Home / Browse projects / Thane, Maharashtra / KAVYA PARK

Registered No litigation declared Others project

KAVYA PARK

By SHREE CONSTRUCTION COMPANY

RG-MH-96464 · RERA P51700010575 · Last updated on MahaRERA portal: 18 Feb 2026

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA
  • Completion date moved by 72 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 72 months from the original
14 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 67%
32 of 173Units unsoldnot recorded sold or booked
10Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

KAVYA PARK is a Others project by SHREE CONSTRUCTION COMPANY in Thane, Maharashtra, registered with MahaRERA as P51700010575 on 31 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 72 months from the original filing. 141 of the 173 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete. 10 complaints are on record with the regulator.

At a glance

Project

  • NameKAVYA PARK
  • TypeOthers
  • Location
    • THANE
    • Thane (M Corp.)
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700010575
  • ReraGenie IDRG-MH-96464

Builder

  • NameSHREE CONSTRUCTION COMPANY
  • Entity typePartnership
  • PartnersUSHA MANSUKHLAL VORA, JIGNESH MANSUKHLAL VORA, MANSUKHLAL CHATRABHUJ VORA
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed90 files

Current status

82%141 of 173 units booked
33.6%Work done, per cost certificate

Figures as on 18 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAVYA PARK A WINGNA1413481058
KAVYA PARK B WINGNA3114471057
KAVYA PARK C WINGNA1513481058

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 18 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 67%.

KAVYA PARK A WING57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Sanitary Fittings within the flats / premises13%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.9%
KAVYA PARK B WING52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises22%
Sanitary Fittings within the flats / premises7%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.18%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
KAVYA PARK C WING52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks44%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.3%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.9%

Progress on shared amenities15

As on 18 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16
BuildingClosed/CoveredTotal
KAVYA PARK A WING22
KAVYA PARK B WING1212
KAVYA PARK C WING22

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,680 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 May 2025

Approvals and building plan

Sanctioning authorityTHANE MUNICIPAL CORPORATION
Permissible FSI8188.69
Proposed, not sanctioned3,962 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD, VENUS APARTMENT, GROUND FLOOR, WADIA STREET, TARDEO MUMBAI-400034
Estimated costRs 56.64 cr
Cost incurredRs 19.05 cr
Work done33.63%
BuildingWingEstimatedIncurred
-NARs 32.25 crRs 4.92 cr
KAVYA PARK C WINGNARs 9.52 crRs 5.03 cr
KAVYA PARK A WINGNARs 9.49 crRs 5.01 cr
KAVYA PARK B WINGNARs 5.38 crRs 4.09 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHIT CONSULTANTS
EngineerBharat C Bhatt
Chartered AccountantS N & CO
PartnerRole in project
SHREE CONSTRUCTION COMPANY-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010449Jun 2021 → Jun 2022

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

EXT51700013466Jun 2021 → Dec 2024

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS

EA22052501215Jun 2021 → Dec 2025

Reason as filed by the promotera Delay in Procuring ULC Order: The said Project was subject to Urban Land Ceiling (ULC) regulations and the process of procuring the necessary ULC order was time-consuming due to procedural formalities and approvals required from the concerned authorities. The alleged delay in obtaining this onder directly impacted the said Project's timeline

EA18022619896Jun 2021 → Jun 2027

Reason as filed by the promoterWe, SHREE CONSTRUCTION COMPANY, are the promoters of the real estate project known as "KAVYA PARK" bearing Maha RERA Registration No. P51700010575 are applying for an extension as:1) Certain permissions require revision and thus keeping in mind the timelines, an extension for completion of project has been applied for

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000044058Supriya P KumbhareM/s Shree Construction Company08/04/2018
CC006000000044120RUCHI JOSHIM/S SHREE CONSTRUCTION CO.14/04/2018
CC006000000056754Rushikesh PatilShree Construction Company28/10/2018
CC006000000396748NISHIKANT SAWANTshree construction company19/07/2023
CC006000000397903KUNAL THAKRENIMISH VORA25/12/2023
CC006000000397989Pravin EdekarSHREE CONSTRUCTION COMPANY30/10/2023
CC006000000408564Snehal M JhaveriM/S SHREE CONSTRUCTION CO03/01/2024
CC006000000408620HARSHAD POPATLAL PANCHALNIMISH VORA25/12/2023
CC006000000408628BEENA VISHWAS PATILNimish Vora25/12/2023
CC006000000428927Rohit Sharad VazareNIMISH VORA18/02/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: KAVYA PARK FORM 1 31 12 2025_11zon.pdf18 Feb 2026
Withdrawal Update Form 2File: SCC KAVYA PARK FORM 2 31 12 2025_11zon.pdf18 Feb 2026
Withdrawal Update Form 3File: SCC KAVYA PARK FORM 3 31 12 2025_11zon.pdf18 Feb 2026
Withdrawal Update Form 1File: KAVYA PARK ARCHITECT CERTIFICATE 30 06 2025.pdf16 Feb 2026
Withdrawal Update Form 1File: FORM 1.pdf16 Feb 2026
Withdrawal Update Form 2File: SCC KAVYA PARK FORM 2 30 06 2025.pdf16 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf16 Feb 2026
Withdrawal Update Form 3File: SCC KAVYA PARK FORM 3 30 06 2025 1.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf16 Feb 2026
Withdrawal Update Form 1File: KAVYA PARK ARCHITECT CERTIFICATE 30 06 2025.pdf6 Feb 2026
Withdrawal Update Form 2File: Form-2 SCC 09 23.pdf6 Feb 2026
Withdrawal Update Form 3File: SCC KAVYA PARK FORM 3 30 06 2025 1.pdf6 Feb 2026
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 march 25 1.pdf9 May 2025
Certificates of CA (Form 3)File: form 3 (3).pdf7 May 2025
Disclosure of sold/ booked inventoryFile: SCC-KAVYA PARK-SOLD AND UNSOLD INVENTORY (1).pdf2 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 march 25.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.PDF25 Apr 2025
Declaration in FORM BFile: KAVYA PARK-FORM-B (1).pdf24 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 march 25.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 03 24.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 06 24.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 09 24.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 12 24.pdf21 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCC-FORM-2-30-09-2024.pdf10 Feb 2025
Certificates of CA (Form 3)File: SCC FORM-3 30092024 (1).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf21 Jan 2025
Certificates of CA (Form 3)File: form 3 oct to dec 23.pdf15 Jan 2025
Certificates of CA (Form 3)File: form 3 jan to march 24.pdf15 Jan 2025
Certificates of CA (Form 3)File: form 3 april to june 24.pdf15 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCC-FORM-2-31-12-2023.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCC-FORM-2-31-03-2024.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCC-FORM-2-30-06-2024.pdf26 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech form 1 06 24.pdf26 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 09 24.pdf26 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf18 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 oct to dec 23.pdf30 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf30 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf6 Jun 2024
CERSAI detailsFile: KAVYA PARK-CERSAI DECLERATION.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form-3 SCC 06 23.pdf27 Oct 2023
Certificates of CA (Form 3)File: Form-3 SCC 09 23.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: KAVYA PARK-inventory disclosure format.pdf25 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architects Certificate for Kavya Park-12 03 2023 (1) (1).pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architects Certificate for Kavya Park-21 06 2023 (2) (1).pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architects Certificate for Kavya Park-12 09 2023 (3) (1).pdf17 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 SCC 06 23.pdf11 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 SCC 09 23.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: KAVYA PARK FORM 2A 2022.pdf22 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KAVYA PARK FORM 2A 2023.pdf22 Jul 2023
Certificates of CA (Form 3)File: Form-3 2019.pdf22 Jul 2023
Certificates of CA (Form 3)File: Form-3 2020.pdf22 Jul 2023
Certificates of CA (Form 3)File: Form-3 2021.pdf22 Jul 2023
Certificates of CA (Form 3)File: Form-3 2022.pdf22 Jul 2023
Certificates of CA (Form 3)File: Form-3 2023.pdf22 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2019.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2020.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2021.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023.pdf21 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 SCC 21-22.pdf18 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 SCC 22-23.pdf18 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 09 20.pdf10 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 05 22.pdf10 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 12 22.pdf10 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Shree Construction Co 20-21.pdf5 Jan 2023
Declaration about Commencement CertificateFile: CC COVERING LETTER PARK.pdf21 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf17 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A 19-20.pdf14 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Shree Construction Company_compressed (1).pdf14 Jul 2021
Disclosure of sold/ booked inventoryFile: INVENTORY DISLCOSURE.pdf14 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf14 Jul 2021
Certificates of CA (Form 3)File: CA KAVYA PARK compressed.pdf14 Nov 2018
Certificates of CA (Form 5)File: KAVYA PARK compressed.pdf9 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate compressed.pdf28 Sep 2018
Layout approvalFile: Layout Plan.pdf31 Jul 2017
Building plan approvalFile: IOD.pdf31 Jul 2017
PAN CardFile: Shree Construction Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf31 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KAVYA HILL VIEWTHANE107CompletedJan 2012Late, Mar 2012
ATLASTHANE45CompletedMar 2011Late, May 2011
Atlantis, ThaneTHANE84CompletedMar 2010Late, Jul 2010

How this compares with Thane

82%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 72 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAVYA PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

2 kmKAVYA PARKCompleted 76Lapsed / revoked 25Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 150 registered projects within 2 km.

Builder: SHREE CONSTRUCTION COMPANY

SHREE CONSTRUCTION COMPANY has 2 registrations on MahaRERA, including KAVYA PARK and Swaroop Residency. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if KAVYA PARK is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAVYA PARK?

The registered promoter entity is SHREE CONSTRUCTION COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAVYA PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KAVYA PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KAVYA PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAVYA PARK?

The professionals named in the filing: Architect: ARCHIT CONSULTANTS; Engineer: Bharat C Bhatt; Chartered Accountant: S N & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAVYA PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAVYA PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAVYA PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.