAJED, GANESH BHIKULALJI SARDA, KUSHALRAJ PREMRAJ KATARIYA, BHERUSINGH NARAYANSINGH RAJPUROHIT
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jan 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING B5NA170000
WING B6NA170000
WING B7NA170000
WING B8NA170000
WING B9NA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 5 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 85%.

WING B591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B785%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
WING B885%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
WING B985%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 5 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered5
BuildingClosed/CoveredTotal
WING B511
WING B611
WING B711
WING B811
WING B911

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,988 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 May 2026
LandownerVillageDistrict
Smt Vijaya Jaising BhosalePune (M Corp.)Pune
Balasaheb Dnyanoba BhosalePune (M Corp.)Pune
Sambhaji Mahadev BhosalePune (M Corp.)Pune
Vitthalrao Sadba BhosalePune (M Corp.)Pune
Trimbak Sadba BhosalePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMRDA Pune
Permissible FSI26156.0
Proposed, not sanctioned26,156 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 1 ground floor grace platina bhavani peth opposite kumar pacific mall pune

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAY AERAM ARCHITECTS
EngineerG A BHILARE CONSULTANTS
EngineerHEMANT NIMBALKAR
Chartered AccountantCA Natwarlal Tawani
Chartered AccountantMallika Bhalgat & Co
Chartered AccountantVinod Kumar Jindal
PartnerRole in project
MAJESTIQUE RISINGSUN LLP-

Litigation declared4

CaseCourtStatus
08/2021Hon Commercial Court Pune At PuneClosed
530/2016Hon Civil Judge Senior Division Pune at PuneOngoing
406/2018Hon Distrcit Court Pune at PuneOngoing
7187/2022Honble Supreme Court of IndiaOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2025

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 MRC Ph III.pdf5 Feb 2026
Form 2File: Form 2 MRC Ph III.pdf5 Feb 2026
Form 3File: Risingsun LLP Phase 3 Q3_compressed.pdf5 Feb 2026
Disclosure of Sold and Booked InventoryFile: Rhythm County PH-III - 31-12-2025.pdf5 Feb 2026
Form 1File: phase - 3_ Form - 1.pdf6 Nov 2025
Form 2File: phase - 3_ Form - 2.pdf6 Nov 2025
Form 3File: Form 3 Risingsun Phase 3 Q2.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rhythm County - PH-III.pdf6 Nov 2025
Form 1File: Form 1 Ph 3.pdf21 Aug 2025
Form 2File: Form 2.pdf21 Aug 2025
Form 3File: Form 3 Q1 Phase 3_compressed.pdf21 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold_compressed.pdf21 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Majestique Risingsun LLP Phase 3 Q4_compressed.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30032025 AC.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032025 EC.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: M Rhythm County - PH-III - 31-3-2025_compressed.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: I 06042022 Form 1 Architect Certificate.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: II 01072022 Form 1 Architect Certificate.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: III 03102022 FOrm 1 Architect Certificate.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: IV 04012023 Form 1 Architect Certificate.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: V 30032024 Form 1.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VI 300924 Form 1 Architect's Certificate.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VII 31122024_Architect Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: I Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: II Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 040123 Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 300324 Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 300624 Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 300924 Form 2 Engineering Certificate.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 311224 Form 2 Engineering Certificate.pdf27 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Complition B5 B6_MRC_compressed.pdf27 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: RC PH-III_compressed.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: RC B5 to B9_compressed.pdf1 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Majestique Risingsun LLP Phase 3 Q3_compressed.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Majestique Risingsun LLP Phase 3 Q2_compressed.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PH - III Risinsgsun Q1_compressed.pdf30 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5 Majestique Risingsun LLP Phase 3.pdf17 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B1B2B3B4 BUILDING COMPLETION_MRC_compressed (1).pdf29 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: MRC Society Registration Certificate B-1234.pdf29 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MRC Form 5 Phase-III.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Rhythm County -B6.pdf26 May 2023
Disclosure of sold/ booked inventoryFile: Rhythm County -B5.pdf26 May 2023
Disclosure of sold/ booked inventoryFile: Rhythm County -B7.pdf26 May 2023
Disclosure of sold/ booked inventoryFile: Rhythm County -B8.pdf26 May 2023
Disclosure of sold/ booked inventoryFile: Rhythm County -B9.pdf26 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase-III_compressed.pdf20 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf23 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - RISINGSUN-PHASE-III.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Majestique Risingsun LLP Form-5 Phase III.pdf18 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf7 Jan 2022
CERSAI detailsFile: Undertaking_Cersai.pdf7 Jan 2022
Copy of the legal title reportFile: STR_MRC.pdf22 Dec 2021
Building plan approvalFile: B8 wing.pdf13 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: B8 wing.pdf13 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QCQA B5 to B9.pdf13 Dec 2021
Layout approvalFile: layout.pdf10 Dec 2021
Building plan approvalFile: B6 B9.pdf10 Dec 2021
Building plan approvalFile: B5 B7.pdf10 Dec 2021
Copy of Layout Approval (in case of layout)File: layout.pdf10 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: B6 B9.pdf10 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: B5 B7.pdf10 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf10 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf2 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf2 Dec 2021
Declaration in FORM BFile: Form B MRC Ph 3.pdf30 Nov 2021
PAN CardFile: Majestique Risingsun LLP.pdf26 Nov 2021
Details of encumbrancesFile: encumbrances.pdf26 Nov 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf26 Nov 2021
Proforma of Allotment letterFile: Unit Agreement Phase III Residential.pdf26 Nov 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationRegisteredStatusPromisedDelivered
Majestique Rhythm County Phase IVP52100054338Handewadi, PuneJan 2024OngoingDec 2028Not due yet

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Majestique Rhythm County Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

2 kmMajestique Rhythm CountyCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: MAJESTIQUE RISINGSUN LLP

MAJESTIQUE RISINGSUN LLP has 6 registrations on MahaRERA, including Majestique Rhythm County Commercial Building Phase - I and Majestique Rhythm County Phase I. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Majestique Rhythm County Phase III is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Majestique Rhythm County Phase III?

The registered promoter entity is MAJESTIQUE RISINGSUN LLP, a partnership as per the filing. Its GSTIN 27ABHFM1323E1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Majestique Rhythm County Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Majestique Rhythm County Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Majestique Rhythm County Phase III?

The professionals named in the filing: Architect: JAY AERAM ARCHITECTS; Engineer: G A BHILARE CONSULTANTS; Engineer: HEMANT NIMBALKAR; Chartered Accountant: CA Natwarlal Tawani; Chartered Accountant: Mallika Bhalgat & Co; Chartered Accountant: Vinod Kumar Jindal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Majestique Rhythm County Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Majestique Rhythm County Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Majestique Rhythm County Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.