ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Kiran Samruddhi A

Completed No litigation declared Residential / Group Housing project

Kiran Samruddhi A

By M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE

RG-MH-15927 · RERA P52100024539 · Last updated on MahaRERA portal: 8 Feb 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 10 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Kiran Samruddhi A is a Residential / Group Housing project by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE in Pune, Maharashtra, registered with MahaRERA as P52100024539 on 18 Feb 2020. The registration is recorded completed; possession was promised by 30 Dec 2023.

At a glance

Project

  • NameKiran Samruddhi A
  • TypeResidential / Group Housing
  • Location
    • SUS
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100024539
  • ReraGenie IDRG-MH-15927

Builder

  • NameM/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE
  • Entity typeIndividual
  • Other registrations10 more →
  • Completed10 of 11
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredFeb 2020PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Feb 2020
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kiran Samruddhi ANA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Kiran Samruddhi A: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered49

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,212 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s. THE ALLIANCE AERO DEVELOPERSSusPune

Approvals and building plan

Permissible FSI3192.69
Proposed, not sanctioned2,193 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAPTE ROAD, DECCAN GYMKHANA, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCKITUDESTUDIO
EngineerMANOJ BHASALE
Chartered AccountantA M SADAVARTE & CO
PartnerRole in project
M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Sep 2023

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Kiran Samruddhi A- Soc Reg Certificate.pdf8 Feb 2024
Disclosure of sold/ booked inventoryFile: Slod-Unsold- Samruddhi A 31-12-23 (1).pdf11 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold-Kiran Samruddhi A-Sept 23.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Kiran Samruddhi A-Sept 23.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Kiran Samruddhi A- Sept23.pdf13 Oct 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4-Kiran Samruddhi A.pdf13 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kiran Samrudhhi A- Complition Certificate.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kiran Samruddhi A June 2022.pdf5 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kiran Samruddhi A Dec 2022.pdf5 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Kiran Samruddhi A Dec 2022.pdf5 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Kiran Samruddhi A March 2023.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold - Kiran Samruddhi A - Sept 2022.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold - Kiran Samruddhi A - Dec 2022.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold -Kiran Samruddhi A - March 2023.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold -Kiran Samruddhi A- March 2023.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Kiran Samruddhi A -Sept 22.pdf21 Mar 2023
Disclosure of sold/ booked inventoryFile: Kiran Samruddhi A- Dec 22.pdf21 Mar 2023
Declaration about Commencement CertificateFile: CC Declarauion - Kiran Samruddhi A .pdf15 Aug 2022
Layout approvalFile: 1.pdf6 Aug 2022
Building plan approvalFile: 2.pdf6 Aug 2022
Building plan approvalFile: 3.pdf6 Aug 2022
Copy of Layout Approval (in case of layout)File: 1.pdf6 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf6 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf6 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: New CC-14-7-2022.pdf6 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kiran Samruddhi A.pdf22 Jul 2022
Disclosure of sold/ booked inventoryFile: Kiran Samruddhi A Sold-unsold_compressed.pdf22 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Form 2A -Kiran Samruddhi A_compressed.pdf16 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi A Engineer Certificates.pdf23 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Samruddhi A - Quality _compressed.pdf23 Apr 2022
Disclosure of sold/ booked inventoryFile: Kiran Samruddhi A -Sold-unsold_compressed.pdf23 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 Kiran samruddhi A.pdf8 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kiran Samruddhi A - Form 2 A.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: Samruddhi A- Sold -Unsold 31-12-21.pdf8 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form1.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A- Samruddhi A.pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold- Unsold- Samruddhi A.pdf13 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I - Kiran Samruddhi A_compressed.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Samruddhi A- Form 2 A.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: Kiran Samruddhi A -Sold Unsold _compressed (1).pdf15 Aug 2021
Proforma of Allotment letterFile: Samruddhi A - Draft.pdf2 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi Form 1.pdf19 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kiran Samruddhi - Arc Certificate_compressed.pdf22 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certifcate.pdf8 Feb 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf8 Feb 2020
Layout approvalFile: Layout Plan_compressed.pdf5 Feb 2020
Building plan approvalFile: Area Key Plan_compressed.pdf5 Feb 2020
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed.pdf5 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: Area Key Plan_compressed.pdf5 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf5 Feb 2020
PAN CardFile: PAN CARD.pdf4 Feb 2020
Copy of the legal title reportFile: Search Report.pdf4 Feb 2020
Details of encumbrancesFile: Encumbrance.pdf4 Feb 2020
Declaration in FORM BFile: Declration- nehete_compressed.pdf4 Feb 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Certificate.pdf4 Feb 2020
Proforma of Allotment letterFile: AGREEMENT DRAFT.pdf4 Feb 2020
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf4 Feb 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Kiran ShubhlabhMohan Nagar soc Baner Pune 4110458CompletedMay 2015Late, Aug 2015
Kiran Silver DewS no 52 Part Susgaon Pune20CompletedJan 2015Late, Mar 2015
Kiran SphurteePart of S no 47 A Susgaon Pune 4110458CompletedSep 2014Late, Nov 2014
Kiran ShubhshreeMohan nagar soc Baner Pune 4110458CompletedMay 2014Late, Jun 2014
Kiran SolitaireS no 278 Part Susgaon Pune 41104532CompletedJan 2014Late, May 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kiran Samruddhi A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SUS13,700+ in Pune

Builder: M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE

M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE has 11 registrations on MahaRERA, including Kiran Sanklp and Kiran Suyog. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kiran Samruddhi A is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kiran Samruddhi A?

The registered promoter entity is M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kiran Samruddhi A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kiran Samruddhi A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kiran Samruddhi A?

The professionals named in the filing: Architect: ARCKITUDESTUDIO; Engineer: MANOJ BHASALE; Chartered Accountant: A M SADAVARTE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kiran Samruddhi A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kiran Samruddhi A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kiran Samruddhi A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.