Home / Browse projects / Pune, Maharashtra / Lodha Belmondo St. Andrews B,C,D Villa 1 to 28
Lodha Belmondo St. Andrews B,C,D Villa 1 to 28
By Macrotech Developers Limited
RG-MH-02647 · RERA P52100000283 · Last updated on MahaRERA portal: 17 Jun 2024
Source: official MahaRERA filing
Red flags
- 5 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Lodha Belmondo St. Andrews B,C,D Villa 1 to 28 is a Residential / Group Housing project by Macrotech Developers Limited in Pune, Maharashtra, registered with MahaRERA as P52100000283 on 12 Jul 2017. The registration is recorded completed; possession was promised by 31 Jul 2018. 5 complaints are on record with the regulator.
At a glance
Project
- NameLodha Belmondo St. Andrews B,C,D Villa 1 to 28
- TypeResidential / Group Housing
- Location
- .
- Gahunje
- Mawal
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000283
- ReraGenie IDRG-MH-02647
Builder
- NameMacrotech Developers Limited
- Entity typeCompany
- CINL45200MH1995PLC093041
- GSTIN27AAACL1490J1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsRajendra Lodha, Rajendra Lodha, Rajendra Lodha, Rajendra Lodha
- Other registrations140 more →
- Completed126 of 141
- No longer live13 lapsed, de-registered or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 Jul 2017
- Promised completion31 Jul 2018
- Revised completionNone
- Buildings17 building records
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LODHA BELMONDO ST ANDREWS B | NA | 23 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO ST ANDREWS C | NA | 23 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO ST ANDREWS D | NA | 23 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 1,2 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 3,4 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 5,6 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 7,8 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 9,10 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 11,12 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 13,14 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 15,16 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 17,18 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 19,20 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 21,22 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 23,24 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 25,26 | NA | 3 | 0 | 0 | 0 | 0 |
| LODHA BELMONDO VILLA 27,28 | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building17
As on 17 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
132 of 187 construction stages are filed complete across 17 buildings. The stage furthest along is Podiums (if any), at 0%.
LODHA BELMONDO ST ANDREWS B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LODHA BELMONDO ST ANDREWS C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LODHA BELMONDO ST ANDREWS D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LODHA BELMONDO VILLA 1,264%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 3,464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 5,664%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 7,864%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 9,1064%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 11,1264%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 13,1464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 15,1664%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 17,1864%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 19,2064%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 21,2264%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 23,2464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LODHA BELMONDO VILLA 25,2682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LODHA BELMONDO VILLA 27,2882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 17 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
| Access to Landscaped Areas | Yes | 100% |
Parking filed514
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| LODHA BELMONDO ST ANDREWS B | 28 | 134 | 162 |
| LODHA BELMONDO ST ANDREWS C | 23 | 139 | 162 |
| LODHA BELMONDO ST ANDREWS D | 23 | 139 | 162 |
| LODHA BELMONDO VILLA 1,2 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 3,4 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 5,6 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 7,8 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 9,10 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 11,12 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 13,14 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 15,16 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 17,18 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 19,20 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 21,22 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 23,24 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 25,26 | 0 | 2 | 2 |
| LODHA BELMONDO VILLA 27,28 | 0 | 2 | 2 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Lodha Developers Limited | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 137/2019 | City Civil Court Vadgaon | NA |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000010435 | MAHENDRA JAGANNATH TIWARI | PALAVA DEVELLERS PVT LTD( LODHA DEVELOPMENT PVT LTD) | 17/10/2017 |
| CC005000000064740 | Amar Pal Singh | Macrotech Developers Limited | 02/11/2020 |
| CC005000000085412 | Surendra Agarwal | Macrotech Developers Ltd. | 14/05/2021 |
| CC005000000279868 | Macrotech Developers Ltd. | Rahul Passi | 18/12/2023 |
| CC005000000279885 | Macrotech Developers Ltd. | Vishal Passi | 18/12/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 22 Nov 2021
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Sold Unsold - LODHA BELMONDO ST ANDREWS B C D VILLA 1 TO 28 - P52100000283 - March 24.pdf | 17 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold - LODHA BELMONDO ST ANDREWS B C D VILLA 1 TO 28 - P52100000283 - Dec23.pdf | 27 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: LODHA BELMONDO ST ANDREWS B C D VILLA 1 TO 28 - P52100000283 - Sep23.pdf | 27 Dec 2023 |
| Layout approvalFile: Sheet no-1 (1) (1)_compressed.pdf | 23 Jan 2023 |
| Copy of Layout Approval (in case of layout)File: Sheet no-1 (1) (1)_compressed.pdf | 23 Jan 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Reg Certificate-St-Andrews.pdf | 13 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Andrews B and Pebble Beach E.pdf | 22 Nov 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Andrews C,D and Villa.pdf | 22 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Belmondo St Andrews B C D Villa 1-28.pdf | 25 Aug 2020 |
| Details of encumbrancesFile: Andrews BCD Villas.pdf | 19 Aug 2019 |
| OtherFile: LDL to MDL.pdf | 29 May 2019 |
| Details of encumbrancesFile: BELMONDO ANDREWS B C D VILLAS.pdf | 25 Feb 2019 |
| Details of encumbrancesFile: Belmondo St Andrews BCD Villa 1 to 28.pdf | 16 Nov 2018 |
| Proforma of Allotment letterFile: ATS_Tower 24_16 October 2018.pdf | 3 Nov 2018 |
| Certificates of CA (Form 5)File: BELMONDO ANDREWS B C D VILLA 1 TO 28.pdf | 1 Oct 2018 |
| Certificates of Architect (Form 4)File: Andrews BCD and Villas.pdf | 17 Aug 2018 |
| Details of encumbrancesFile: Lodha Belmondo - Andrews B C D Villas.pdf | 14 Aug 2018 |
| Copy of the legal title reportFile: 15_Second Supplemental _Lodha Belmondo.pdf | 17 May 2018 |
| Details of encumbrancesFile: Belmondo St Andrews B C D Villas.pdf | 30 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC FINAL1.pdf | 19 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC FINAL 2.pdf | 19 Jan 2018 |
| Certificates of Architect (Form 4)File: Lodha Belmondo St Andrews B C D and Villas.pdf | 1 Dec 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lodha Belmondo St Andrews B C D and Villas.pdf | 8 Nov 2017 |
| Proforma of Allotment letterFile: ATS (Belmondo) - v2 - 2 November 2017.pdf | 6 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: St Andrews B C D and Villas (R).pdf | 7 Jul 2017 |
| Declaration in FORM BFile: Belmondo St Andrews B,C,D and Villa one to Twenty Eight.pdf | 6 Jul 2017 |
| Certificates of CA (Form 3)File: Segment 001 of Belmondo St Andrews B C D and Villas 1 to 28(R).pdf | 6 Jul 2017 |
| Certificates of CA (Form 3)File: Segment 002 of Belmondo St Andrews B C D and Villas 1 to 28(R).pdf | 6 Jul 2017 |
| Certificates of CA (Form 3)File: Segment 003 of Belmondo St Andrews B C D and Villas 1 to 28(R).pdf | 6 Jul 2017 |
| Certificates of CA (Form 3)File: Segment 004 of Belmondo St Andrews B C D and Villas 1 to 28(R).pdf | 6 Jul 2017 |
| Certificates of CA (Form 3)File: Segment 005 of Belmondo St Andrews B C D and Villas 1 to 28(R).pdf | 6 Jul 2017 |
| Building plan approvalFile: 46 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 47 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 48 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 49 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 50 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 51 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 52 (R)pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 57(R) pdf.pdf | 4 Jul 2017 |
| Building plan approvalFile: 58 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 46 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 47 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 48 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 49 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 50 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 51 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 52 (R)pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 57(R) pdf.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: 58 (R)pdf.pdf | 4 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Lodha Belmondo St Andrews B,C,D,Villa one to Twenty Eight.pdf | 3 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: One Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Two Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Three Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Four Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Five Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Six Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Seven Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Eight Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nine Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ten Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Eleven Lodha Belmondo - St Andrews B,C,D and Villa 1 to 28 - Form One.pdf | 1 Jul 2017 |
| Layout approvalFile: T-22,23,24,Villa-1 to 28 PDF.pdf | 29 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: T-22,23,24,Villa-1 to 28 PDF.pdf | 29 Jun 2017 |
| Proforma of Allotment letterFile: Allotment Letter and Agreement to sale.pdf | 29 Jun 2017 |
| Copy of the legal title reportFile: Title Report V2.pdf | 28 Jun 2017 |
| PAN CardFile: PALAVA DWELLERS PVT LTD PAN CARD.pdf | 26 Jun 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| PALAVA SAVANNA AND SIENA | Kalyan Shilphata Road | 423 | Completed | Aug 2020 | Sep 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 140 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
Keep Lodha Belmondo St. Andrews B,C,D Villa 1 to on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near .13,700+ in Pune
Filed coordinates, straight-line distance. 95 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: Macrotech Developers Limited
Macrotech Developers Limited has 141 registrations on MahaRERA, including LODHA BELMONDO ASHBRIDGE D, E and LODHA BELMONDO AUGUSTA B. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Lodha Belmondo St. Andrews B,C,D Villa 1 to 28 is delayed beyond 31 Jul 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Lodha Belmondo St. Andrews B,C,D Villa 1 to 28?
The registered promoter entity is Macrotech Developers Limited, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Lodha Belmondo St. Andrews B,C,D Villa 1 to 28?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Lodha Belmondo St. Andrews B,C,D Villa 1 to 28?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Lodha Belmondo St. Andrews B,C,D Villa 1 to 28?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in Lodha Belmondo St. Andrews B,C,D Villa 1 to 28?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback