ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Kesar Kalhaar

Registered No litigation declared Residential / Group Housing project

Kesar Kalhaar

By HR Realty

RG-MH-05593 · RERA P52100056224 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 26 months from the original
7 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 95%
19 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

Kesar Kalhaar is a Residential / Group Housing project by HR Realty in Pune, Maharashtra, registered with MahaRERA as P52100056224 on 22 May 2024. Possession is promised by 31 Dec 2028. The completion date has moved by 26 months from the original filing. 6 of the 25 units on this registration are recorded sold or booked, and 7 of 44 construction stages are filed complete.

At a glance

Project

  • NameKesar Kalhaar
  • TypeResidential / Group Housing
  • Location
    • chinchawad
    • pune
    • Kiwale
    • Haveli
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100056224
  • ReraGenie IDRG-MH-05593

Builder

  • NameHR Realty
  • Entity typePartnership
  • PartnersAnkit Pravinkumar Pokar, Dilipkumar Hiralal Patel, Maulikkumar Gangaram Patel, Mukeshkumar Mavjibhai Patel, Nitinkumar Narsinhbhai Patel, Vinod Kumar Manibhai Patel, Chetankumar Shantilal Patel, Dilip Manilal Patel, Naginkumar Dhanjibhai Patel, Pankaj Kumar Purushottam Das Patel, Rasiklal Somjibhai Patel, Vipulkumar Ratilal Dholu

Key dates

this monthRegisteredMay 2024First promiseOct 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 May 2024
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 21 Oct 2026)
  • Buildings4 building records
  • Documents filed97 files

Current status

24%6 of 25 units booked
36.0%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA44808
A2NA44808
B1NA44303
B2NA44606

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 95%.

A10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B167%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B248%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,600 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Sep 2025

Approvals and building plan

Sanctioning authoritypimpri chinchwad municipal corporation
Permissible FSI6576.79
Proposed, not sanctioned6,277 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchground floor shop no 1 to 4 sai manglam bldg A, Sector -13, spine road, PCNTDA moshi pimpri chinchwa
Estimated costRs 22.99 cr
Cost incurredRs 8.29 cr
Work done36.04%
BuildingWingEstimatedIncurred
A1NARs 5.25 cr-
A2NARs 5.25 cr-
B1NARs 5.25 crRs 3.74 cr
B2NARs 5.25 crRs 3.74 cr
-NARs 2.00 crRs 80.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnuradha Govardhan
EngineerGaurav Patel
EngineerAMOL KONDIBA KANK
Chartered AccountantSwati Patel
Chartered AccountantBhavik J Velani
PartnerRole in project
HR Realty-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30072621943Oct 2026 → Dec 2028

Reason as filed by the promoterThe construction of Building A1 and A2 is majorily left and the construction of Building B1 and B2 are almost done and hence, the extention is needed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: FORM2A HR REALTY.pdf30 Jul 2026
Form 2A (FY 2025-2026)File: FORM2A HR REALTY.pdf30 Jul 2026
Form 2A (FY 2026-2027)File: FORM2A HR REALTY.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf17 Jul 2026
Withdrawal Update Form 2File: Form 2_.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf17 Jul 2026
Form 5 (FY 2025-2026)File: Scan Form-5 HR REALTY.pdf16 Jun 2026
Withdrawal Update Form 1File: Form 1 20042026.pdf20 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf2 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf2 Mar 2026
Withdrawal Update Form 3File: FORM 3.pdf2 Mar 2026
Withdrawal Update Form 1File: FORM 1.pdf9 Feb 2026
Withdrawal Update Form 2File: FORM 2.pdf9 Feb 2026
Withdrawal Update Form 3File: FORM 3.pdf9 Feb 2026
Form 5 (FY 2024-2025)File: Uploded Form-5.pdf8 Oct 2025
Building plan approvalFile: IMG_1300.pdf19 Sep 2025
Building plan approvalFile: IMG_1301.pdf19 Sep 2025
Building plan approvalFile: IMG_1302.pdf19 Sep 2025
Building plan approvalFile: IMG_1303_compressed.pdf19 Sep 2025
Building plan approvalFile: IMG_1304.pdf19 Sep 2025
Layout approvalFile: IMG_1436 - LAY OUT.pdf19 Sep 2025
Building plan approvalFile: IMG_1437.pdf19 Sep 2025
Building plan approvalFile: IMG_1438.pdf19 Sep 2025
Building plan approvalFile: IMG_1439.pdf19 Sep 2025
Building plan approvalFile: IMG_1440.pdf19 Sep 2025
Building plan approvalFile: IMG_1441.pdf19 Sep 2025
Building plan approvalFile: IMG_1442.pdf19 Sep 2025
Layout approvalFile: IMG_1299_compressed - LAY OUT.pdf19 Sep 2025
Form 1File: Form 1 30062025.pdf14 Aug 2025
Form 2File: Form 2 30062025.pdf14 Aug 2025
Form 3File: Form 3 30062025.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf14 Aug 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_Q4.pdf5 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A2425.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_SIGNED.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_311224_compressed.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_SIGNED.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Q1.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Q2.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Q3.pdf14 Feb 2025
Building plan approvalFile: A1 A2 2_compressed.pdf20 May 2024
Building Plan Approval / NA Order for plotted developmentFile: A1 A2 2_compressed.pdf20 May 2024
Other - TechnicalFile: A1 A2 2_compressed.pdf20 May 2024
Building plan approvalFile: HPSC A1(5).pdf16 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC A1(5).pdf16 May 2024
Copy of the legal title reportFile: HR Realty Search.pdf30 Apr 2024
Other - TechnicalFile: HR Realty CC Verify.pdf30 Apr 2024
Other - TechnicalFile: HR Realty verify cc plot b.pdf30 Apr 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Financial.pdf28 Mar 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Legal.pdf28 Mar 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Financial.pdf28 Mar 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Legal.pdf28 Mar 2024
Declaration in FORM BFile: Form b.pdf28 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 aRCHITECT CERTIFICATE.pdf28 Mar 2024
CERSAI detailsFile: Cersai report kesar kalhaar.pdf28 Mar 2024
CERSAI detailsFile: CERSAI Declaration.pdf28 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 HR_11zon.pdf28 Mar 2024
Other - TechnicalFile: 4_PDEED.pdf28 Mar 2024
Other - TechnicalFile: Declaration of Non Registration Standalone Project.pdf28 Mar 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (13).pdf27 Mar 2024
Layout approvalFile: HPSC0286_7_11zon.pdf27 Mar 2024
Building plan approvalFile: 1 Copy of Layout Approval (in case of layout) (13).pdf27 Mar 2024
Building plan approvalFile: HPSC0281_2_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0282_3_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0289_10_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0290_11_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0291_12_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0284_5_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0285_6_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0286_7_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0287_8_11zon.pdf27 Mar 2024
Building plan approvalFile: HPSC0288_9_11zon.pdf27 Mar 2024
PAN CardFile: 11zon_rotated-PDF (7).pdf27 Mar 2024
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (13).pdf27 Mar 2024
Copy of Layout Approval (in case of layout)File: HPSC0286_7_11zon.pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Copy of Layout Approval (in case of layout) (13).pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0281_2_11zon.pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0282_3_11zon.pdf27 Mar 2024

How this compares with Pune

24%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 26 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kesar Kalhaar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pune13,700+ in Pune

2 kmKesar KalhaarCompleted 71Lapsed / revoked 46Other 97Dot size: filed unitsN

Filed coordinates, straight-line distance. 214 registered projects within 2 km.

Builder: HR Realty

HR Realty has 1 registration on MahaRERA, including Kesar Kalhaar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kesar Kalhaar is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kesar Kalhaar?

The registered promoter entity is HR Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kesar Kalhaar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kesar Kalhaar?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kesar Kalhaar?

The professionals named in the filing: Architect: Anuradha Govardhan; Engineer: Gaurav Patel; Engineer: AMOL KONDIBA KANK; Chartered Accountant: Swati Patel; Chartered Accountant: Bhavik J Velani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kesar Kalhaar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kesar Kalhaar. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kesar Kalhaar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.