Leela by Empyrean Landmarks - Phase I

By Empyrean Landmarks

RG-MH-63789 · RERA P52100052570 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2027Possession promisedmoved 12 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
7 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

Leela by Empyrean Landmarks - Phase I is a Residential / Group Housing project by Empyrean Landmarks in Kharadi, Haveli, 411014, registered with MahaRERA as P52100052570 on 11 Sep 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 65 of the 72 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameLeela by Empyrean Landmarks - Phase I
  • TypeResidential / Group Housing
  • Location
    • River Road
    • Kharadi
    • Haveli
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052570
  • ReraGenie IDRG-MH-63789

Builder

  • NameEmpyrean Landmarks
  • Entity typePartnership
  • PartnersPramod Shankar Jawalkar, Sandeep Sadashiv Ghule, Mangesh Somnath Bahirat, Mangesh Ramesh Magar, Krishna Rajesh Pawar
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2023First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed120 files

Current status

90%65 of 72 units booked
63.8%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E WingNA211872072

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

E Wing: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed98

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots98
Closed/Covered98

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,305 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Jul 2025
LandownerVillageDistrict
Ameya Arun KodrePanchgani (M Cl)Satara
Jyoti Arun KodreMundhawaPune
Pooja Arun KodreMundhawaPune
Arun Sambhaji KodreMundhawaPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI7530.59
Proposed, not sanctioned7,319 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTARA CHAMBERS, NEAR MARIYAI, POLICE CHOWKY, MUMBAIPUNE ROAD, PUNE-411001
Estimated costRs 26.00 cr
Cost incurredRs 16.59 cr
Work done63.81%
BuildingWingEstimatedIncurred
E WingNARs 22.10 crRs 15.93 cr
-NARs 3.90 crRs 66.30 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCubix Architects Associates
EngineerBricklane
EngineerRavindra Khaire Khaire
EngineerSarang Bhaskar
EngineerNaresh Parulekar
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates
PartnerRole in project
Empyrean Landmarks-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25042620738Dec 2026 → Dec 2027

Reason as filed by the promoterDisruption in Supply Chain and Delay in Procurement of Construction Materials,Labour Shortage - Skilled and Unskilled Workforce,Price Escalation and Cost Overruns

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 CUBIX PH-1.pdf20 Jul 2026
Withdrawal Update Form 2File: FORM -2 PH-2.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM-3 PH-1.pdf20 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf23 Apr 2026
Withdrawal Update Form 2File: FORM2 Mar26.pdf23 Apr 2026
Withdrawal Update Form 3File: FORM 3 PH-1.pdf23 Apr 2026
Withdrawal Update Form 1File: ARCH CERTIFICATE PH 1 signed.pdf3 Feb 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE PH1 Signed.pdf3 Feb 2026
Withdrawal Update Form 3File: FORM 3 PH1 signed Dec 25.pdf3 Feb 2026
Form 2A (FY 2023-2024)File: 2 FOrm 2A Ph 1 Mar 24.pdf7 Nov 2025
Form 2A (FY 2024-2025)File: Form-2A Ph-1 ( FY 24-25)_compressed.pdf7 Nov 2025
Form 5 (FY 2023-2024)File: EL- Form 5 Phase -I.pdf7 Nov 2025
Withdrawal Update Form 1File: FORM-1 (PH1).pdf1 Nov 2025
Withdrawal Update Form 2File: FORM-2 (PH1).pdf1 Nov 2025
Withdrawal Update Form 3File: FORM-3 (PH1)_and Sold Unsold.pdf1 Nov 2025
Form 5 (FY 2024-2025)File: EL- Form 5 Phase -I.pdf29 Sep 2025
Withdrawal Update Form 1File: PH-1 ARCH CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 1File: PH-1 ARCH CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 2File: PH-1 ENG CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 2File: PH-1 ENG CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 3File: PH-1 FORM -3.pdf19 Jul 2025
Withdrawal Update Form 3File: PH-1 FORM -3.pdf19 Jul 2025
Form 1File: 01 Form 1 Sep 23.pdf16 Jul 2025
Form 2File: 01 Form 2 Sep 23.pdf16 Jul 2025
Form 3File: 01 Form 3 Sep 23.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 01 Sold Unsold Sep 23.pdf16 Jul 2025
Form 1File: 02 Form 1 Dec 23.pdf16 Jul 2025
Form 2File: 02 FOrm 2 Dec 23.pdf16 Jul 2025
Form 3File: 02 Form 3 Dec 23.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 02 Sold unsold Dc23.pdf16 Jul 2025
Form 1File: 03 Frm1 Mar 24.pdf16 Jul 2025
Form 2File: 03 Form 2 Mar 24.pdf16 Jul 2025
Form 3File: 03 Form 3 Mar 24 to be uploaded.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 03 Sold unsold Mar 24.pdf16 Jul 2025
Form 1File: 04 Form 1 June 24.pdf16 Jul 2025
Form 2File: 04 Form 2 June 24.pdf16 Jul 2025
Form 3File: 04 Form 3 June 24.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 04 Sold Unsold June 24.pdf16 Jul 2025
Form 1File: 05 Form 1 Sep 24.pdf16 Jul 2025
Form 2File: 05 Sep 24.pdf16 Jul 2025
Form 3File: 05 Form 3 Sep 24.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 05 Sold Unsold Sep 24.pdf16 Jul 2025
Form 1File: 06 Form 1 Dec 24.pdf16 Jul 2025
Form 2File: 06 FOrm 2 Dec 24.pdf16 Jul 2025
Form 3File: 06 Form 3 Dec24.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 06 Dec 24 sold unsold.pdf16 Jul 2025
Form 1File: 07 Form 1 Mar 25.pdf16 Jul 2025
Form 2File: 07 Mar 25 Form 2.pdf16 Jul 2025
Form 3File: 07 Form 3 Mar 25.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 07 Mar 25 Sold Unsold.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 -Ph1_compressed.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ph1_compressed.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold -Unsold Inventory Ph-1_compressed.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 Ph-1 Form-1 For Q3_compressed.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 Ph-1 Form-3 For Q3_compressed.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Ph-1 Form-2 For Q3_compressed.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: 04 Ph-1 Sold-Unsold Inventory For Q3_compressed.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 FOR FY 23-24_11zon.pdf21 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 FOR FY 23-24_11zon.pdf21 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Q-2_compressed.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Q-2_11zon.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 -Q-2_compressed.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory- Q-2_compressed.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_2_11zon.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_3_11zon.pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: SOLD -UNSLOD SHEET_4_11zon.pdf10 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3_1_11zon.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 Arch CERTIFICATE FOR Q-4 2024-Uploaded.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENG CERTIFICATE FOR Q4-2024-uploaded.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Data-Uploaded.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 CERTIFICATE FOR Q-4 2024_compressed.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Q 4 23-24-(signed)_compressed.pdf2 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3- 14-03-2024.pdf14 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 09 Declaration For Designated Bank Account_compressed Ok.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 23 Compressed_Final.pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 23 Compressed.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 23_11zon.pdf4 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23_11zon.pdf4 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 23 Revised_Signed.pdf4 Feb 2024

Keep Leela by Empyrean Landmarks - Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kharadi, Haveli

Builder: Empyrean Landmarks

Empyrean Landmarks has 2 registrations on MahaRERA, including Leela by Empyrean Landmarks - Phase I and Leela by Empyrean Landmarks Ph2. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if Leela by Empyrean Landmarks - Phase I is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Leela by Empyrean Landmarks - Phase I?

The registered promoter entity is Empyrean Landmarks, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Leela by Empyrean Landmarks - Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Leela by Empyrean Landmarks - Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Leela by Empyrean Landmarks - Phase I?

The professionals named in the filing: Architect: Cubix Architects Associates; Engineer: Bricklane; Engineer: Ravindra Khaire Khaire; Engineer: Sarang Bhaskar; Engineer: Naresh Parulekar; Chartered Accountant: Patel & Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Leela by Empyrean Landmarks - Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Leela by Empyrean Landmarks - Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Leela by Empyrean Landmarks - Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.