Home / Browse projects / Palghar, Maharashtra / KESHAV SRUSHTI

Registered No litigation declared Residential / Group Housing project

KESHAV SRUSHTI

By SRUSHTI REALTORS

RG-MH-97738 · RERA P99000019551 · Last updated on MahaRERA portal: 19 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
16 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
54 of 92Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

KESHAV SRUSHTI is a Residential / Group Housing project by SRUSHTI REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000019551 on 8 Feb 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 38 of the 92 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.

At a glance

Project

  • NameKESHAV SRUSHTI
  • TypeResidential / Group Housing
  • Location
    • MAHIM VILLAGE
    • PALGHAR WEST
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000019551
  • ReraGenie IDRG-MH-97738

Builder

  • NameSRUSHTI REALTORS
  • Entity typePartnership
  • PartnersDINESH KESHAVLAL SANGHRAJKA, DIGESH KISHOR SANGHRAJKA

Key dates

this monthRegisteredFeb 2019First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Feb 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed114 files

Current status

41%38 of 92 units booked
100.0%Work done, per cost certificate

Figures as on 19 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KESHAV SRUSHTI BLDG NO 1NA13842850
KESHAV SRUSHTI BLDG NO 2NA13742042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

KESHAV SRUSHTI BLDG NO 173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
KESHAV SRUSHTI BLDG NO 273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered10
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
KESHAV SRUSHTI BLDG NO 15510
KESHAV SRUSHTI BLDG NO 25510

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,811 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
CHAMANLAL HANSRAJ GUPTAMumbai CityMumbai City
VISHAL CHAMANLAL GUPTAMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityCOLLECTOR OFFICE PALGHAR
Permissible FSI3810.75
Proposed, not sanctioned3,811 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKACHERI ROAD PALGHAR WEST
Estimated costRs 11.21 cr
Cost incurredRs 11.21 cr
Work done100.0%
BuildingWingEstimatedIncurred
KESHAV SRUSHTI BLDG NO 1NARs 9.39 crRs 9.39 cr
KESHAV SRUSHTI BLDG NO 2NARs 90.92 lakhRs 90.92 lakh
-NARs 90.92 lakhRs 90.92 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMORPH DESINGH STUDIO
EngineerMESHRAM & THUKRAL
Chartered AccountantANIKET M PADHYE & CO
Chartered AccountantD R TAMBOLI & ASSOCAITES
PartnerRole in project
SRUSHTI REALTORS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000017072Dec 2022 → Dec 2023

Reason as filed by the promoterOccupation certificate Pursued

EXT99000013965Dec 2022 → Jun 2023

Reason as filed by the promoterPURSUED FOR OC

EXT99000018714Dec 2022 → Dec 2024

Reason as filed by the promoteroc not recevied

EXT99000027104Dec 2022 → Dec 2025

Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 3. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 4. Also,we are uploading the PERTChart/work completion schedule of the project. 5. Hence,we request you to consider our request & justification & grant extension to our

EA17062621408Dec 2022 → Dec 2026

Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project is Completed & have Applied for OC which is expected in 3 to 6 months. 3. Also,we are uploading the PERTChart/work completion schedule of the project. 4. Hence,we request you to consider our request & justification & grant extension to our said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Mar 2023

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 March 2026.pdf19 Sep 2026
Withdrawal Update Form 1File: Form-1 June 2026 (1).pdf19 Sep 2026
Withdrawal Update Form 2File: Form-2 March 2026.pdf19 Sep 2026
Withdrawal Update Form 2File: Form-2 June 2026 (3).pdf19 Sep 2026
Withdrawal Update Form 3File: Form-3 March 2026.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3 Woods (1).pdf19 Sep 2026
Form 5 (FY 2024-2025)File: Form-5(Fy 2024-25).pdf10 Sep 2026
Form 2A (FY 2024-2025)File: Form-2A 2024-2025.pdf23 Jun 2026
Form 2A (FY 2025-2026)File: Form -2 A 2025-2026.pdf23 Jun 2026
Withdrawal Update Form 1File: Form-1 Dec 2025.pdf14 May 2026
Withdrawal Update Form 1File: Form-1 Sep 2025.pdf14 May 2026
Withdrawal Update Form 2File: Form-2 Dec 2025 (1).pdf14 May 2026
Withdrawal Update Form 2File: Form-2 Sep 2025.pdf14 May 2026
Withdrawal Update Form 3File: Form-3 Dec 2025.pdf14 May 2026
Withdrawal Update Form 3File: Form-3 Dec 2025.pdf14 May 2026
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf30 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM-1 NEW.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM-2 NEW.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold unsold merged.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 Keshav Srushti Fy 2023-24_compressed.pdf7 Jan 2025
Certificates of CA (Form 3)File: CA Certificate Form-3 New SRUSHTI REALTORS.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: sOLD UNSOLD KESHAV SRUSHTI.pdf6 Jan 2025
Declaration in FORM BFile: Affidavid cum declaration.pdf28 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1.pdf28 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From-2.pdf28 Dec 2024
CERSAI detailsFile: declaration.pdf28 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From-2A.pdf28 Dec 2024
Disclosure of sold/ booked inventoryFile: ilovepdf_merged (4)SPLD UNSOLD LATEST.pdf7 Mar 2024
Certificates of CA (Form 3)File: Keshav form-3 final_compressed.pdf7 Mar 2024
Certificates of CA (Form 3)File: Keshav form-3 final_compressed.pdf7 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: From -2A 19-20 new.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: sold unsold new.pdf12 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From -2A 20-21.pdf1 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: From -2A 20-21.pdf1 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM -2A 22-23.pdf1 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUSRE ALL PARTNERS.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FROM -5.pdf1 Feb 2024
Declaration in FORM BFile: Affidavit cum Declaration (2).pdf31 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 with sign of promoter.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: From -2A 19-20.pdf31 Jan 2024
CERSAI detailsFile: DECLARATION CERSAI.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: sold unsold merged.pdf31 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate Bank account.pdf31 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 jan 24.pdf20 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 jan 24.pdf20 Jan 2024
Deviation Report with respect to Allotment letterFile: ALLOTMENT LEETER.pdf20 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Agreement Draft.pdf20 Jan 2024
Home Buyer /Allottee Grievance Redressal CellFile: CONCENT LETTER NEW JAN 24.pdf20 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From-1.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From -2.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From -2.pdf10 Jan 2024
Certificates of CA (Form 3)File: from 3 Q_4 22-23.pdf10 Jan 2024
Proforma of Agreement for saleFile: Agreement Draft.pdf17 Jul 2023
Proforma of Agreement for saleFile: Agreement Draft.pdf16 Jul 2023
Details of encumbrances concerned to FinanceFile: SOLD UNSOLD DETAILS FOR RERA.pdf13 Jul 2023
Details of encumbrances concerned to LegalFile: SOLD UNSOLD DETAILS FOR RERA.pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DETAILS FOR RERA.pdf13 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FROM -5 JULY-2023.pdf13 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From-1.pdf11 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From -2.pdf11 Jul 2023
Certificates of CA (Form 3)File: from_3__Q_1__20230701_12251955.pdf1 Jul 2023
Certificates of CA (Form 3)File: from_3__Q_2__20230701_12313377.pdf1 Jul 2023
Certificates of CA (Form 3)File: from_3__Q_3__20230701_12351128.pdf1 Jul 2023
Certificates of CA (Form 3)File: from_3__Q_4__20230701_12325885.pdf1 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a.pdf12 Mar 2023
OtherFile: Appendix - G.pdf12 Mar 2023
OtherFile: architect.pdf12 Mar 2023
Other - FinanceFile: extension payment.pdf12 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: architech CERTIFICATE).pdf5 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: architech certifigate build no 1.pdf5 Mar 2023
OtherFile: extension payment.pdf5 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a 20-21.pdf26 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form_2__engineer_s_certificate (1).pdf26 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf26 Feb 2023
Certificates of CA (Form 3)File: DEC-20.pdf21 Feb 2023
Certificates of CA (Form 3)File: JUNE-20_compressed.pdf21 Feb 2023
Certificates of CA (Form 3)File: SEP-20_compressed.pdf21 Feb 2023
Certificates of CA (Form 3)File: MAR-21_compressed.pdf21 Feb 2023

How this compares with Palghar

41%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 48 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KESHAV SRUSHTI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR WEST3,200+ in Palghar

2 kmKESHAV SRUSHTICompleted 126Lapsed / revoked 60Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 327 registered projects within 2 km.

Builder: SRUSHTI REALTORS

SRUSHTI REALTORS has 1 registration on MahaRERA, including KESHAV SRUSHTI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if KESHAV SRUSHTI is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KESHAV SRUSHTI?

The registered promoter entity is SRUSHTI REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KESHAV SRUSHTI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KESHAV SRUSHTI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KESHAV SRUSHTI?

The professionals named in the filing: Architect: MORPH DESINGH STUDIO; Engineer: MESHRAM & THUKRAL; Chartered Accountant: ANIKET M PADHYE & CO; Chartered Accountant: D R TAMBOLI & ASSOCAITES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KESHAV SRUSHTI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KESHAV SRUSHTI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KESHAV SRUSHTI to a free account