Registration lapsed No litigation declared Residential / Group Housing project

Mahavir Kalpavruksha - J Wing

By Damji Shamji Realty Private Limited

RG-MH-89838 · RERA P51700013805 · Last updated on MahaRERA portal: 10 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 21 months past the filed date
  • 10 complaints at MahaRERA
  • Completion date moved by 13 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jan 2025Possession promised21 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
10Complaints at MahaRERAon this registration
Jump to the 158 documents Report an error

Mahavir Kalpavruksha - J Wing is a Residential / Group Housing project by Damji Shamji Realty Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700013805 on 25 Oct 2017. Possession was promised by 21 Jan 2025 and is now 21 months past that date. The completion date has moved by 13 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameMahavir Kalpavruksha - J Wing
  • TypeResidential / Group Housing
  • Location
    • Kasarvadavali
    • Owale
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013805
  • ReraGenie IDRG-MH-89838

Builder

  • NameDamji Shamji Realty Private Limited
  • Entity typeCompany
  • DirectorPranay Vasantlal Shah
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

21 months past promisethis monthRegisteredOct 2017First promiseDec 2023Revised toJan 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Oct 2017
  • Promised completion21 Jan 2025
  • Revised completionRevised to 21 Jan 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed158 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mahavir Kalpavruksha - Wing JNA320000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Mahavir Kalpavruksha - Wing J: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed235

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots235
Closed/Covered220
Open Space15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,135 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI17500.0
Proposed, not sanctioned7,651 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1/2, Samyak Darshan, Jn of Tilak Road, Ghatkopar East, Mumbai 400077

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnil Hassanand Jagwani
PartnerRole in project
Damji Shamji Realty Pvt.Ltd.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018229Dec 2023 → Dec 2024

Reason as filed by the promoterWhen the country was enveloped by the Covid-19 pandemic, the Real Estate sector like many other sectors came to a complete standstill. The Indian Real Estate sector faced a major setback due to the pandemic slowing down its growth momentum. The alarming surge in the number of covid -19 cases made it difficult for us to adhere to the terms and conditions/ stipulations embodied / incorporated in the agreements entered into by us with the respective purchasers/ buyers etc. We faced a lot of difficulties with respect to completion of our project due to severe financial constraints as the demand fo

EXT51700025815Dec 2023 → Jan 2025

Reason as filed by the promoterWe were unable to complete the project within the stipulated time period as declared in the Registration Certificate as the project was affected by ‘force majeure’ viz. Covid Pandemic and as a matter of which, we were forced to take the 1 (one) year extension as provided under Section 6 of the Act. We have almost completed the project sans interior work. We have applied for Occupation Certificate (for short, “OC”) with the concerned authorities and the same is awaited. We are apprehensive of not getting co-operation from the allottees for consent for obtaining extension. We are hopeful of gett

Litigation declared2

CaseCourtStatus
930/2008Court of Civil Judge SD ThaneFor Final Argument
736/2011Court of Civil Judge SD ThaneSuit is disposed off

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000408366PRIYA HITESH JAINDamji Shamji Realty Private Limited07/12/2023
CC12500178MANISHA AMIT TAISHETEDamji Shamji Realty Private Limited19/01/2025
CC12501034BIPIN SATYAWAN BANDEKARDamji Shamji Realty Private Limited27/03/2025
CC12500236Manoj Bansilal MoreManoj More23/01/2025
CC12501112Mrunmayee Mahesh KhanolkarDamji Shamji Realty Private Limited02/04/2025
CC12501093AMIT ARUN TAISHETEDamji Shamji Realty Private Limited01/04/2025
CC12502229Denishkumar Hemantkumar GandhiDamji Shamji Realty Private Limited04/07/2025
CC12502025Kiran ShettyDamji Shamji Realty Private Limited21/06/2025
CC12503758Sanjay ChaudhariDamji Shamji Realty Pvt.Ltd.27/10/2025
CC12602588Shailesh Rajendra AgrawalDamji Shamji Realty Pvt.Ltd.03/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Feb 2025

Documents filed158

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf6 Feb 2025
Certificates of CA (Form 3)File: CA Certificate.pdf5 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Declaration for OC.pdf3 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 213 OC Certificate.pdf30 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: form 4.pdf23 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf17 Jan 2025
CERSAI detailsFile: CERSAI Report.pdf17 Jan 2025
Declaration in FORM BFile: Form B.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf25 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf6 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf5 Nov 2024
Certificates of CA (Form 3)File: CA Certificate.pdf5 Nov 2024
CERSAI detailsFile: CERSAI Report.pdf5 Nov 2024
Details of encumbrancesFile: Declaration of no encumbrance.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf26 Jul 2024
CERSAI detailsFile: CERSAI Report.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf26 Jul 2024
Certificates of CA (Form 3)File: CA Certificate.pdf26 Jul 2024
Details of encumbrancesFile: Declaration of no encumbrance.pdf21 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf19 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf18 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf18 Apr 2024
CERSAI detailsFile: CERSAI Report.pdf18 Apr 2024
Certificates of CA (Form 3)File: CA Certificate.pdf18 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf13 Jan 2024
CERSAI detailsFile: CERSAI Report.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf13 Jan 2024
Certificates of CA (Form 3)File: CA Certificate.pdf13 Jan 2024
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf20 Dec 2023
Declaration in FORM BFile: Affidavit cum declaration.pdf20 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (2022-2023).pdf20 Dec 2023
Declaration in FORM BFile: Affidavit cum declaration.pdf14 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf14 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Oct 2023
CERSAI detailsFile: CERSAI Report.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf19 Oct 2023
Certificates of CA (Form 3)File: CA Certificate.pdf19 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf27 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf27 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf27 Sep 2023
CERSAI detailsFile: CERSAI Report.pdf27 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf27 Sep 2023
Certificates of CA (Form 3)File: CA Certificate.pdf27 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf10 May 2023
Certificates of CA (Form 3)File: CA Certificate.pdf10 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Apr 2023
CERSAI detailsFile: CERSAI Report.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-2020.pdf30 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021.pdf30 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022.pdf30 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 2018-19.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf16 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf16 Jan 2023
CERSAI detailsFile: CERSAI Report.pdf16 Jan 2023
Certificates of CA (Form 3)File: CA Certificate.pdf16 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf13 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf13 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf13 Oct 2022
CERSAI detailsFile: CERSAI report.pdf13 Oct 2022
Certificates of CA (Form 3)File: CA Certificate.pdf13 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf4 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf4 Aug 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf4 Aug 2022
CERSAI detailsFile: CERSAI Report.pdf4 Aug 2022
Certificates of CA (Form 3)File: CA Certificate.pdf4 Aug 2022
CERSAI detailsFile: CERSAI Report.pdf4 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.PDF3 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf3 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold.pdf3 Jun 2022
Certificates of CA (Form 3)File: CA Certificate.pdf3 Jun 2022
Declaration about Commencement CertificateFile: Architect Certificate - Mahavir Kalpavruksha - Wing J - 31122021.PDF15 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate - Mahavir Kalpavruksha - Wing J - 31122021_compressed (1).pdf15 Jan 2022
CERSAI detailsFile: CERSAI Certificate - DS Realty - Mahavir Kalpavruksha J Wing - 31122021.pdf15 Jan 2022

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Mahavir Kalpavruksha - CloverNear Parshwanath Engineering College Ghodbunder Road Owale Village Thane West - 400 60758CompletedDec 2014Late, Oct 2015
Mahavir Kalpavruksha - MapelNear Parshwanath Engineering College Ghodbunder Road Owale Village Thane West - 400 60758CompletedAug 2013Late, Jul 2014
Mahavir Kalpavruksha - CedarNear Parshwanath Engineering College Ghodbunder Road Owale Village Thane 40060758CompletedAug 2013Late, Jul 2014
Mahavir Kalpavruksha - HazelNear Parshwanath Engineering College Ghodbunder Road Owale Village Thane West - 400 60758CompletedApr 2013Late, Oct 2013
Mahavir Kalpavruksha - CoralNear Parshwanath Engineering College Ghodbunder Road Owale Village Thane West - 400 60788CompletedApr 2013Late, Oct 2013

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 13 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahavir Kalpavruksha - J Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Owale7,600+ in Thane

2 kmMahavir Kalpavruksha - JCompleted 78Lapsed / revoked 24Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: Damji Shamji Realty Private Limited

Damji Shamji Realty Private Limited has 3 registrations on MahaRERA, including Mahavir Kalpavruksha - Oak, Tulip, Alcacia, Almond and Mahavir Kalpavruksha - J Wing. Its filings disclose 7 earlier MahaRERA projects: declares 0 of 7 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Mahavir Kalpavruksha - J Wing shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Mahavir Kalpavruksha - J Wing is delayed beyond 21 Jan 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahavir Kalpavruksha - J Wing?

The registered promoter entity is Damji Shamji Realty Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahavir Kalpavruksha - J Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mahavir Kalpavruksha - J Wing?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mahavir Kalpavruksha - J Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahavir Kalpavruksha - J Wing?

The professionals named in the filing: Architect: Anil Hassanand Jagwani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahavir Kalpavruksha - J Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahavir Kalpavruksha - J Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahavir Kalpavruksha - J Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.