KUBER HEIGHTS

By SHREEJI INFRA GROUP

RG-MH-55285 · RERA P51700047224 · Last updated on MahaRERA portal: 8 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
7 of 11Construction stages donefurthest along: Installation of Lifts, 95%
26 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

KUBER HEIGHTS is a Residential / Group Housing project by SHREEJI INFRA GROUP in Thane, Maharashtra, registered with MahaRERA as P51700047224 on 12 Oct 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 8 of the 34 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameKUBER HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • MANGAON
    • DOMBIVALI
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700047224
  • ReraGenie IDRG-MH-55285

Builder

  • NameSHREEJI INFRA GROUP
  • Entity typePartnership
  • PartnersVATSAL DHIRAJ PATEL, DHIRAJ PREMJIBHAI PATEL, SANTOSH KUBER MANE

Key dates

this monthRegisteredOct 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Oct 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed99 files

Current status

24%8 of 34 units booked
66.5%Work done, per cost certificate

Figures as on 8 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KUBER HEIGHTSNA7728634

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

KUBER HEIGHTS: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes55%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Open Space35

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jan 2026
LandownerVillageDistrict
MAHENDRA M BHOIRMangaonThane

Approvals and building plan

Sanctioning authorityMumbai Metropolitan Region Development Authority
Permissible FSI1522.67
Proposed, not sanctioned1,523 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNILJE RURAL 421204
Estimated costRs 3.50 cr
Cost incurredRs 2.33 cr
Work done66.51%
BuildingWingEstimatedIncurred
KUBER HEIGHTSNARs 3.00 crRs 2.33 cr
-NARs 50.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG N Gandhe
EngineerRajesh Thakare
Chartered AccountantKartik Patel
Chartered AccountantCA Velani and Pokar RAMESH POKAR
PartnerRole in project
SHREEJI INFRA GROUP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700026056Dec 2024 → Dec 2025

Reason as filed by the promoter• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We would like to inform you that due to a change in the project plan and an increase in the construction area, it became necessary to obtain approval from the local authorities, which resulted in a considerable time lapse. The revised plan has also necessitated modifications to the construction activities, leading to additional time requirements. Consequently, the delay in obtaining approvals and the subsequent changes in cons

EA27012619585Dec 2024 → Dec 2026

Reason as filed by the promotera) During the pandemic years, the industry faced severe supply chain disruptions, labour shortages, liquidity constraints, and slowdown in construction activities, which adversely affected the project timeline. b) Due to a change in the project plan and an increase in the construction area, it became necessary to obtain revised approvals from the local authorities. The approval process consumed considerable time, and the revised plan also required modifications in construction methodology, resulting in further delay in execution. c) The project has progressed substantially, with approximately

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf8 Jul 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf8 Jul 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Uploaded.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 31032026 Signed.pdf6 Jul 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Signed.pdf6 Jul 2026
Withdrawal Update Form 2File: Form 2 31032026.pdf6 Jul 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 Signed.pdf6 Jul 2026
Withdrawal Update Form 3File: Form 3 31032026 - Signed.pdf6 Jul 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 Uploaded.pdf6 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf17 Jun 2026
Form 5 (FY 2025-2026)File: Form 5 25-26_.pdf16 Jun 2026
Form 1File: Architect Certificate _11zon.pdf27 May 2026
Form 2File: Form 2 30092024.pdf27 May 2026
Form 3File: Form 3_compressed.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 30062024.pdf27 May 2026
Form 1File: Architect Certificate _11zon.pdf27 May 2026
Form 2File: Form 2 30092024.pdf27 May 2026
Form 3File: Form 3_compressed.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 30092024.pdf27 May 2026
Form 1File: Form 1.pdf27 May 2026
Form 2File: Form 2.pdf27 May 2026
Form 3File: Form 3 ScannedCompressed.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 31122024.pdf27 May 2026
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf28 Jan 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf28 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf28 Jan 2026
Form 1File: Form 1.pdf21 Jan 2026
Form 2File: mane mangaon 30 sep 2025.pdf21 Jan 2026
Form 3File: Form 3 30092025_11zon.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 30092025.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 31122025.pdf21 Jan 2026
Form 1File: Form 1 31122025 Architect Certificate.pdf21 Jan 2026
Form 2File: Form 2 31122025.pdf21 Jan 2026
Form 3File: Form 3 31122025_11zon.pdf21 Jan 2026
Form 5 (FY 2024-2025)File: Form 5_24_25.pdf30 Sep 2025
Form 5 (FY 2023-2024)File: Form 5.pdf30 Sep 2025
Form 5 (FY 2022-2023)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf30 Sep 2025
Form 1File: Form 1.pdf16 Jul 2025
Form 2File: Form 2.pdf16 Jul 2025
Form 3File: Form 3 ScannedCompressed.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 31_03_2025.pdf16 Jul 2025
Form 1File: Form 1 Final.pdf16 Jul 2025
Form 2File: Form 2 Final.pdf16 Jul 2025
Form 3File: Form 3 Scanned 30062025 Compressed.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure 30062025.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 2024.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 2024.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) September 2024.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) December 2024.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 2025.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2) September 2024.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2) December 2024.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2) MArch 2025.pdf1 May 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_Kuber Heights.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure 31_03_2025.pdf28 Apr 2025
Other - TechnicalFile: PERT Chart.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_31_12_24.pdf15 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf15 Apr 2025
Declaration in FORM BFile: Form B Rera Update .pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate _11zon.pdf4 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf4 Jan 2025
Building plan approvalFile: HPSCANNER2344.pdf3 May 2024
Building plan approvalFile: HPSCANNER2345.pdf3 May 2024
Building plan approvalFile: HPSCANNER2346.pdf3 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2344.pdf3 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2345.pdf3 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2346.pdf3 May 2024
Commencement Certificates / NA Order for plotted developmentFile: S041000390_2404231313000.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Certificate 31_03_23.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf6 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf6 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE March 23.pdf30 Mar 2023
Proforma of Allotment letterFile: SALE AGREEMENT FOR RERA Part 1.pdf22 Sep 2022
Proforma of Allotment letterFile: SALE AGREEMENT FOR RERA Part 2.pdf22 Sep 2022

How this compares with Thane

24%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KUBER HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVALI7,600+ in Thane

Builder: SHREEJI INFRA GROUP

SHREEJI INFRA GROUP has 1 registration on MahaRERA, including KUBER HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if KUBER HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KUBER HEIGHTS?

The registered promoter entity is SHREEJI INFRA GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KUBER HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KUBER HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KUBER HEIGHTS?

The professionals named in the filing: Architect: G N Gandhe; Engineer: Rajesh Thakare; Chartered Accountant: Kartik Patel; Chartered Accountant: CA Velani and Pokar RAMESH POKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KUBER HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KUBER HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KUBER HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.