Registration lapsed No litigation declared Commercial project

MAJESTIQUE MARBELLA PHASE II

By Majestique Empire LLP

RG-MH-17236 · RERA P52100030349 · Last updated on MahaRERA portal: 11 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Sep 2025Possession promised13 months past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
1Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

MAJESTIQUE MARBELLA PHASE II is a Commercial project by Majestique Empire LLP in Kharadi Pune, 411014, registered with MahaRERA as P52100030349 on 17 Aug 2021. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAJESTIQUE MARBELLA PHASE II
  • TypeCommercial
  • Location
    • Kharadi Pune
    • 411014
  • Pincode411014
  • RERA no.P52100030349
  • ReraGenie IDRG-MH-17236

Builder

  • NameMajestique Empire LLP
  • Entity typePartnership
  • GSTIN27ABLFM0397E1Z3
  • PartnerRajendra Bhavarlal Mehta
  • Other registrations5 more →
  • No longer live4 lapsed, de-registered or revoked

Key dates

13 months past promisethis monthRegisteredAug 2021First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2021
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING C COMMERCIALNA40000
BUILDING D COMMERCIALNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

BUILDING C COMMERCIAL97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING D COMMERCIAL97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 11 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes65%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes95%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered60
BuildingClosed/CoveredTotal
BUILDING C COMMERCIAL3232
BUILDING D COMMERCIAL2828

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,408 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
M/S SHARAD MUTHA HOUSING DEVELOPMENT LTD-Pune
TAKSHILA COOP SOCIETY THROUGH POA M/S SHARAD MUTHA-Pune

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI2584.19
Proposed, not sanctioned2,584 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR JAY AERAM
EngineerJW CONSULTANT
Chartered AccountantNATWARLAL TAWANI
Chartered AccountantV K Jindal & Co
PartnerRole in project
Majestique Empire LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027540Dec 2024 → Sep 2025

Reason as filed by the promoter1. That we have completed around 90% work of the said project. And now only finishing work is pending which will be completed in due course of time i.e. within 30/09/2025. Further, we have applied for completion certificate for this project from Pune Municipal Corporation, Pune. As to obtain OC from PMC we need some time. Requesting for extension of few months 2. Further more, we have completed the other building projects in the same entire project and obtained OC / Completion Certificate from PMC, Pune. (Copy of the OC/ Completion Certificate is attached for your reference) 3. That out of 60

Litigation declared1

CaseCourtStatus
389/2020Honble Civil Judge Junior DivisionPending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604193Siddhant Narendra ChotheMajestique Empire LLP04/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Majestique Empire LLP Phase 2 FORM 5.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: marbella II 30- 09-2025.pdf26 Nov 2025
Form 3File: Empire LLP FORM 3 Phase 2 Q2.pdf26 Nov 2025
Form 2File: Form 2 Ph II.pdf26 Nov 2025
Form 1File: Form 1 Ph II.pdf26 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 2_compressed (1).pdf6 May 2025
Disclosure of sold/ booked inventoryFile: marbella II 31 march 2025_compressed.pdf11 Apr 2025
Proforma of Allotment letterFile: Allotment Ph II.pdf4 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A new.pdf4 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation Allotment_Ph II.pdf4 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Agreement_Ph II.pdf4 Mar 2025
Proforma of Agreement for saleFile: Agreement Ph ii.pdf4 Mar 2025
Details of encumbrancesFile: No Encum Ph II.pdf1 Mar 2025
Details of encumbrances concerned to FinanceFile: No Encum Ph II.pdf1 Mar 2025
Declaration in FORM BFile: Form B_Ph-II_Promoter.pdf1 Mar 2025
Declaration about Commencement CertificateFile: Format D phase-II.pdf1 Mar 2025
CERSAI detailsFile: Cersai Dec.pdf1 Mar 2025
Details of encumbrances concerned to LegalFile: No Encum Ph II.pdf1 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Dicloser Rajendra.pdf1 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser Manish sir.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 Phase II.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 Phase II.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Ph II.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 2_compressed.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 2 Q1_compressed.pdf1 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Majestique Empire LLP Phase 2 Q2_compressed.pdf1 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5 Majestique Empire LLP Phase 2.pdf17 Dec 2024
Disclosure of sold/ booked inventoryFile: PH-II sold unsold.pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: Marbella commercial C, D.pdf7 Jun 2024
Disclosure of sold/ booked inventoryFile: Marbella Ph-II wing C commercial.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase - 2.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed (2).pdf23 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf23 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (2).pdf23 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase-II Form-3_compressed.pdf20 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Empire Phase II.pdf23 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Phase-II_compressed.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Majestique Empire LLP Form-5 Phase II.pdf30 Nov 2022
Disclosure of sold/ booked inventoryFile: Marbella C wing (2)_compressed.pdf18 Jun 2022
Disclosure of sold/ booked inventoryFile: Marbella D wing_compressed.pdf18 Jun 2022
Declaration about Commencement CertificateFile: Form D II.pdf12 Aug 2021
Copy of the legal title reportFile: STR Kharadi 42_.pdf26 Jul 2021
Details of encumbrancesFile: Encum.pdf11 Mar 2021
Proforma of Allotment letterFile: Commercial Agreement.pdf23 Feb 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf13 Feb 2021
Declaration in FORM BFile: Form B.pdf5 Feb 2021
Layout approvalFile: 01.pdf4 Feb 2021
Building plan approvalFile: 02.pdf4 Feb 2021
Building plan approvalFile: 03.pdf4 Feb 2021
Building plan approvalFile: 04.pdf4 Feb 2021
Building plan approvalFile: 05.pdf4 Feb 2021
Building plan approvalFile: 06.pdf4 Feb 2021
Building plan approvalFile: 07.pdf4 Feb 2021
Building plan approvalFile: 08.pdf4 Feb 2021
Building plan approvalFile: 09.pdf4 Feb 2021
Building plan approvalFile: 10.pdf4 Feb 2021
Building plan approvalFile: 11.pdf4 Feb 2021
Copy of Layout Approval (in case of layout)File: 01.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 02.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 03.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 04.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 05.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 06.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 07.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 08.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 09.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 10.pdf4 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf4 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: C-C.pdf4 Feb 2021
PAN CardFile: PAN_Majestique Empire.pdf3 Feb 2021

Keep MAJESTIQUE MARBELLA PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kharadi Pune

Builder: Majestique Empire LLP

Majestique Empire LLP has 6 registrations on MahaRERA, including MAJESTIQUE MARBELLA PHASE 1 and MAJESTIQUE MARBELLA PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that MAJESTIQUE MARBELLA PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MAJESTIQUE MARBELLA PHASE II is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAJESTIQUE MARBELLA PHASE II?

The registered promoter entity is Majestique Empire LLP, a partnership as per the filing. Its GSTIN 27ABLFM0397E1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAJESTIQUE MARBELLA PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAJESTIQUE MARBELLA PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAJESTIQUE MARBELLA PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAJESTIQUE MARBELLA PHASE II?

The professionals named in the filing: Architect: MR JAY AERAM; Engineer: JW CONSULTANT; Chartered Accountant: NATWARLAL TAWANI; Chartered Accountant: V K Jindal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAJESTIQUE MARBELLA PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAJESTIQUE MARBELLA PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAJESTIQUE MARBELLA PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.