Registration lapsed No litigation declared Residential / Group Housing project

Le Jardin

By Jay Construction India

RG-MH-59734 · RERA P51800008046 · Last updated on MahaRERA portal: 12 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 90 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2019Possession promised90 months past this date
7 of 11Construction stages donefurthest along: Slabs of Super Structure, 93%
2Complaints at MahaRERAon this registration
Jump to the 30 documents Report an error

Le Jardin is a Residential / Group Housing project by Jay Construction India in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008046 on 18 Aug 2017. Possession was promised by 30 Apr 2019 and is now 90 months past that date. The completion date has moved by 11 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameLe Jardin
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008046
  • ReraGenie IDRG-MH-59734

Builder

  • NameJay Construction India
  • Entity typePartnership
  • PartnersJayesh Jayantilal Mistry, Jayesh Jayantilal Mistry, Manish Jayantilal Mistry, Manish Jayantilal Mistry, Shushila Jayantilal Mistry, Shushila Jayantilal Mistry

Key dates

90 months past promisethis monthRegisteredAug 2017First promiseMay 2018Revised toApr 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Apr 2019
  • Revised completionRevised to 30 Apr 2019 (originally 18 May 2018)
  • Buildings1 building record
  • Documents filed30 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
La JardinNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 93%.

La Jardin: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure93%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Closed/Covered1
Open Space63

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,938 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5223.77
Proposed, not sanctioned4,660 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChembur Branch Mumbai

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDilip Jayawant & Associates
EngineerMahimtura Consultants pvt ltd
PartnerRole in project
Jay Construction India-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000725May 2018 → Apr 2019

Reason as filed by the promoterNew DP 2034

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000194148Pradeep VohraJay Construction India23/09/2020
CC006000000198921Rajesh SadaranganiJay Construction India02/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Nov 2024

Documents filed30

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2441313_OC_signed.pdf12 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect's certificate 2020.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect's certificate 2022.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect's certificate 2023.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Paresh Kothari Civil Engineer Certificate for 2019.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Paresh Kothari Civil Engineer Certificate for 2021.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Karan Kothari CA Certificate for 2022.pdf20 Jun 2023
Certificates of CA (Form 3)File: Karan Kothari CA Certificate for 2019.pdf20 Jun 2023
Certificates of CA (Form 3)File: Karan Kothari CA Certificate for 2020.pdf20 Jun 2023
Certificates of CA (Form 3)File: Karan Kothari CA Certificate for 2021.pdf20 Jun 2023
Certificates of CA (Form 3)File: Karan Kothari CA Certificate for 2022.pdf20 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Certificate.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect’s Certificate.pdf1 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginner Certificate.pdf1 Oct 2019
Certificates of CA (Form 3)File: Form 3 Auditor Certificate.pdf20 Dec 2018
Certificates of CA (Form 5)File: CARera Certificate.pdf15 Oct 2018
OtherFile: Engineers.pdf15 Oct 2018
Layout approvalFile: Building Plan Approval.pdf31 Jul 2017
Building plan approvalFile: Building Plan Approval.pdf31 Jul 2017
PAN CardFile: PAN Card JCI.pdf31 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf31 Jul 2017
Details of encumbrancesFile: DETAILS OF ENCUMBRANCES.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Building Plan Approval.pdf31 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate.pdf31 Jul 2017
Declaration in FORM BFile: Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Rera Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Rera Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Rera Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Sale AGREEMENT.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 11 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Le Jardin on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmLe JardinCompleted 139Lapsed / revoked 110Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 383 registered projects within 2 km.

Builder: Jay Construction India

Jay Construction India has 1 registration on MahaRERA, including Le Jardin. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Le Jardin shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Le Jardin is delayed beyond 30 Apr 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Le Jardin?

The registered promoter entity is Jay Construction India, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Le Jardin?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Le Jardin?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Le Jardin?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Le Jardin?

The professionals named in the filing: Architect: Dilip Jayawant & Associates; Engineer: Mahimtura Consultants pvt ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Le Jardin?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Le Jardin. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Le Jardin to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.