Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KIRAN SAMRUDDHI B is a Residential / Group Housing project by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE in Pune, Maharashtra, registered with MahaRERA as P52100029302 on 18 May 2021. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 68 of the 71 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameKIRAN SAMRUDDHI B
- TypeResidential / Group Housing
- Location
- SUS
- Mulshi
- Pune
- 411021
- Pincode411021
- RERA no.P52100029302
- ReraGenie IDRG-MH-17495
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 May 2021
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2023)
- Buildings1 building record
- Documents filed65 files
Current status
Figures as on 24 Feb 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KIRAN SAMRUDDHI B | NA | 9 | 9 | 71 | 0 | 71 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
KIRAN SAMRUDDHI B: 70% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 24 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| THE ALLIANCE AURO DEVELOPERS | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCKITUDESTUDIO RUPESH JA |
| Engineer | MANOJ BHASALE |
| Engineer | MOHIT BASAPPA ABBIGERI |
| Chartered Accountant | A M SADAVARTE & CO |
| Partner | Role in project |
|---|---|
| M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterConstruction of the said project is not yet completed because of delayed in revised sanction.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502891 | SARIKA PRASHANT POWAR | M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE | 18/08/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 May 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 KIRAN SAMRUDDHI B.pdf | 24 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 KIRAN SAMRUDDHI B.pdf | 24 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B Form 1.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Kiran Samruddhi B Sold Unsold.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Kiran Samruddhi.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Kiran Samruddhi B Inventory.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B - Form 1 Dec 2023.pdf | 5 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1-Kiran Samruddhi B -31-3-2024.pdf | 5 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Form -1-Kiran Samruddhi B -31-3-2024.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kiran Samruddhi - Form 3_compressed.pdf | 14 Feb 2024 |
| Layout approvalFile: Layout B-20-01-23 (1)_compressed.pdf | 2 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: Layout B-20-01-23 (1)_compressed.pdf | 2 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Kiran Samruddhi B -Revised CC 20-01-2023 (1)_compressed.pdf | 2 Feb 2024 |
| Declaration about Commencement CertificateFile: Kiran Samruddhi B - CC Delcaration.pdf | 2 Feb 2024 |
| Declaration about Commencement CertificateFile: Kiran Samruddhi B -Revised CC 20-01-2023 (1)_compressed.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B- Form -1-31-03-22.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B -Form 1-30-9-22.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B- Form -31-12-22.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B -Form 1-31-3-23.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B-Form-1 -30-6-23.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B - Form 1-30-9-23.pdf | 2 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kiran Samruddhi B - form-5-2022.pdf | 2 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kiran Samruddhi B - From-5-2023.pdf | 2 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold-Samruddhi B 31-12-23 (1).pdf | 11 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Samruddhi B -31-12-23.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold -Unsold- Kiran Samruddhi B -Sept-23.pdf | 17 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Kiran Samruddhi B -Sept 23.pdf | 13 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Kiran Samruddhi B -Sept 23.pdf | 13 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Kiran Samruddhi B -Quality Assurance -30-06-2023.pdf | 15 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Kiran Samruddhi B -Sold Unsold - 30-06-2023.pdf | 15 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Kiran Samruddhi B June2022.pdf | 5 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B - Form 1 Dec 2022.pdf | 5 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A - Kiran Samruddhi B March 2023.pdf | 5 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold- Kiran Samruddhi B - Sept 2022.pdf | 5 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold - Kiran Samruddhi B - Dec 2022.pdf | 5 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold - Kiran Samruddhi B March 2023.pdf | 5 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kiran Samruddhi B.pdf | 22 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A Quality Kiran samruddhi B compressed.pdf | 22 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Kiran Samruddhi B Sold unsold compressed.pdf | 22 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi B ARCHIT.pdf | 23 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Samruddhi B- Quality _compressed.pdf | 23 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Kiran Samruddhi B-Sold-Unsold_compressed (1).pdf | 23 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Samruddhi B- Sold -Unsold 31-12-21.pdf | 28 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 (Kiran Samruddhi B).pdf | 8 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Samruddhi B -Form 2A -Quality Ass_compressed.pdf | 8 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 Samruddhi B.pdf | 13 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A- Samruddhi B.pdf | 13 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold- Samruddhi B.pdf | 13 Oct 2021 |
| Copy of the legal title reportFile: Search Report 1-10.pdf | 10 May 2021 |
| Copy of the legal title reportFile: Search Report 11-20.pdf | 10 May 2021 |
| Declaration in FORM BFile: Promoter Declaration.pdf | 10 May 2021 |
| Layout approvalFile: Layout.pdf | 5 May 2021 |
| Building plan approvalFile: Plan 1.pdf | 5 May 2021 |
| Building plan approvalFile: Plan 2.pdf | 5 May 2021 |
| PAN CardFile: PAN.pdf | 5 May 2021 |
| Details of encumbrancesFile: No -Enc.pdf | 5 May 2021 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 5 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf | 5 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf | 5 May 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC (1)_compressed.pdf | 5 May 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (2)_compressed.pdf | 5 May 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certifcate.pdf | 5 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA (1).pdf | 5 May 2021 |
| Proforma of Allotment letterFile: AGREEMENT DRAFT.pdf | 5 May 2021 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 5 May 2021 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kiran Shubhlabh | Mohan Nagar soc Baner Pune 411045 | 8 | Completed | May 2015 | Late, Aug 2015 |
| Kiran Silver Dew | S no 52 Part Susgaon Pune | 20 | Completed | Jan 2015 | Late, Mar 2015 |
| Kiran Sphurtee | Part of S no 47 A Susgaon Pune 411045 | 8 | Completed | Sep 2014 | Late, Nov 2014 |
| Kiran Shubhshree | Mohan nagar soc Baner Pune 411045 | 8 | Completed | May 2014 | Late, Jun 2014 |
| Kiran Solitaire | S no 278 Part Susgaon Pune 411045 | 32 | Completed | Jan 2014 | Late, May 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 10 other registrations, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep KIRAN SAMRUDDHI B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SUS13,700+ in Pune
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE
M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE has 11 registrations on MahaRERA, including Kiran Sanklp and Kiran Suyog. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that KIRAN SAMRUDDHI B shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KIRAN SAMRUDDHI B is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KIRAN SAMRUDDHI B?
The registered promoter entity is M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KIRAN SAMRUDDHI B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KIRAN SAMRUDDHI B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KIRAN SAMRUDDHI B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KIRAN SAMRUDDHI B?
The professionals named in the filing: Architect: ARCKITUDESTUDIO RUPESH JA; Engineer: MANOJ BHASALE; Engineer: MOHIT BASAPPA ABBIGERI; Chartered Accountant: A M SADAVARTE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KIRAN SAMRUDDHI B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback