ReraGenieLog inGet a buyer report

Home / Browse projects / MAJESTIQUE MARBELLA PHASE VI

Registered Litigation declared Residential / Group Housing project

MAJESTIQUE MARBELLA PHASE VI

By Majestique Empire LLP

RG-MH-79963 · RERA P52100051012 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Apr 2027Possession promisedno revision filed
7 of 11Construction stages donefurthest along: Internal walls, 95%
19 of 93Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

MAJESTIQUE MARBELLA PHASE VI is a Residential / Group Housing project by Majestique Empire LLP in KHARADI, 411014, registered with MahaRERA as P52100051012 on 19 May 2023. Possession is promised by 30 Apr 2027. 74 of the 93 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameMAJESTIQUE MARBELLA PHASE VI
  • TypeResidential / Group Housing
  • Location
    • KHARADI
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051012
  • ReraGenie IDRG-MH-79963

Builder

  • NameMajestique Empire LLP
  • Entity typePartnership
  • GSTIN27ABLFM0397E1Z3
  • PartnerRajendra Bhavarlal Mehta
  • Other registrations5 more →
  • No longer live4 lapsed, de-registered or revoked

Key dates

this monthRegisteredMay 2023PromisedApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 May 2023
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed131 files

Current status

80%74 of 93 units booked
68.2%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA201693093

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

WING A: 94% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes15%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes10%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed88

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots88
Closed/Covered88

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,464 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Mar 2026
LandownerVillageDistrict
M/s. Sharad Mutha Housing Development LtdAhmadnagar (M Corp.)Ahmednagar

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI10699.0
Proposed, not sanctioned9,656 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEXT TO RUBY HALL CLINIC PUNE 411001
Estimated costRs 42.65 cr
Cost incurredRs 29.07 cr
Work done68.17%
BuildingWingEstimatedIncurred
WING ANARs 39.98 crRs 28.88 cr
-NARs 2.67 crRs 19.48 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Jay Aeram
EngineerMr Gulabrao Anandrao Bhilare
EngineerSunil Zumbre
Chartered AccountantCA SANKET BHANDARI
Chartered AccountantV K Jindal & Co
Chartered AccountantMallika Bhagat & Co
PartnerRole in project
Majestique Empire LLP-

Litigation declared1

CaseCourtStatus
389/2020Honble CJSD Pune at PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 01.pdf20 Aug 2026
Withdrawal Update Form 1File: 4 Form 01 M Ph 6.pdf20 Aug 2026
Withdrawal Update Form 2File: 2 Form 02 Empire Ph VI.pdf20 Aug 2026
Withdrawal Update Form 2File: 5 Form 02 M Ph 6.pdf20 Aug 2026
Withdrawal Update Form 3File: Empire LLP Phase 6 Q4 signed1.pdf20 Aug 2026
Withdrawal Update Form 3File: Empire LLP Phase 6 Q4 signed1.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 01.pdf23 Jul 2026
Withdrawal Update Form 1File: Form 01.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 02.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 02.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM-06.pdf23 Jul 2026
Withdrawal Update Form 3File: EMPIRE PH 6 - FY 202627 - Q1- FORM 3_compressed.pdf23 Jul 2026
Form 2A (FY 2023-2024)File: 01-Form 2A.pdf20 Jul 2026
Form 2A (FY 2024-2025)File: 01-Form 2A.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: 01-Form 2A.pdf20 Jul 2026
Form 2A (FY 2026-2027)File: 01-Form 2A.pdf20 Jul 2026
Form 1File: form 01.pdf17 Mar 2026
Form 2File: form 02.pdf17 Mar 2026
Form 3File: Form 03_compressed (1).pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: PH-VI sold unsold.pdf17 Mar 2026
Form 1File: form 01.pdf17 Mar 2026
Form 2File: Form 02.pdf17 Mar 2026
Form 3File: Form 03.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Marbella A (1).pdf17 Mar 2026
Form 1File: FORM-01.pdf17 Mar 2026
Form 2File: FORM-02.pdf17 Mar 2026
Form 3File: Form 03_compressed (2).pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Marbella ph-VI-wing A.pdf17 Mar 2026
Form 1File: FORM-01.pdf17 Mar 2026
Form 2File: FORM-02.pdf17 Mar 2026
Form 3File: Form 3.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: disclouser.pdf17 Mar 2026
Form 1File: FORM-1.pdf17 Mar 2026
Form 2File: FORM-02.pdf17 Mar 2026
Form 3File: Form 03.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: disclouser.pdf17 Mar 2026
Form 1File: FORM 01.pdf16 Mar 2026
Form 2File: FORM 02.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: 01 SOLD AND UNSOLD.pdf16 Mar 2026
Form 3File: FORM 03_compressed.pdf16 Mar 2026
Form 1File: FORM 01.pdf16 Mar 2026
Form 2File: FORM 02.pdf16 Mar 2026
Form 3File: Empire Q1 Phase 6_compressed.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Marbella VI 30-06-2025.pdf16 Mar 2026
Form 1File: Form 01.pdf16 Mar 2026
Form 2File: Form 02.pdf16 Mar 2026
Form 3File: FORM 3 Majestique Empire LLP Phase 6_compressed.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: marbella VI 31 march 2025.pdf16 Mar 2026
Form 1File: Form 01.pdf16 Mar 2026
Form 2File: Form 02.pdf16 Mar 2026
Form 3File: Form 03.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Marbella A-Ph-VI (1).pdf16 Mar 2026
Form 1File: Form 01.pdf16 Mar 2026
Form 2File: Form 02.pdf16 Mar 2026
Form 3File: Form 03_compressed (1).pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: A - Marbella-Ph-VI (1).pdf16 Mar 2026
Form 5 (FY 2024-2025)File: Majestique Empire LLP Phase 6 FORM 5.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: marbella VI 30092025.pdf26 Nov 2025
Form 3File: Empire LLP Phase 6 Q2.pdf26 Nov 2025
Form 2File: Form 2 Ph VI.pdf26 Nov 2025
Form 1File: Form 1 Ph VI.pdf26 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 6_compressed (1).pdf6 May 2025
Disclosure of sold/ booked inventoryFile: marbella VI 31 march 2025_compressed.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: A - Marbella-Ph-VI.pdf29 Mar 2025
Disclosure of sold/ booked inventoryFile: Marbella A-Ph-VI.pdf29 Mar 2025
Layout approvalFile: PLAN-01-19_compressed.pdf26 Mar 2025
Building plan approvalFile: PLAN-04-19_compressed.pdf26 Mar 2025
Building plan approvalFile: PLAN-05-19_compressed.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: PLAN-01-19_compressed.pdf26 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC-42 KHARADI.pdf26 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN-04-19_compressed.pdf26 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN-05-19_compressed.pdf26 Mar 2025
Declaration about Commencement CertificateFile: CC-42 KHARADI.pdf26 Mar 2025
Declaration about Commencement CertificateFile: Format D.pdf26 Mar 2025
Declaration about Commencement CertificateFile: Format D.pdf26 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 6 _compressed.pdf25 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 6_compressed.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 6 Q1_compressed.pdf1 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 6 Q2_compressed.pdf1 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5 Majestique Empire LLP Phase 6.pdf17 Dec 2024

Keep MAJESTIQUE MARBELLA PHASE VI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHARADI

2 kmMAJESTIQUE MARBELLA PHASCompleted 49Lapsed / revoked 26Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 105 registered projects within 2 km.

Builder: Majestique Empire LLP

Majestique Empire LLP has 6 registrations on MahaRERA, including MAJESTIQUE MARBELLA PHASE 1 and MAJESTIQUE MARBELLA PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if MAJESTIQUE MARBELLA PHASE VI is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAJESTIQUE MARBELLA PHASE VI?

The registered promoter entity is Majestique Empire LLP, a partnership as per the filing. Its GSTIN 27ABLFM0397E1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAJESTIQUE MARBELLA PHASE VI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAJESTIQUE MARBELLA PHASE VI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAJESTIQUE MARBELLA PHASE VI?

The professionals named in the filing: Architect: Mr Jay Aeram; Engineer: Mr Gulabrao Anandrao Bhilare; Engineer: Sunil Zumbre; Chartered Accountant: CA SANKET BHANDARI; Chartered Accountant: V K Jindal & Co; Chartered Accountant: Mallika Bhagat & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAJESTIQUE MARBELLA PHASE VI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAJESTIQUE MARBELLA PHASE VI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAJESTIQUE MARBELLA PHASE VI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.