ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / KRISHNA KUNJ

Registered No litigation declared Residential / Group Housing project

KRISHNA KUNJ

By SHANTI CONSTRUCTION

RG-MH-41261 · RERA P52100048469 · Last updated on MahaRERA portal: 26 Nov 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
11 of 11Construction stages doneevery applicable stage filed complete
0 of 38Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

KRISHNA KUNJ is a Residential / Group Housing project by SHANTI CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100048469 on 3 Jan 2023. Possession is promised by 31 Dec 2027. 38 of the 38 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA KUNJ
  • TypeResidential / Group Housing
  • Location
    • ADARSHNAGAR ROAD
    • CHNADRABHAGA CORNER SANTOSH DREAM SOCIETY
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048469
  • ReraGenie IDRG-MH-41261

Builder

  • NameSHANTI CONSTRUCTION
  • Entity typePartnership
  • PartnerHAMBIRRAO GULABRAO AWATE
  • PartnerAVINASH GULABRAO AWATE
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredJan 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed64 files

Current status

100%38 of 38 units booked

Figures as on 26 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRISHNA KUNJNA6632638

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

KRISHNA KUNJ: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,079 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jun 2025
LandownerVillageDistrict
SHANTI CONSTRUCTIONPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI3993.0
Proposed, not sanctioned3,993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHETTY COMPLEX SAMBHAJI NAGAR CHINCHWAD MIDC PCMC PUNE

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHIRAJ TAKKEKAR
EngineerPRAVIN GIRI BUWA
EngineerRATHI GROUP
Chartered AccountantSAURABH P MAHAGAONKAR
Chartered AccountantPGMJ & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
SHANTI CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf26 Nov 2025
Form 1File: FORM 1_compressed.pdf17 Jul 2025
Form 2File: Form 2.pdf17 Jul 2025
Form 3File: Form Final.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 May 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final_compressed.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf25 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf25 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf31 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MR AWATE SIR.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 UPLOAD.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2nd Engineer Certificate of Shanti Construction (Krishnakunj) (30-09-2024).pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Cellular Form.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular 31032024.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular 30062024.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Signed PS_compressed.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Signed PS_compressed.pdf8 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form.pdf31 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form.pdf31 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Certificate.pdf31 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Record_Krishnakunj_220923.pdf31 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Record_Krishnakunj_220923.pdf31 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE .pdf31 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Cert_Krishnakunj_220923.pdf28 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Record_Krishnakunj_220923.pdf28 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf28 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_Krishnakunj.pdf28 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MR AWATE FORM 1.pdf27 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Record Krishnakunj 220923.pdf27 Sep 2023
Deviation Report with respect to Allotment letterFile: declaration on deviation in allotment letter.pdf24 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 17102022_compressed.pdf17 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 41022_compressed.pdf4 Oct 2022
CERSAI detailsFile: CERSAI NEW.pdf28 Sep 2022
CERSAI detailsFile: CERSAI NEW.pdf28 Sep 2022
Declaration in FORM BFile: Form B Affidavit.pdf21 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank Details.pdf21 Sep 2022
Copy of the legal title reportFile: compressed search result 1.pdf6 Sep 2022
Details of encumbrances concerned to FinanceFile: declaration of encumberance on project property financial.pdf6 Sep 2022
Details of encumbrances concerned to LegalFile: Encumbarance Certificate by Builder LEGAL.pdf6 Sep 2022
Declaration about Commencement CertificateFile: declaration commencement certificate (1).pdf6 Sep 2022
Proforma of Agreement for saleFile: Agreement - Draft Performa.pdf6 Sep 2022
Proforma of Allotment letterFile: Allottment Letter Proforma.pdf6 Sep 2022
Deviation Report with respect to model copy of AgreementFile: deviation allotment.pdf6 Sep 2022
Layout approvalFile: Layout 1.pdf5 Sep 2022
Layout approvalFile: Layout 2.pdf5 Sep 2022
Layout approvalFile: Sanction Plan.pdf5 Sep 2022
Building plan approvalFile: NA ORDER.pdf5 Sep 2022
PAN CardFile: PAN SHANTI CONSTRUCTION.pdf5 Sep 2022
Copy of Layout Approval (in case of layout)File: Layout 1.pdf5 Sep 2022
Copy of Layout Approval (in case of layout)File: Layout 2.pdf5 Sep 2022
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf5 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf5 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf5 Sep 2022

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNA KUNJ on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHNADRABHAGA CORNER SANTOSH DREAM SOCIETY13,700+ in Pune

2 kmKRISHNA KUNJCompleted 65Lapsed / revoked 35Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 227 registered projects within 2 km.

Builder: SHANTI CONSTRUCTION

SHANTI CONSTRUCTION has 3 registrations on MahaRERA, including FINESSIA 4TH FLOOR TO 9TH FLOOR and Heritage Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KRISHNA KUNJ is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNA KUNJ?

The registered promoter entity is SHANTI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNA KUNJ?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRISHNA KUNJ?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNA KUNJ?

The professionals named in the filing: Architect: DHIRAJ TAKKEKAR; Engineer: PRAVIN GIRI BUWA; Engineer: RATHI GROUP; Chartered Accountant: SAURABH P MAHAGAONKAR; Chartered Accountant: PGMJ & ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA KUNJ?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA KUNJ. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA KUNJ to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.