Home / Browse projects / Thane, Maharashtra / MAHAAVIR PRIDE

Registered No litigation declared Others project

MAHAAVIR PRIDE

By MAHAAVIR BUILDCON LLP

RG-MH-28922 · RERA P51700027307 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 18 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
111 of 482Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

MAHAAVIR PRIDE is a Others project by MAHAAVIR BUILDCON LLP in Thane, Maharashtra, registered with MahaRERA as P51700027307 on 1 Dec 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 18 months from the original filing. 371 of the 482 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameMAHAAVIR PRIDE
  • TypeOthers
  • Location
    • MANPADA ROAD
    • DOMBIVALI EAST
    • Bhopar
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700027307
  • ReraGenie IDRG-MH-28922

Builder

  • NameMAHAAVIR BUILDCON LLP
  • Entity typePartnership
  • PartnersSANJAY B DHARIWAL, BHANWARLAL VIRDHICHAND CHHAJER, VIJAYKUMAR RANKA
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2020First promiseDec 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2020
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed136 files

Current status

77%371 of 482 units booked
89.8%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAHAAVIR PRIDE, WING - BNA372722542267
MAHAAVIR PRIDE, WING - ANA372717540215

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

MAHAAVIR PRIDE, WING - B84%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
MAHAAVIR PRIDE, WING - A84%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed396

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots396
Closed/Covered396
BuildingClosed/CoveredTotal
MAHAAVIR PRIDE, WING - B190190
MAHAAVIR PRIDE, WING - A206206

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,590 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 May 2025

Approvals and building plan

Sanctioning authoritykalyan Dombivli muncipal corporation
Permissible FSI36984.0
Proposed, not sanctioned35,653 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSECTOR 17 VASHI
Estimated costRs 105.00 cr
Cost incurredRs 94.30 cr
Work done89.81%
BuildingWingEstimatedIncurred
MAHAAVIR PRIDE, WING - BNARs 49.88 crRs 47.15 cr
MAHAAVIR PRIDE, WING - ANARs 49.88 crRs 47.15 cr
-NARs 5.25 cr-

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTHAPATYA NIRMAAN
ArchitectDESIGNO PLUS
ArchitectAbhikalpa Architects and Interior Designers
EngineerNAMDEV RANGNATH SUTAR
EngineerSK Consultants & Engineers
Chartered AccountantKailash Chand Jain & Co
Chartered AccountantMANISH KUMAR GUPTA & CO
Chartered AccountantCA Rutuja Narsingh & Associates
Chartered AccountantM/s. Pratiksha Tulshyan & Associates
Chartered AccountantNB Sayed & Associates
PartnerRole in project
MAHAAVIR BUILDCON LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA18122518746Dec 2025 → Jun 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work

EA10062621308Dec 2025 → Jun 2027

Reason as filed by the promoterThe delay in the completion of the project has primarily occured due to regulatory compliances mandated by the Maharashtra Pollution Control Board (MPCB), which consumed nearly four months of continuous administrative and operational effort. The cycle began with the Show Cause Notice dated 09/12/2025; and extended until the official regulatory sign-off on 07/04/2026, during which we were required to dismantle the RMC batching plant, implement dust suppression measures, and attend mandatory hearing. This prolonged compliance process severely diverted resources from construction activities. In a

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2020-2021)File: Form 2A 2020-21.pdf1 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A 2021-22.pdf1 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 2024-25.pdf1 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf1 Aug 2026
Form 2A (FY 2022-2023)File: Form 2A 2022-23.pdf1 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf1 Aug 2026
Withdrawal Update Form 1File: Form 1 - Mahaavir Pride as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 - Mahaavir Pride as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 - Mahaavir Pride as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 1File: Form 1 of Mahaavir Pride as on 31-03-2026.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 of Mahaavir Pride as on 31-03-2026.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 of Mahaavir Pride as on 31-03-2026.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 - Mahaavir Pride as on Dec 2025.pdf28 Feb 2026
Withdrawal Update Form 2File: Form 2 - Mahaavir Pride as on Dec 2025.pdf28 Feb 2026
Withdrawal Update Form 3File: Form 3 - Mahaavir Pride as on Dec 2025.pdf28 Feb 2026
Withdrawal Update Form 1File: Form 1 - Mahaavir Pride as on Sep 2025.pdf29 Nov 2025
Withdrawal Update Form 2File: Form 2 - Mahaavir Pride as on Sept 2025.pdf29 Nov 2025
Withdrawal Update Form 3File: Form 3 - Mahaavir Pride as on Sept 2025.pdf29 Nov 2025
Layout approvalFile: Plan 1_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 2_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 3_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 4_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 5_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 6_compressed.pdf30 Sep 2025
Building plan approvalFile: Plan 7_compressed.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: MahaavirPride_Form 5_FY2425.pdf30 Sep 2025
Form 1File: Form 1 - Mahaavir Pride as on June 2025.pdf6 Sep 2025
Form 2File: Form 2 - Mahaavir Pride as on June 2025 (SIGNED).pdf6 Sep 2025
Form 3File: Form 3 - Mahaavir Pride as on June 2025 (SIGNED).pdf6 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Mahaavir Pride as on June 2025 (SIGNED).pdf6 Sep 2025
Proforma of Agreement for saleFile: AFS 2025 04.pdf17 May 2025
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2025 03 31.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2024 12.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2025 04.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2025 01.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2025 04.pdf24 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2024 05.pdf24 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured unsecured Finance 2025-04-22.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2024-12-31.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2024 12 31.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2024 07.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2024 10.pdf5 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2024-06-30_compressed.pdf5 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2024-09-30_compressed.pdf5 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2024 MARCH_1.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2024 06.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2024 09.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2024 06 30.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2024 09 30.pdf22 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured unsecured Finance.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2024-03-31.pdf31 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Mahaavir Buildcon LLp).pdf31 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (B L Chhajer).pdf31 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Vijay kumar ranka).pdf31 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Sanjay B Dhariwal).pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2024 04.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 04.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2024 04 25.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 04.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2024 03 31.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2023-12-31.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2023 09.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2023 12.pdf9 Jan 2024
Proforma of Agreement for saleFile: AFS 3 2024 01.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2023 06.pdf2 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2022 07.PDF2 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2023 06.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 03.pdf2 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2023-09-30.pdf2 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2023-12-31.pdf2 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2023-03-31_compressed.pdf2 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CA CERTIFICATE 2023-06-30_compressed.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2023 MARCH.pdf2 Jan 2024
Copy of the legal title reportFile: TITLE CERTIFICATE 2 2023 11.pdf3 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC 2 2023 10 27.pdf3 Nov 2023
Proforma of Agreement for saleFile: AFS 2 2023 11 03.pdf3 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2023 06 30.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT 2023 03.pdf3 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 2023 03.pdf3 May 2023
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY UPTO 2023-03-31.pdf3 May 2023

How this compares with Thane

77%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 18 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHAAVIR PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVALI EAST7,600+ in Thane

2 kmMAHAAVIR PRIDECompleted 78Lapsed / revoked 74Other 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 296 registered projects within 2 km.

Builder: MAHAAVIR BUILDCON LLP

MAHAAVIR BUILDCON LLP has 2 registrations on MahaRERA, including MAHAAVIR PRIDE and MAHAAVIR LABDHI PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MAHAAVIR PRIDE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHAAVIR PRIDE?

The registered promoter entity is MAHAAVIR BUILDCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHAAVIR PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAHAAVIR PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHAAVIR PRIDE?

The professionals named in the filing: Architect: STHAPATYA NIRMAAN; Architect: DESIGNO PLUS; Architect: Abhikalpa Architects and Interior Designers; Engineer: NAMDEV RANGNATH SUTAR; Engineer: SK Consultants & Engineers; Chartered Accountant: Kailash Chand Jain & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHAAVIR PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHAAVIR PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHAAVIR PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.