ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Laxmina Krishna Niwas

Registered No litigation declared Residential / Group Housing project

Laxmina Krishna Niwas

By Laxmina Argentum Realties (India) Private Limited

RG-MH-06243 · RERA P51800052240 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 7 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
24 of 41Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

Laxmina Krishna Niwas is a Residential / Group Housing project by Laxmina Argentum Realties (India) Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800052240 on 2 Aug 2023. Possession is promised by 31 Oct 2026. The completion date has moved by 7 months from the original filing. 17 of the 41 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameLaxmina Krishna Niwas
  • TypeResidential / Group Housing
  • Location
    • Plot No 194
    • Gaothan Road No.3
    • Chembur - East
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800052240
  • ReraGenie IDRG-MH-06243

Builder

  • NameLaxmina Argentum Realties (India) Private Limited
  • Entity typeCompany
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2023First promiseMar 2026Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Aug 2023
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed68 files

Current status

41%17 of 41 units booked
100.0%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Laxmina Krishna NiwasNA131141041

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Laxmina Krishna Niwas: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area864 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Saravanabhava Co-operative Housing Society LimitedDeonarMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2312.15
Proposed, not sanctioned1,538 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGlamcent, GF - 1st Floor, 350, Central Avenue Road, Chembur, Mumbai - 400071
Estimated costRs 8.35 cr
Cost incurredRs 8.35 cr
Work done100.0%
BuildingWingEstimatedIncurred
Laxmina Krishna NiwasNARs 7.93 crRs 7.93 cr
-NARs 41.75 lakhRs 41.75 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeole Bros
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
Laxmina Argentum Realties (India) Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30032620455Mar 2026 → Oct 2026

Reason as filed by the promoterThe application has been submitted for Occupancy Certificate in respect of the project has already been made; however, certain compliance requirements were raised by the Planning Authority, due to which some documents are required to be re-submitted. We are in the process of complying with the said requirements and, upon submission of the requisite compliances, the Planning Authority is expected to issue the Occupancy Certificate within the prescribed statutory timelines. We presently expect to receive the Occupancy Certificate on or before 31/10/2026. We kindly request an extension until 31/1

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Laxmina Krishna Niwas as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 - Laxmina Krishna Niwas as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 - Laxmina Krishna Niwas as on June 2026.pdf16 Jul 2026
Form 5 (FY 2024-2025)File: Form 5 of Laxmina Krishna Niwas - FY 2024-25.pdf6 Jun 2026
Withdrawal Update Form 1File: Form 1 - Laxmina Krishna Niwas as on March 2026.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 - Laxmina Krishna Niwas as on March 2026.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 - Laxmina Krishna Niwas as on March 2026.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 - Laxmina Krishna Niwas as on 31-12-2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - Lamina Krishna Niwas as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - Laxmina Krishna Niwas as on 31-12-2025.pdf20 Jan 2026
Form 1File: Form 1 - Lamina Krishna Niwas as on Sep 2025.pdf16 Oct 2025
Form 2File: Form 2 - Lamina Krishna Niwas as on Sep 2025.pdf16 Oct 2025
Form 3File: Form 3 - Laxmina Krishna Niwas as on 30-09-2025.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Lamina Krishna Niwas as on Sep 2025.pdf16 Oct 2025
Form 1File: Form 1 - Laxmina Krishna Niwas as on June 2025.pdf20 Jul 2025
Form 2File: Form 2 - Laxmina Krishna Niwas as on June 2025.pdf20 Jul 2025
Form 3File: Form 3 - Laxmina Krishna Niwas as on 30-06-2025.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Laxmina Krishna Niwas as on June 2025.pdf20 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on 31-03-2025.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on March 2025.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Laxmina Krishna Niwas as on March 2025.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on Dec 2024.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on Dec 2024.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Laxmina Krishna Niwas as on December 2024.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: Information of Sold Inventory - Laxmina Krishna Niwas.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on Sep 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on Sep 2024.pdf17 Oct 2024
Building plan approvalFile: 11th floor approved plan.pdf14 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC 13-8-24.pdf14 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 11th floor approved plan.pdf14 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Laxmina Krishna Niwas - FY 2023-24.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on June 2024.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on June 2024.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Laxmina Krishna Niwas as on June 2024.pdf4 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SCAN_20240410_170132797.pdf11 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on March 2024.pdf10 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on 31-03-2024.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Laxmina Krishna Niwas as on Dec 2023.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas as on 31-12-2023.pdf16 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: FURTHER CC UPTO 8TH FLOOR.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Laxmina Krishna Niwas as on Dec 2023.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Laxmina Krishna Niwas as on Dec 2023.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Laxmina Krishna Niwas as on 30-09-2023.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Laxmina Krishna Niwas as on 30-09-2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmina Krishna Niwas.pdf19 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf31 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Laxmina-1-9_merged_compressed.pdf19 Jul 2023
Copy of the legal title reportFile: Title Report rera.pdf14 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Jul 2023
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (6) (1).pdf14 Jul 2023
Declaration in FORM BFile: Form B - Promoter.pdf14 Jul 2023
CERSAI detailsFile: Cersai Declaration.pdf14 Jul 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Finance.pdf13 Jul 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Legal.pdf13 Jul 2023
Details of encumbrances concerned to LegalFile: Encumbrance Finance.pdf13 Jul 2023
Details of encumbrances concerned to LegalFile: Encumbrance Legal.pdf13 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf13 Jul 2023
Deviation Report with respect to Allotment letterFile: deviation allotment report.pdf13 Jul 2023
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement (10) (1).pdf13 Jul 2023
Layout approvalFile: Layout Pg 1.pdf29 Jun 2023
Building plan approvalFile: Layout Pg 1.pdf29 Jun 2023
Building plan approvalFile: Layout Pg 2-3.pdf29 Jun 2023
PAN CardFile: Company pan.pdf29 Jun 2023
Copy of Layout Approval (in case of layout)File: Layout Pg 1.pdf29 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout Pg 1.pdf29 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout Pg 2-3.pdf29 Jun 2023
Proforma of Agreement for saleFile: AFS_Laxmi Krishna Niwas_Laxmina Argenitum realties pvt ltd_20072023.pdf29 Jun 2023
Proforma of Allotment letterFile: Allotment Letter-Laxmina Krishna Niwas.pdf29 Jun 2023

How this compares with Mumbai Suburban

41%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 7 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Laxmina Krishna Niwas on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur - East6,700+ in Mumbai Suburban

2 kmLaxmina Krishna NiwasCompleted 163Lapsed / revoked 136Other 166Dot size: filed unitsN

Filed coordinates, straight-line distance. 465 registered projects within 2 km.

Builder: Laxmina Argentum Realties (India) Private Limited

Laxmina Argentum Realties (India) Private Limited has 1 registration on MahaRERA, including Laxmina Krishna Niwas. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Laxmina Krishna Niwas is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Laxmina Krishna Niwas?

The registered promoter entity is Laxmina Argentum Realties (India) Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Laxmina Krishna Niwas?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Laxmina Krishna Niwas?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Laxmina Krishna Niwas?

The professionals named in the filing: Architect: Deole Bros; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Laxmina Krishna Niwas?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Laxmina Krishna Niwas. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Laxmina Krishna Niwas to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.