ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KANCHAN AVENUE AND KANCHAN RATNA

Registered No litigation declared Others project

KANCHAN AVENUE AND KANCHAN RATNA

By NOVEL ESTATE

RG-MH-18389 · RERA P99000076698 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
10 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
105 of 105Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

KANCHAN AVENUE AND KANCHAN RATNA is a Others project by NOVEL ESTATE in Palghar, Maharashtra, registered with MahaRERA as P99000076698 on 21 Jun 2024. Possession is promised by 31 Dec 2029. 0 of the 105 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameKANCHAN AVENUE AND KANCHAN RATNA
  • TypeOthers
  • Location
    • PALGHAR MAHIM ROAD
    • PALGHAR
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000076698
  • ReraGenie IDRG-MH-18389

Builder

  • NameNOVEL ESTATE
  • Entity typePartnership
  • PartnersUMESH VARDICHAND JAIN, RAJESH MAHENDRA MEHTA

Key dates

this monthRegisteredJun 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Jun 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed53 files

Current status

0%0 of 105 units booked
87.2%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO-1 TYPE ANA5508787
BUILDING NO -2 TYPE BNA7618018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

BUILDING NO-1 TYPE A68%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO -2 TYPE B52%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed100

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots100
Closed/Covered22
Open Space78
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO-1 TYPE A145266
BUILDING NO -2 TYPE B82634

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,721 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jun 2025
LandownerVillageDistrict
KAUSHAL JAYANTKUMAR PATELPalghar Palghar
NIRMAL JAYANTKUMAR PATELPalghar Palghar

Approvals and building plan

Sanctioning authorityPALGHAR MUNICIPAL COUNCIL
Permissible FSI6624.05
Proposed, not sanctioned6,624 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR SHIVPRASAD COMMERCIAL COMPLEX MAHIM ROAD PALGHAR WEST 401404
Estimated costRs 16.20 cr
Cost incurredRs 14.12 cr
Work done87.18%
BuildingWingEstimatedIncurred
BUILDING NO-1 TYPE ANARs 9.86 crRs 9.37 cr
BUILDING NO -2 TYPE BNARs 4.63 crRs 3.47 cr
-NARs 1.71 crRs 1.28 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU SHILP
EngineerSHAH & ASSOCIATES
Chartered AccountantCHIRAG K JAIN & CO
Chartered AccountantChirag Jain
Chartered AccountantD.R.AGARWAL & ASSOCIATES
PartnerRole in project
NOVEL ESTATE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 5-Kanchan Avenue(Fy 2025-26).pdf4 May 2026
Withdrawal Update Form 1File: FORM-1 DEC 2025.pdf29 Apr 2026
Withdrawal Update Form 2File: form 2.pdf29 Apr 2026
Withdrawal Update Form 3File: Form 3 Kanchan Avenue and Ratna.pdf29 Apr 2026
Withdrawal Update Form 1File: FORM-1 DEC 2025.pdf17 Mar 2026
Withdrawal Update Form 1File: FORM-1 DEC 2025.pdf17 Mar 2026
Withdrawal Update Form 2File: Form-2.pdf17 Mar 2026
Withdrawal Update Form 2File: FORM-2 DEC 2025.pdf17 Mar 2026
Withdrawal Update Form 3File: FORM 3 CA Novel Estate (1).pdf17 Mar 2026
Withdrawal Update Form 3File: FORM 3 CA Novel Estate (1).pdf17 Mar 2026
Withdrawal Update Form 1File: Form-1.pdf21 Oct 2025
Withdrawal Update Form 2File: Form-2.pdf21 Oct 2025
Withdrawal Update Form 3File: Form-3.pdf21 Oct 2025
Form 5 (FY 2024-2025)File: Novel Estate - Avenue Form 5.pdf10 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Kanchan Avenue.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: sold Unsold Inventory -kanchan Avenue.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold _ Kanchan Avenue_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Estate kanchan avenue.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Estate kanchan avenue.pdf18 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch - Kanchan Avenue AND Ratna 151124.pdf16 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng - Kanchan Avenue AND Ratna 151124.pdf16 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch - Kanchan Avenue AND Ratna 151124.pdf16 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng - Kanchan Avenue AND Ratna 151124.pdf16 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM-3 kANCHAN AVENUE FINAL AFTER CORRECTION_compressed.pdf19 Jun 2024
PAN CardFile: novel estate pan card.pdf14 Jun 2024
Other - TechnicalFile: KANCHAN AVENUE ANNEXURE A.pdf11 Jun 2024
Copy of the legal title reportFile: Title kanchan avenue FINAL_compressed.pdf10 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: KANCHAN AVENUE CC VERIFICATION.pdf10 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Decleartion K A.pdf10 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report Novel Estate.pdf10 Jun 2024
Other - TechnicalFile: KANCHAN AVENUE CC VERIFICATION.pdf10 Jun 2024
Other - LegalFile: Novel Estate Partnership Deed_rotated_compressed.pdf7 Jun 2024
Layout approvalFile: Kanchan Avenue Plan Copy_compressed.pdf31 May 2024
Building plan approvalFile: Kanchan Avenue Plan Copy-2-3.pdf31 May 2024
Copy of Layout Approval (in case of layout)File: Kanchan Avenue Plan Copy_compressed.pdf31 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Kanchan Avenue Plan Copy-2-3.pdf31 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 K A.pdf31 May 2024
Proforma of Agreement for saleFile: Draft First Sale Agreement - Novel estate.pdf31 May 2024
Details of encumbrances concerned to FinanceFile: Declaration Fianance KA.pdf28 May 2024
Details of encumbrances concerned to FinanceFile: Declaration Legal K A.pdf28 May 2024
Details of encumbrances concerned to LegalFile: Declaration Fianance KA.pdf28 May 2024
Details of encumbrances concerned to LegalFile: Declaration Legal K A.pdf28 May 2024
Declaration about Commencement CertificateFile: Declaration CC K A.pdf28 May 2024
Declaration in FORM BFile: Affidivait Cum Declaration Developers K A.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kanchan Avenue and Ratna.pdf28 May 2024
CERSAI detailsFile: Declaration Security Interest K A.pdf28 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure RM KBH.pdf28 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure UJ KBH.pdf28 May 2024
Proforma of Allotment letterFile: Annesure I Allotment Letter K A_compressed.pdf28 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Draft Allotment K A.pdf28 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Kanchan Avenue CC Nagar Parishad Order.pdf23 May 2024

How this compares with Palghar

0%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANCHAN AVENUE AND KANCHAN RATNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR3,200+ in Palghar

2 kmKANCHAN AVENUE AND KANCHCompleted 124Lapsed / revoked 57Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 317 registered projects within 2 km.

Builder: NOVEL ESTATE

NOVEL ESTATE has 1 registration on MahaRERA, including KANCHAN AVENUE AND KANCHAN RATNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if KANCHAN AVENUE AND KANCHAN RATNA is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANCHAN AVENUE AND KANCHAN RATNA?

The registered promoter entity is NOVEL ESTATE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANCHAN AVENUE AND KANCHAN RATNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KANCHAN AVENUE AND KANCHAN RATNA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANCHAN AVENUE AND KANCHAN RATNA?

The professionals named in the filing: Architect: VASTU SHILP; Engineer: SHAH & ASSOCIATES; Chartered Accountant: CHIRAG K JAIN & CO; Chartered Accountant: Chirag Jain; Chartered Accountant: D.R.AGARWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANCHAN AVENUE AND KANCHAN RATNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANCHAN AVENUE AND KANCHAN RATNA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANCHAN AVENUE AND KANCHAN RATNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.