ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / KIRAN SANSKRITI

Completed No litigation declared Residential / Group Housing project

KIRAN SANSKRITI

By M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE

RG-MH-15402 · RERA P52100023835 · Last updated on MahaRERA portal: 8 Feb 2024

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

KIRAN SANSKRITI is a Residential / Group Housing project by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE in Pune, Maharashtra, registered with MahaRERA as P52100023835 on 7 Jan 2020. The registration is recorded completed; possession was promised by 30 Jun 2023.

At a glance

Project

  • NameKIRAN SANSKRITI
  • TypeResidential / Group Housing
  • Location
    • SUS
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100023835
  • ReraGenie IDRG-MH-15402

Builder

  • NameM/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE
  • Entity typeIndividual
  • Other registrations10 more →
  • Completed10 of 11
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredJan 2020PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Jan 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KIRAN SANSKRITINA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

KIRAN SANSKRITI: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,782 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3052.45
Proposed, not sanctioned1,552 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRASTA PETH PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArckitude Studio
EngineerManoj Bhosale
Chartered AccountantA M Sadavarte & Co
PartnerRole in project
M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017821Jun 2023 → Oct 2023

Reason as filed by the promoterWe have received completion certificate dated 15/09/2023. We want to apply for Extension till completion.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Sep 2023

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Kiran Sanskriti Soc Reg Certificate.pdf8 Feb 2024
Other - TechnicalFile: 1 Architect’s Certificate on Completion of Project (Form 4).pdf17 Jan 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form -4 -Sanskriti.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Kiran Sanskriti-Sept 23.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A -Kiran Sanskriti-Sept 23.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Kiran Sanskriti- June 23.pdf13 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kiran Sanskriti- Complition Certifcate.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: Kiran Sanskriti-Sold Unsold -30-6-2023.pdf15 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Kiran Sanskriti- March 22.pdf5 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Kiran Sanskriti- Dec 2022.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold - Kiran Sanskriti - Sept 2022.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold -Kiran Sanskriti- Dec 2022.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold -Kiran Sanskriti March 2023.pdf5 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kiran Sanskriti.pdf22 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assiurance Kiran Sanskriti_compressed.pdf22 Jul 2022
Disclosure of sold/ booked inventoryFile: Kiran Sanskriti Sold-unsold_compressed.pdf22 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Sanskrit- Quality_compressed.pdf23 Apr 2022
Disclosure of sold/ booked inventoryFile: Kiran Sanskriti -Sold-unsold_compressed.pdf23 Apr 2022
Layout approvalFile: Revised Plan 1.pdf29 Mar 2022
Building plan approvalFile: Revised Plan 2.pdf29 Mar 2022
Copy of Layout Approval (in case of layout)File: Revised Plan 1.pdf29 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan 2.pdf29 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf29 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form I - (Kiran Sanskriti).pdf8 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Sanskriti- Form 2A -Quality Assurance_compressed.pdf8 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A - Sanskriti.pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold- Unsold- Sanskriti.pdf13 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I - Kiran Sanskriti_compressed.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sanskriti-Form 2 A.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: Kiran Sanskriti-Sold -Unsold_compressed.pdf15 Aug 2021
Proforma of Allotment letterFile: Agreement to sell Kiran Sankruti revised - Copy.pdf2 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Sanskriti Form 1_compressed.pdf19 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Sanskriti - Arc Certifciate.pdf22 Oct 2020
Proforma of Allotment letterFile: ALLOTMENT LETTER (1).pdf3 Jan 2020
Layout approvalFile: PROPOSED PLAN.pdf1 Jan 2020
Copy of Layout Approval (in case of layout)File: PROPOSED PLAN.pdf1 Jan 2020
Proforma of Allotment letterFile: revised -rera - FINAL AGREEMENT -.pdf1 Jan 2020
Building plan approvalFile: NA.pdf31 Dec 2019
Copy of the legal title reportFile: Search report -87.pdf31 Dec 2019
Copy of the legal title reportFile: Search Report-128.pdf31 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: NA.pdf31 Dec 2019
Declaration in FORM BFile: Declaration_compressed.pdf31 Dec 2019
Details of encumbrancesFile: Encumbrance Certificate.pdf30 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Certifciate -27-12-19.pdf30 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certifcate -27-12-19.pdf30 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert- Sanskriti.pdf30 Dec 2019
Layout approvalFile: PLAN_compressed (1).pdf27 Dec 2019
PAN CardFile: PAN CARD.pdf27 Dec 2019
Copy of Layout Approval (in case of layout)File: PLAN_compressed (1).pdf27 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Dec 2019

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Kiran ShubhlabhMohan Nagar soc Baner Pune 4110458CompletedMay 2015Late, Aug 2015
Kiran Silver DewS no 52 Part Susgaon Pune20CompletedJan 2015Late, Mar 2015
Kiran SphurteePart of S no 47 A Susgaon Pune 4110458CompletedSep 2014Late, Nov 2014
Kiran ShubhshreeMohan nagar soc Baner Pune 4110458CompletedMay 2014Late, Jun 2014
Kiran SolitaireS no 278 Part Susgaon Pune 41104532CompletedJan 2014Late, May 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KIRAN SANSKRITI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SUS13,700+ in Pune

Builder: M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE

M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE has 11 registrations on MahaRERA, including Kiran Sanklp and Kiran Suyog. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KIRAN SANSKRITI is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KIRAN SANSKRITI?

The registered promoter entity is M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KIRAN SANSKRITI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KIRAN SANSKRITI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KIRAN SANSKRITI?

The professionals named in the filing: Architect: Arckitude Studio; Engineer: Manoj Bhosale; Chartered Accountant: A M Sadavarte & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KIRAN SANSKRITI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KIRAN SANSKRITI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KIRAN SANSKRITI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one