Home / Browse projects / Pune, Maharashtra / Kedar Residency
Kedar Residency
By Subhagya Promoters & Builders Pvt Ltd
RG-MH-23004 · RERA P52100032109 · Last updated on MahaRERA portal: 18 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kedar Residency is a Others project by Subhagya Promoters & Builders Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100032109 on 14 Dec 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 95 of the 130 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameKedar Residency
- TypeOthers
- Location
- Kiwale Mamurdi Road
- Near Masulkar Farm
- Mamurdi
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032109
- ReraGenie IDRG-MH-23004
Builder
- NameSubhagya Promoters & Builders Pvt Ltd
- Entity typeCompany
- GSTIN27AAECA6364L1ZC
- Managing DirectorRajendra Hindurao Bhosale
- DirectorsSavita Ghanshyam Gajare, Bharati Rajendra Bhosale
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Dec 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed159 files
Current status
Figures as on 18 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kedar Residency | NA | 14 | 13 | 110 | 20 | 130 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
Kedar Residency: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed163
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Subhagya Promoters and Builders Pvt Ltd | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Kedar Residency | NA | Rs 20.52 cr | Rs 20.26 cr |
| - | NA | Rs 4.21 cr | Rs 3.41 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rims Design Studio |
| Engineer | Aviraj Shivaji KOrade |
| Engineer | Sangram Subhash Koratkar |
| Chartered Accountant | Wagh Kulkarni & Associates |
| Chartered Accountant | DV JAYADE |
| Partner | Role in project |
|---|---|
| Subhagya Promoters & Builders Pvt Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to unforeseen circumstances, including shortages of construction materials, labour constraints, and financial challenges, the construction work of the said project was delayed, and consequently, the project could not be completed within the originally registered timeline. As a result, there was a delay in obtaining the Completion Certificate from the Competent Authority, and the Completion Certificate bearing No. 217/2026 was subsequently issued on 25/03/2026. Since the Completion Certificate was received after the registered project completion date, we respectfully request the Hon'ble Mah
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed159
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 3102026.PDF | 18 Sep 2026 |
| Withdrawal Update Form 1File: kedar f1 jun.pdf | 18 Sep 2026 |
| Withdrawal Update Form 2File: Form2 31032026.PDF | 18 Sep 2026 |
| Withdrawal Update Form 2File: kedar f2 jun.pdf | 18 Sep 2026 |
| Withdrawal Update Form 3File: KEDAR RESIDENCY F3.pdf | 18 Sep 2026 |
| Withdrawal Update Form 3File: kedar f3 jun.pdf | 18 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 3102026.PDF | 23 Jul 2026 |
| Withdrawal Update Form 2File: Form2 31032026.PDF | 23 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 31032026.PDF | 23 Jul 2026 |
| Form 1File: Form 1 3102026.PDF | 22 Jul 2026 |
| Form 2File: Form2 31032026.PDF | 22 Jul 2026 |
| Form 3File: Form 3 31032026.PDF | 22 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold March 2026.PDF | 22 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 3102026.PDF | 22 Jul 2026 |
| Withdrawal Update Form 2File: Form2 31032026.PDF | 22 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 31032026.PDF | 22 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A (1).PDF | 22 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 FY24-25.PDF | 22 Jul 2026 |
| Disclosure of sold/ booked inventoryFile: Kedar residency sold unsold 30 june 2025.PDF | 8 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate march 25_Form 1.PDF | 5 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate june 25_Form 1.PDF | 5 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 3132024.PDF | 15 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 dec 31122024.PDF | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate Form 2.PDF | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Kedar Residency.PDF | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architec Certificate Form 1.PDF | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi certif march 24_03022025155625.PDF | 3 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi certif june 24_03022025155719.PDF | 3 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi certif Sapt 24_03022025155753.PDF | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024.PDF | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024.PDF | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2024.PDF | 7 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera march_26102024114054.PDF | 29 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera june_26102024114130.PDF | 29 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera sapt_26102024114202.PDF | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineer Certificate.PDF | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Kedar residency Rera 30062024.PDF | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Kedar residency Rera_30092024.PDF | 14 Oct 2024 |
| Layout approvalFile: Plan No 1 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 1 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 2 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 3 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 4 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 5 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 6 6924.pdf | 11 Oct 2024 |
| Building plan approvalFile: Plan No 7 6924.pdf | 11 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: Plan No 1 6924.pdf | 11 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate Mamurdi 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 1 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 2 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 3 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 4 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 5 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 6 6924.pdf | 11 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 7 6924.pdf | 11 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement 30062023.pdf | 15 May 2024 |
| Disclosure of sold/ booked inventoryFile: Kedar sold unsold_15052024175823.PDF | 15 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate 1_03052024113919.PDF | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate 2_03052024114003.PDF | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate 3_03052024114045.PDF | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kmw 1_29042024150750.PDF | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kmw 2_29042024151018.PDF | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kmw 3_29042024151053.PDF | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KMW_04032024165814.PDF | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30 june 22_25012024160732.PDF | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30 sept 22_25012024160829.PDF | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31 Dec 22_25012024160924.PDF | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31 march 23_25012024161224.PDF | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KMW 30622.PDF | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KMW 30922.PDF | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KMW 311222-compressed.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KMW 3132023.PDF | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 30june 2022_17012024151103.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 30 sept 2022_17012024151211.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 31 Dec 2022_17012024151303.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31mar 2023_17012024151701.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 june 2023_17012024152224.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 sept 2023_17012024152828.PDF | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31 Dec 2023_17012024152909.PDF | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Kedar 30 june 2022_16012024154823.PDF | 16 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAPTRASHRI RESIDENCY | S NO 75 AND 76 AHER NAGAR WALHEKARWADI CHINCHWAD PUNE- 411033 | 195 | Completed | Dec 2019 | Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 159 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kedar Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Masulkar Farm13,700+ in Pune
Filed coordinates, straight-line distance. 433 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: Subhagya Promoters & Builders Pvt Ltd
Subhagya Promoters & Builders Pvt Ltd has 1 registration on MahaRERA, including Kedar Residency. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kedar Residency is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kedar Residency?
The registered promoter entity is Subhagya Promoters & Builders Pvt Ltd, a company as per the filing. Its GSTIN 27AAECA6364L1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kedar Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kedar Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kedar Residency?
The professionals named in the filing: Architect: Rims Design Studio; Engineer: Aviraj Shivaji KOrade; Engineer: Sangram Subhash Koratkar; Chartered Accountant: Wagh Kulkarni & Associates; Chartered Accountant: DV JAYADE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kedar Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback