ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KANCHAN VATIKA

Completed No litigation declared Residential / Group Housing project

KANCHAN VATIKA

By Novel Build-con

RG-MH-28429 · RERA P99000026327 · Last updated on MahaRERA portal: 1 Sep 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Nov 2023Possession promisedregistration recorded completed
40 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

KANCHAN VATIKA is a Residential / Group Housing project by Novel Build-con in Palghar, Maharashtra, registered with MahaRERA as P99000026327 on 11 Sep 2020. The registration is recorded completed; possession was promised by 4 Nov 2023.

At a glance

Project

  • NameKANCHAN VATIKA
  • TypeResidential / Group Housing
  • Location
    • Devisha Road
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000026327
  • ReraGenie IDRG-MH-28429

Builder

  • NameNovel Build-con
  • Entity typePartnership
  • PartnersUMESH VARDICHAND JAIN, RAJESH MAHENDRA MEHTA
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2020PromisedNov 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Sep 2020
  • Promised completion4 Nov 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANCHAN VATIKA-1NA90000
KANCHAN VATIKA BUNGLOW 1NA30000
KANCHAN VATIKA BUNGLOW 2NA20000
KANCHAN VATIKA BUNGLOW 3NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 1 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

KANCHAN VATIKA-191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KANCHAN VATIKA BUNGLOW 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KANCHAN VATIKA BUNGLOW 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KANCHAN VATIKA BUNGLOW 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23
BuildingClosed/CoveredTotal
KANCHAN VATIKA-12020
KANCHAN VATIKA BUNGLOW 111
KANCHAN VATIKA BUNGLOW 211
KANCHAN VATIKA BUNGLOW 311

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,094 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4681.0
Proposed, not sanctioned4,681 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHIM ROAD, PALGHAR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNishant P Patil
EngineerSHAH &ASSOCIATES
Chartered AccountantD R AGRAWAL & ASSOCIATES
PartnerRole in project
Novel Build-con-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Sep 2023

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Vatika.pdf1 Sep 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Vatika.pdf1 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1_compressed.pdf3 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 kanchan vatika.pdf3 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold - Kanchan Vatika.pdf3 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Vatika 2021-22.pdf3 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 Vatika 2022-23.pdf3 Jun 2023
Declaration about Commencement CertificateFile: NA Order Nagar Parishad vatika.pdf22 Nov 2022
Proforma of Agreement for saleFile: Draft Agreement Copy.pdf22 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format Allotment Letter.pdf22 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format - A.pdf22 Nov 2022
Deviation Report with respect to Allotment letterFile: Format Allotment Letter.pdf22 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Format Sale Agree.pdf22 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Vatika 13-7.pdf18 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng- Stru Vatika 13-7.pdf18 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Suervisor Certi_ Vatika.pdf18 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold _Unsold List Vatika.pdf18 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Letter Vatika _ 20_4.pdf4 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Vatika 20_4.pdf4 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold _Unsold List Vatika.pdf4 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA FORM NO 5 VATIKA.pdf4 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kanchan Vatika CA.pdf16 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Vatika 012022.pdf12 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Vatika 012022.pdf12 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KBC 19-20.pdf31 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: NA Order Nagar Parishad vatika.pdf16 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Letter Vatika.pdf16 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold unsold List vatika.pdf16 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA VATIKA_1.pdf16 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold_Unsold_Vatika_compressed.pdf7 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Vatika.pdf26 May 2021
Proforma of Allotment letterFile: Agreement_Vatika_-_Draft_New_Blank.pdf5 May 2021
Building plan approvalFile: Type B 1.pdf4 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Type B 1.pdf4 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Nagar Parishad Order_new.pdf4 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter - Vatika.pdf4 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer-Structure.pdf4 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate.pdf4 May 2021
Layout approvalFile: Layout.pdf14 Apr 2021
Building plan approvalFile: Type A.pdf14 Apr 2021
Building plan approvalFile: Type B_compressed.pdf14 Apr 2021
Building plan approvalFile: Type C.pdf14 Apr 2021
Copy of Layout Approval (in case of layout)File: Layout.pdf14 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: Type A.pdf14 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: Type B_compressed.pdf14 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: Type C.pdf14 Apr 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate-1.pdf20 Aug 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf20 Aug 2020
Building plan approvalFile: Plan Bld No 2 3 4.pdf19 Aug 2020
PAN CardFile: Buildcon Pan Card.pdf19 Aug 2020
Details of encumbrancesFile: Encumbrances.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Bld No 2 3 4.pdf19 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: N A ORDER NH.pdf19 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf19 Aug 2020
Proforma of Allotment letterFile: Allotment Letter.pdf19 Aug 2020
Layout approvalFile: Layout Plan.pdf10 Aug 2020
Building plan approvalFile: Plan Bldg 1.pdf10 Aug 2020
Copy of the legal title reportFile: Search Report.pdf10 Aug 2020
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf10 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Bldg 1.pdf10 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: Nagar Parishad Order.pdf10 Aug 2020
Declaration in FORM BFile: Owner Affidivit.pdf10 Aug 2020
Proforma of Allotment letterFile: Rera Draft Palghar 1306 1314 ( Novel Buildcon ).pdf10 Aug 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
KANCHAN BUSINESS CENTERMAHIM MANOR ROAD PAGLHAR110CompletedJun 2023Jun 2023

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANCHAN VATIKA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palghar3,200+ in Palghar

2 kmKANCHAN VATIKACompleted 20Lapsed / revoked 16Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: Novel Build-con

Novel Build-con has 3 registrations on MahaRERA, including KANCHAN VATIKA and SHREE SAKET. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if KANCHAN VATIKA is delayed beyond 4 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANCHAN VATIKA?

The registered promoter entity is Novel Build-con, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANCHAN VATIKA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KANCHAN VATIKA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANCHAN VATIKA?

The professionals named in the filing: Architect: Nishant P Patil; Engineer: SHAH &ASSOCIATES; Chartered Accountant: D R AGRAWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANCHAN VATIKA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANCHAN VATIKA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANCHAN VATIKA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.