ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KANCHAN BUSINESS CENTER

Completed No litigation declared Commercial project

KANCHAN BUSINESS CENTER

By NOVEL BUILDCON

RG-MH-02942 · RERA P99000020390 · Last updated on MahaRERA portal: 28 Nov 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

KANCHAN BUSINESS CENTER is a Commercial project by NOVEL BUILDCON in Palghar, Maharashtra, registered with MahaRERA as P99000020390 on 9 Apr 2019. The registration is recorded completed; possession was promised by 30 Jun 2024.

At a glance

Project

  • NameKANCHAN BUSINESS CENTER
  • TypeCommercial
  • Location
    • MAHIM MANOR ROAD
    • PALGHAR
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000020390
  • ReraGenie IDRG-MH-02942

Builder

  • NameNOVEL BUILDCON
  • Entity typePartnership
  • PartnersRAJESH MAHENDRA MEHTA, UMESH VARDICHAND JAIN
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredApr 2019PromisedJun 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Apr 2019
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANCHAN BUSINESS CENTERNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

KANCHAN BUSINESS CENTER: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Open Space44

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,880 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4965.54
Proposed, not sanctioned4,190 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Old Uma Villa, Mahim Road, Palghar, 401404

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNishant Prabhakar Patil
EngineerShah & Associates
PartnerRole in project
NOVEL BUILDCON-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Sep 2022

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Nagar Parisha Order New.pdf28 Nov 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: KBC Society Regi.pdf28 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - KBC.pdf28 Nov 2022
Deviation Report with respect to Allotment letterFile: No Allot- KBC.pdf28 Nov 2022
Deviation Report with respect to model copy of AgreementFile: No Change Agree KBC.pdf28 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC CERTIFICATE FULL.pdf6 Sep 2022
Architect’s Certificate on Completion of Project (Form 4)File: Architect_4.pdf6 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech KBC 13-7.pdf18 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng -Stru- KBC 13-7.pdf18 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Suervisor Certi_ KBC.pdf18 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold List - KBC.pdf18 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Letter KBC 20_4.pdf23 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng KBC 20-4.pdf23 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold List - KBC.pdf23 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KBC CERTI CA.pdf23 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect KBC 012022.pdf12 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng KBC 012022.pdf12 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KBC 19-20.pdf31 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certi KBC.pdf18 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certi KBC.pdf18 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold List KBC.pdf18 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate KBC.pdf18 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC KBC.pdf18 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng_-_KBC 20210814_compressed.pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect percentage.pdf7 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold_Unsold_KBC.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 September 2019_compressed.pdf21 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 December 2019_compressed.pdf21 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 March 2020_compressed.pdf21 Aug 2020
Declaration in FORM BFile: FORM B REVISED.pdf2 Apr 2019
Layout approvalFile: MYSCAN_20190326_0001 (6).pdf29 Mar 2019
Copy of Layout Approval (in case of layout)File: MYSCAN_20190326_0001 (6).pdf29 Mar 2019
Declaration in FORM BFile: FORM B.pdf29 Mar 2019
Certificates of CA (Form 3)File: CA.pdf29 Mar 2019
Proforma of Allotment letterFile: Allotment letter.pdf29 Mar 2019
Proforma of Allotment letterFile: Agreement.pdf29 Mar 2019
Details of encumbrancesFile: NO ENCUMBRANCE.pdf23 Mar 2019
Building plan approvalFile: PALGHAR COMM 1.pdf22 Mar 2019
Building plan approvalFile: PALGHAR COMM 2 copy.pdf22 Mar 2019
PAN CardFile: PAN.pdf22 Mar 2019
Copy of the legal title reportFile: Title_compressed.pdf22 Mar 2019
Building Plan Approval (IOD)File: PALGHAR COMM 1.pdf22 Mar 2019
Building Plan Approval (IOD)File: PALGHAR COMM 2 copy.pdf22 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: Nagarparishad_compressed.pdf22 Mar 2019

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANCHAN BUSINESS CENTER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR3,200+ in Palghar

2 kmKANCHAN BUSINESS CENTERCompleted 118Lapsed / revoked 49Other 139Dot size: filed unitsN

Filed coordinates, straight-line distance. 306 registered projects within 2 km.

Builder: NOVEL BUILDCON

NOVEL BUILDCON has 2 registrations on MahaRERA, including KANCHAN BUSINESS CENTER and KANCHAN IMPERIAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if KANCHAN BUSINESS CENTER is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANCHAN BUSINESS CENTER?

The registered promoter entity is NOVEL BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANCHAN BUSINESS CENTER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KANCHAN BUSINESS CENTER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANCHAN BUSINESS CENTER?

The professionals named in the filing: Architect: Nishant Prabhakar Patil; Engineer: Shah & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANCHAN BUSINESS CENTER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANCHAN BUSINESS CENTER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANCHAN BUSINESS CENTER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.