Home / Browse projects / Kolhapur, Maharashtra / LAXMI CASA

Registered No litigation declared Others project

LAXMI CASA

By MAHESH SOHANLAL JHAWAR

RG-MH-80447 · RERA P53000046625 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 20 months
  • 1 extension taken
  • Rs 4.00 crore secured on the land, in favour of NK enterprises
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 20 months from the original
4 of 11Construction stages donefurthest along: Stilt Floor, 95%
31 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

LAXMI CASA is a Others project by MAHESH SOHANLAL JHAWAR in Kolhapur, Maharashtra, registered with MahaRERA as P53000046625 on 25 Aug 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 20 months from the original filing. 2 of the 33 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameLAXMI CASA
  • TypeOthers
  • Location
    • NARAYAN MALA
    • NEAR DKTE HIGHSCHOOL
    • Ichalkaranji (M Cl)
    • Hatkanangle
    • Kolhapur
    • 416121
  • Pincode416121
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000046625
  • ReraGenie IDRG-MH-80447

Builder

  • NameMAHESH SOHANLAL JHAWAR
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2022First promiseApr 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Aug 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Apr 2025)
  • Buildings1 building record
  • Documents filed83 files

Current status

6%2 of 33 units booked
82.4%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAXMI CASANA7728533

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

LAXMI CASA: 74% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,849 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofNK enterprises
Secured amountRs 4.00 crore
CERSAI search filedYes
Declared on20 Jul 2025

Approvals and building plan

Sanctioning authorityIchalkaranji Municipal Corporation
Permissible FSI4251.84
Proposed, not sanctioned4,252 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMeto House Mahatma Gandhi Road Dhobi Talao Mumbai 400020
Estimated costRs 19.74 cr
Cost incurredRs 16.26 cr
Work done82.4%
BuildingWingEstimatedIncurred
LAXMI CASANARs 17.95 crRs 16.20 cr
-NARs 1.79 crRs 6.43 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhay Pise and Associates
EngineerKrishna Pakhare
Chartered AccountantPRSB and Associates
Chartered AccountantRustgi and Associates
PartnerRole in project
MAHESH SOHANLAL JHAWAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000027953Apr 2025 → Dec 2026

Reason as filed by the promoterOur Construction work of project is going on we completed 50% construction work of Project. Our Project completion date is 30/04/2025 but we are unable to complete the work within stipulated time. Hence we are applied for extension till 31/12/2026 that we can complete entire project and can upload completion certificate too on portal. We humbly request to the authority that please grant us extension till 31/12/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 (2).pdf20 Apr 2026
Withdrawal Update Form 2File: FORM 2 (3).pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3_ C A.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: FORM 2A (7).pdf20 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf13 Jan 2026
Withdrawal Update Form 2File: FORM 2_organized.pdf13 Jan 2026
Withdrawal Update Form 3File: FORM 3_compressed (22).pdf13 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5.pdf28 Oct 2025
Withdrawal Update Form 1File: FORM 1.pdf17 Oct 2025
Withdrawal Update Form 2File: form 2.pdf17 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf17 Oct 2025
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE[1]_compressed.pdf20 Jul 2025
Withdrawal Update Form 2File: ENGINEER CERTIFICATE_compressed (3).pdf20 Jul 2025
Withdrawal Update Form 3File: CA FORM 3_compressed (1).pdf20 Jul 2025
Form 1File: ARCHITECH CERTIFICATE_compressed.pdf18 Jun 2025
Form 2File: ENGINEER CERTIFICATE (2).pdf18 Jun 2025
Form 3File: CA Form 3_compressed.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_compressed.pdf18 Jun 2025
Declaration in FORM BFile: Form B.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold unsold .pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE _compressed.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate_compressed (1).pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_compressed.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_compressed.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_compressed.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE[1]_compressed.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM - 5_compressed.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 final.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_CERTIFICATE_.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf2 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_compressed (1).pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF iNVENTORY.pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE_OF_UNSOLD_INVENTORY_compressed.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (8).pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (4).pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE DEC 2023.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar Qtr_compressed.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June_compressed (1).pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 march.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 june.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory sep_compressed.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: sold unsold march.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: sold unsold june.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration form sep 2023.pdf13 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration form sep 2023.pdf13 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Sep_compressed.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certif_compressed.pdf7 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineer Certificate_compressed.pdf7 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_CA Certificate_compressed.pdf7 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_CA certificate_compressed.pdf7 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Laxmi Casa compress.pdf19 Nov 2022
Disclosure of sold/ booked inventoryFile: Sold unsold inventary-Laxmi casa compress.pdf19 Nov 2022
Building plan approvalFile: Final Sanctioned Plan.pdf3 Aug 2022
Building plan approvalFile: Declaration on sanctioned Plan.pdf3 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Final Sanctioned Plan.pdf3 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Declaration on sanctioned Plan.pdf3 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf3 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank account Declaration - RERA.pdf3 Aug 2022
Details of encumbrances concerned to FinanceFile: Encumbrance concerned to Finance.pdf12 Jul 2022
Details of encumbrances concerned to LegalFile: Encumbrances Concerned to Legal.pdf12 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf12 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200239978936_For_Asset_Based_Search_17_06_2022_15_47_44_969.pdf12 Jul 2022
Proforma of Allotment letterFile: Agreement to Sell.pdf12 Jul 2022
Proforma of Allotment letterFile: Allotment Letter.pdf12 Jul 2022
Deviation Report with respect to Allotment letterFile: No Deviation - Allotment Letter.pdf12 Jul 2022
Deviation Report with respect to model copy of AgreementFile: No Deviation - Agreement to Sell.pdf12 Jul 2022
Layout approvalFile: Layout Plan approval.pdf16 Jun 2022
PAN CardFile: Pan Card.pdf16 Jun 2022
Copy of the legal title reportFile: Legal Title Report Final.pdf16 Jun 2022
Copy of the legal title reportFile: Search Report.pdf16 Jun 2022
Copy of Layout Approval (in case of layout)File: Layout Plan approval.pdf16 Jun 2022
Declaration about Commencement CertificateFile: Declaration about CC.pdf16 Jun 2022

How this compares with Kolhapur

6%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 20 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep LAXMI CASA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR DKTE HIGHSCHOOL880+ in Kolhapur

2 kmLAXMI CASACompleted 3Lapsed / revoked 2Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: MAHESH SOHANLAL JHAWAR

MAHESH SOHANLAL JHAWAR has 1 registration on MahaRERA, including LAXMI CASA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if LAXMI CASA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAXMI CASA?

The registered promoter entity is MAHESH SOHANLAL JHAWAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAXMI CASA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAXMI CASA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAXMI CASA?

The professionals named in the filing: Architect: Abhay Pise and Associates; Engineer: Krishna Pakhare; Chartered Accountant: PRSB and Associates; Chartered Accountant: Rustgi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAXMI CASA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAXMI CASA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAXMI CASA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.