ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / LA MAISON 18/34

Registered No litigation declared Others project

LA MAISON 18/34

By Jyot Niranjan Jadhav

RG-MH-15469 · RERA P51500050155 · Last updated on MahaRERA portal: 6 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

LA MAISON 18/34 is a Others project by Jyot Niranjan Jadhav in Aurangabad, Maharashtra, registered with MahaRERA as P51500050155 on 21 Mar 2023. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameLA MAISON 18/34
  • TypeOthers
  • Location
    • CIDCO N-3
    • NEAR JAIN MANDIR
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431003
  • Pincode431003
  • RERA no.P51500050155
  • ReraGenie IDRG-MH-15469

Builder

  • NameJyot Niranjan Jadhav
  • Entity typeIndividual

Key dates

this monthRegisteredMar 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Mar 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LA MAISON 18/34NA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

LA MAISON 18/34: 47% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 6 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Open Space28

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,350 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6660.25
Proposed, not sanctioned1,325 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAURANGABAD

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Jyot Niranjan Jadhav-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 Form-1 June 25.pdf6 Dec 2025
Form 2File: 2 Form-2 June 25.pdf6 Dec 2025
Form 3File: 3 Form-3 June 25.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: 4 Sold June 25.pdf6 Dec 2025
Form 1File: 1 Form-1 Sep 25.pdf6 Dec 2025
Form 2File: 2 Form-2 Sep 25.pdf6 Dec 2025
Form 3File: 3 Form-3 Sep 25.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: 4 Sold Sep 25.pdf6 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Form 3 Dec 24.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Form 3 Mar 25.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: 9 Sold Dec 24.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: 11 Sold Mar 25.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 Dec 24.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 March 25.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form-2 Dec 24.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form- 2 March 25.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 Jun 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form-1 Sep 24.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Form-2 Jun 24.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form-2 Sep 24.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: La Maison Form 3 June.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: La Maison Form 3 sep.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: La Maison Form-1 14-April-24 (1).pdf29 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: La Maison Form-2 14-April-24 (1).pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: La Maison Form-2A 10-April-24 (1).pdf29 May 2024
Disclosure of sold/ booked inventoryFile: La Maison Sold 30-Sep-23 (1).pdf29 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: La Maison Form-3 15-April-24 (1).pdf29 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: La Maison Form 1 Dec-23.pdf9 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CCI_000110.pdf4 Jan 2024
Disclosure of sold/ booked inventoryFile: La Maison - Sold-Unsold (Dec-2023).pdf3 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: La Maison -Self Declarition (Dec-2023).pdf3 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 ( 12-04-2023 ).pdf2 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 ( 15-07-2023 ).pdf2 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 ( 05-10-2023 ).pdf2 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MARCH-23_ENG.pdf2 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUNE_ENG.pdf2 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEPT_ENG.pdf2 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM_2A.pdf2 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold ( March-2023 ).pdf10 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold ( June-2023 ).pdf10 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold ( September-2023 ).pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration ( March-2023 ).pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration ( June-2023 ).pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration ( September-2023 ).pdf10 Oct 2023
Layout approvalFile: JADHAV PLAN.pdf27 Jan 2023
Building plan approvalFile: JADHAV PLAN.pdf27 Jan 2023
PAN CardFile: Jyot Jadhav PAN.pdf27 Jan 2023
Copy of the legal title reportFile: Legal Title Report RERA.pdf27 Jan 2023
Details of encumbrances concerned to FinanceFile: NO ENC - FIN - Signed (1).pdf27 Jan 2023
Details of encumbrances concerned to FinanceFile: NO ENC - LEGAL - Signed (1).pdf27 Jan 2023
Details of encumbrances concerned to LegalFile: NO ENC - FIN - Signed (1).pdf27 Jan 2023
Details of encumbrances concerned to LegalFile: NO ENC - LEGAL - Signed (1).pdf27 Jan 2023
Copy of Layout Approval (in case of layout)File: JADHAV PLAN.pdf27 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: JADHAV PLAN.pdf27 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: CIDCO Revised Construction Permission Commencement Certificate.pdf27 Jan 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCMENT CERITIFICATE - Signed (1).pdf27 Jan 2023
Declaration in FORM BFile: Form B.pdf27 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200258796730_For_Asset_Based_Search_27_01_2023_17_11_01_017.pdf27 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: La Masion Form 3.pdf27 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure - Signed.pdf27 Jan 2023
Proforma of Allotment letterFile: Allotment_compressed.pdf27 Jan 2023
Proforma of Agreement for saleFile: ATS RERA.pdf27 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 'A' - Separate Bank Account for Real Estate Projects - Signed (1).pdf27 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment - Signed (1).pdf27 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report ATS - Signed (1).pdf27 Jan 2023

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep LA MAISON 18/34 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR JAIN MANDIR1,400+ in Aurangabad

Builder: Jyot Niranjan Jadhav

Jyot Niranjan Jadhav has 1 registration on MahaRERA, including LA MAISON 18/34. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if LA MAISON 18/34 is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LA MAISON 18/34?

The registered promoter entity is Jyot Niranjan Jadhav, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LA MAISON 18/34?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LA MAISON 18/34?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in LA MAISON 18/34?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LA MAISON 18/34. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LA MAISON 18/34 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.