Home / Browse projects / Pune, Maharashtra / LITTLE EARTH MASULKAR CITY PHASE 2

Registration lapsed No litigation declared Residential / Group Housing project

LITTLE EARTH MASULKAR CITY PHASE 2

By Kolte-Patil Developers Limited

RG-MH-12561 · RERA P52100005032 · Last updated on MahaRERA portal: 23 Mar 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
24 of 66Construction stages doneacross 6 buildings; furthest along: Slabs of Super Structure, 80%
3Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

LITTLE EARTH MASULKAR CITY PHASE 2 is a Residential / Group Housing project by Kolte-Patil Developers Limited in Pune, Maharashtra, registered with MahaRERA as P52100005032 on 9 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameLITTLE EARTH MASULKAR CITY PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Kivale Mamurdi Road
    • Kivale
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005032
  • ReraGenie IDRG-MH-12561

Builder

  • NameKolte-Patil Developers Limited
  • Entity typeCompany
  • DirectorGIRISH Anand ZINGADE
  • Other registrations63 more →
  • Completed14 of 64
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings6 building records
  • Documents filed79 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B3NA140000
B4NA140000
B12NA230000
C19NA130000
C20NA130000
C21NA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 23 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

B363%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)10%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B463%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)10%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B1247%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)25%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
C1961%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
C2061%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
C2161%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 23 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes40%
Street LightingYes20%
Community BuildingsYes65%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceYes60%
Open ParkingYes0%

Parking filed129

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots129
Closed/Covered6
Open Space123
BuildingClosed/CoveredOpen SpaceTotal
B312223
B415051
B12189
C1911213
C2011718
C2111415

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,839 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI22029.2
Proposed, not sanctioned22,029 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch8/3,ERANDVANA, KARVE ROAD PUNE 411004

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectADVANTAGE ARCHITECTURE
ArchitectSHREE ASSOCIATES
EngineerHANSAL PAREKH & ASSOCIATES
Chartered AccountantVDA & ASSOCIATES
PartnerRole in project
Kolte-Patil Developers Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003730Dec 2019 → Dec 2020

Reason as filed by the promoterDue to overall late performance and execution at the end of the contractor, as the contractor has faced issues of labour, unavailability of river sand, cash crunch and working capital issues at contractor’s end due to current market conditions the respective project milestones have been delayed.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000033504Rajanishh ChopraaRajesh Keshav Chavan03/10/2019
CC005000000177939Sachin Ajit SetiyaSampada Realities Pvt Ltd15/12/2022
CC005000000177945Surabhi Ajit SetiyaSampada Realities Private Limited15/12/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Mar 2022

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: B12 Society Formation.pdf23 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B12 OC.pdf12 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Little Earth PH2 Completion Certificate.pdf5 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: sept 19.pdf16 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 PH 2.pdf16 Dec 2019
Certificates of CA (Form 3)File: SRPL P2 30062019.pdf27 Aug 2019
Certificates of CA (Form 5)File: Form 5 Phase 2.pdf11 Dec 2018
Proforma of Allotment letterFile: PH 2 RERA FINAL DRAFT AGREEMENT TO SALE.pdf11 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ArcCertificate.pdf12 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EngCertificate.pdf12 Jun 2018
Certificates of CA (Form 3)File: CACertificate.pdf12 Jun 2018
Building plan approvalFile: scan6662.pdf8 Jan 2018
Building plan approvalFile: scan6663.pdf8 Jan 2018
Building plan approvalFile: scan6665.pdf8 Jan 2018
Building plan approvalFile: scan6668.pdf8 Jan 2018
Building plan approvalFile: scan6669.pdf8 Jan 2018
Building plan approvalFile: scan6670.pdf8 Jan 2018
Building plan approvalFile: scan6671.pdf8 Jan 2018
Building plan approvalFile: scan6672.pdf8 Jan 2018
Building plan approvalFile: scan6673.pdf8 Jan 2018
Building plan approvalFile: scan6673.pdf8 Jan 2018
Layout approvalFile: scan6258.pdf8 Jan 2018
Building plan approvalFile: scan6739.pdf8 Jan 2018
Building plan approvalFile: scan6742.pdf8 Jan 2018
Building plan approvalFile: scan6743.pdf8 Jan 2018
Building plan approvalFile: scan6744.pdf8 Jan 2018
Copy of Layout Approval (in case of layout)File: scan6258.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6662.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6663.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6665.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6668.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6669.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6670.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6671.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6672.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6673.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6673.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6739.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6742.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6743.pdf8 Jan 2018
Building Plan Approval (IOD)File: scan6744.pdf8 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: LetestCC.pdf8 Jan 2018
Proforma of Allotment letterFile: Agreement to Sale.pdf27 Oct 2017
Building plan approvalFile: C19.pdf28 Jul 2017
Building plan approvalFile: C19-1.pdf28 Jul 2017
Building plan approvalFile: C20.pdf28 Jul 2017
Building plan approvalFile: C20-1.pdf28 Jul 2017
Building plan approvalFile: C21.pdf28 Jul 2017
Building plan approvalFile: C21-1.pdf28 Jul 2017
Building plan approvalFile: B12.pdf28 Jul 2017
Building plan approvalFile: B12-1.pdf28 Jul 2017
Building plan approvalFile: B4-1.pdf28 Jul 2017
Layout approvalFile: KIWALE LAY OUT.pdf28 Jul 2017
Building plan approvalFile: B3.pdf28 Jul 2017
Building plan approvalFile: B3-1.pdf28 Jul 2017
Building plan approvalFile: B4.pdf28 Jul 2017
PAN CardFile: SRPL PAN.pdf28 Jul 2017
Copy of the legal title reportFile: search report 2016.pdf28 Jul 2017
Details of encumbrancesFile: Details of Encumbrance - mortgage Deed.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: KIWALE LAY OUT.pdf28 Jul 2017
Building Plan Approval (IOD)File: B3.pdf28 Jul 2017
Building Plan Approval (IOD)File: B3-1.pdf28 Jul 2017
Building Plan Approval (IOD)File: B4.pdf28 Jul 2017
Building Plan Approval (IOD)File: B4-1.pdf28 Jul 2017
Building Plan Approval (IOD)File: B12.pdf28 Jul 2017
Building Plan Approval (IOD)File: B12-1.pdf28 Jul 2017
Building Plan Approval (IOD)File: C19.pdf28 Jul 2017
Building Plan Approval (IOD)File: C19-1.pdf28 Jul 2017
Building Plan Approval (IOD)File: C20.pdf28 Jul 2017
Building Plan Approval (IOD)File: C20-1.pdf28 Jul 2017
Building Plan Approval (IOD)File: C21.pdf28 Jul 2017
Building Plan Approval (IOD)File: C21-1.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE 2015.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT2016.pdf28 Jul 2017
Declaration in FORM BFile: FORM B.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate Kiwale.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - ENGINEERS CERTIFICATE.pdf28 Jul 2017
Certificates of CA (Form 3)File: Form 3 - CA CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement to Sale.pdf28 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
LITTLE EARTH MASULKAR CITY PHASE IS NO 19 HISSA NO 1 TO 7 PLUS 9 SLASH 1 KIWALE MAMURDI ROAD KIWALE PUNE 412101172CompletedDec 2016Late, Jan 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LITTLE EARTH MASULKAR CITY PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kivale13,700+ in Pune

2 kmLITTLE EARTH MASULKAR CICompleted 88Lapsed / revoked 51Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 244 registered projects within 2 km.

Builder: Kolte-Patil Developers Limited

KOLTE-PATIL DEVELOPERS LIMITED has 64 registrations on MahaRERA, including 24K OPULA and 24K ATRIA. Its filings disclose 14 earlier MahaRERA projects: declares 13 of 14 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that LITTLE EARTH MASULKAR CITY PHASE 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LITTLE EARTH MASULKAR CITY PHASE 2 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LITTLE EARTH MASULKAR CITY PHASE 2?

The registered promoter entity is Kolte-Patil Developers Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LITTLE EARTH MASULKAR CITY PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LITTLE EARTH MASULKAR CITY PHASE 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LITTLE EARTH MASULKAR CITY PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LITTLE EARTH MASULKAR CITY PHASE 2?

The professionals named in the filing: Architect: ADVANTAGE ARCHITECTURE; Architect: SHREE ASSOCIATES; Engineer: HANSAL PAREKH & ASSOCIATES; Chartered Accountant: VDA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LITTLE EARTH MASULKAR CITY PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LITTLE EARTH MASULKAR CITY PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LITTLE EARTH MASULKAR CITY PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.