ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / KANAKIA LEVELS

Completed No litigation declared Residential / Group Housing project

KANAKIA LEVELS

By KANAKIA SPACES REALTY PRIVATE LIMITED

RG-MH-09300 · RERA P51800000223 · Last updated on MahaRERA portal: 6 Feb 2023

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2021Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Internal walls, 99%
7Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

KANAKIA LEVELS is a Residential / Group Housing project by KANAKIA SPACES REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000223 on 10 Jul 2017. The registration is recorded completed; possession was promised by 30 Oct 2021. The completion date has moved by 24 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameKANAKIA LEVELS
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000223
  • ReraGenie IDRG-MH-09300

Builder

  • NameKANAKIA SPACES REALTY PRIVATE LIMITED
  • Entity typeCompany
  • Other registrations10 more →
  • Completed11 of 11
  • Declared earlier projects15 →

Key dates

this monthRegisteredJul 2017First promiseOct 2019Revised toOct 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Jul 2017
  • Promised completion30 Oct 2021
  • Revised completionRevised to 30 Oct 2021 (originally 31 Oct 2019)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANAKIA LEVELSNA460000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

KANAKIA LEVELS: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)98%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 6 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes95%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes96%
Open ParkingYes96%
OTHERSYes75%

Parking filed522

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots522
Closed/Covered517
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,647 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHAH HOUSECON PRIVATE LIMITEDBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI61350.24
Proposed, not sanctioned61,350 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch349 BUSINESS POINT BUILDING ANDHERI EAST MUMBAI 400069

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUSHIKESH HADNOORKAR
ArchitectMr.Vishwas Satodia
ArchitectMr. Supasit
ArchitectMR CHARUDATTA V SAMANT
EngineerMr.Nikhil Shanghavi
EngineerMR CHARUDATTA V SAMANT
PartnerRole in project
KANAKIA SPACES REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800002563Oct 2019 → Oct 2020

Reason as filed by the promoterWe have registered the real estate project namely “Kanakia Levels” bearing Registration No. P51800000223 (“Real Estate Project”) with the Maharashtra Real Estate Regulatory Authority (hereinafter referred to as "Authority") under the provisions of Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as "RERA") and the rules made thereunder. The Real Estate Project was assigned Registration No. P51800000223 and Authority has issued Certificate of Registration dated 10.07.2017. The Registration is valid for a period commencing from 10/07/2017 and ending with 31/10/2019. Th

Litigation declared12

CaseCourtStatus
478/2014NATIONAL CONSUMERS DISPUTES REDRESSAL COMMISSIONPENDING FOR FINAL HEARING DISPUTE IN RESPECT OF ONE FLAT FORMING PART OF CO PROMOTER SHARE
917/2014HIGH COURT MUMBAIORDER PASSED IN NOTICE OF MOTION ALONG WITH THIS SUIT CHALLENGED BY FILLING APPEAL IN RESPECT OF ONE
901/2017HIGH COURTFOR ADMISSION
2492/2017NATIONAL CONSUMER DISPUTE REDRESSAL COMMISSIONPENDING FOR EVIDENCE
3536/2017NATIONAL CONSUMERS DISPUTES REDRESSAL COMMISSIONPENDING FOR EVIDENCE
3874/2017NATIONAL CONSUMERS DISPUTES REDRESSAL COMMISSIONPENDING FOR EVIDENCE
1259/2019HIGH COURTFOR ADMISSION
3274/2018HIGH COURTFOR ADMISSION
1355/2019CITY CIVIL COURTDISPUTE IN RESPECT OF ONE FLAT FORMING PART OF CO PROMOTER SHARE
1356/2019CITY CIVIL COURTDISPUTE IN RESPECT OF ONE FLAT FORMING PART OF CO PROMOTER SHARE
812/2017CITY CIVIL COURTSUMMARY SUIT
306/2018METROPOLITAN MAGISTRATE COURTVERIFICATION INQUIRY

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000044363AJAY JANESHWAR GARGKANAKIA SPACES REALTY PVT LTD17/06/2018
CC006000000078808Ajay GargKanakia spaces realty pvt Ltd07/04/2019
CC006000000056501DAYABHAI SUTARIASHAH HOUSECON PVT LTD09/10/2018
CC006000000120983Sandeep Rajesh ThakkerKanakia Spaces Realty Pvt Ltd.20/09/2019
CC006000000192401Subhash Mahadappa PanchgalleKanakia Residential Private Limited03/03/2020
CC006000000192634Prahlad B. SutharKanakia Spaces Realty Pvt Ltd18/02/2020
CC006000000197696Modilal Bapna & AnrKanakia Residential Private limited21/08/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: OC.pdf6 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: levels registration certificate_compressed.pdf23 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf4 Jun 2021
Certificates of CA (Form 5)File: Form 5 Levels RERA.pdf2 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: levels.pdf2 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: levels.pdf2 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels.pdf4 Nov 2019
OtherFile: OC levels 10102019.pdf23 Oct 2019
Certificates of CA (Form 5)File: levels.pdf7 Sep 2019
Details of encumbrancesFile: Index-II.pdf21 Aug 2019
Certificates of CA (Form 3)File: CA Cert Levels 30062019.pdf21 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels Arch Certificate 3062019.pdf16 Aug 2019
Certificates of CA (Form 3)File: Levels RERA Certificate.pdf9 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels Architect Certificate.pdf8 Jul 2019
Details of encumbrancesFile: 01-Zenworld -Index-II.pdf6 Feb 2019
Certificates of CA (Form 3)File: Kanakia Levels Certificate Dec 2018-.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Levels 31-12-18.pdf15 Jan 2019
Certificates of CA (Form 3)File: Levels Certificate 30 September 2018.pdf6 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: kanakia levels 17-10-18.pdf5 Nov 2018
Certificates of CA (Form 5)File: Form 5 Levels RERA.pdf29 Sep 2018
Certificates of CA (Form 3)File: Levels CA Certificate.pdf22 Aug 2018
OtherFile: Part OCC letter 26 07 2018.pdf21 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Levels.pdf28 Jun 2018
Details of encumbrancesFile: Levels_Index-II.pdf20 Jun 2018
Certificates of CA (Form 3)File: Levels Cost Certificate.pdf11 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels Architect Certifcate 31 12 2017.pdf20 Feb 2018
Certificates of CA (Form 3)File: Levels Revised.pdf20 Feb 2018
Certificates of CA (Form 3)File: Levels - CA CertificatE.pdf26 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate kanakia levels.pdf29 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels - Architect Certificate.pdf5 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Levels - Engineer Certificate.pdf5 Jul 2017
Certificates of CA (Form 3)File: REVISED LEVEL CERTIFICATE.pdf5 Jul 2017
Building plan approvalFile: LAYOUT.pdf4 Jul 2017
Layout approvalFile: LAYOUT.pdf4 Jul 2017
Building plan approvalFile: SHEET 1 TO 3.pdf4 Jul 2017
Building plan approvalFile: SHEET 4 TO 6.pdf4 Jul 2017
Building plan approvalFile: SHEET 7 TO 9.pdf4 Jul 2017
Building plan approvalFile: SHEET 10 TO 12.pdf4 Jul 2017
Building plan approvalFile: SHEET 13 TO 15.pdf4 Jul 2017
Building plan approvalFile: SHEET 13 TO 15.pdf4 Jul 2017
Building plan approvalFile: SHEET 16 TO 18.pdf4 Jul 2017
Building plan approvalFile: SHEET 19 AND 20.pdf4 Jul 2017
PAN CardFile: KRPL PAN CARD.PDF4 Jul 2017
Copy of the legal title reportFile: Title Certificate Levels.pdf4 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE KANAKIA AND SHAH.pdf4 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf4 Jul 2017
Building Plan Approval (IOD)File: LAYOUT.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 1 TO 3.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 4 TO 6.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 7 TO 9.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 10 TO 12.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 13 TO 15.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 13 TO 15.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 16 TO 18.pdf4 Jul 2017
Building Plan Approval (IOD)File: SHEET 19 AND 20.pdf4 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: malad (levels) CC.pdf4 Jul 2017
Declaration in FORM BFile: Levels - Form B Part 1.pdf4 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels - Form B Part 2.pdf4 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels - Form B Part 3.pdf4 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Levels - Form B Part 4.pdf4 Jul 2017
Proforma of Allotment letterFile: Proforma Allotment Letter and Agreement for Sale.pdf4 Jul 2017

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise8 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WALLSTREET WING BCHAKALA ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 400093211CompletedDec 2017Mar 2017
KANAKIA AROHADATTAPADA ROAD DONGRI OFF VILLAGE KANHERI NEAR LOHANA MARRIAGE HALL BORIVALI EAST MUMBAI 400066183CompletedDec 2017Mar 2017
ZILLION PHASE 2LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070107CompletedDec 2016Late, Jan 2017
BOOMERANG PHASE 2MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 40007256CompletedJun 2015Late, May 2016
ZILLION PHASE 1LBS ROAD JUNCTION CST ROAD BKC ANNEXE MUMBAI 400070100CompletedDec 2014Late, Jul 2015
ATRIUM 2NEXT TO 215 ATRIUM BEHIND COURTYARD BY MARRIOTT ANDHERI KURLA ROAD ANDHERI EAST MUMBAI 40009364CompletedDec 2014Late, Jan 2015
SAMARPAN EXOTICAWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066189CompletedApr 2014Late, Jun 2014
351 ICONWESTERN EXPRESS HIGHWAY ANDHERI EAST MUMBAI 4000699CompletedSep 2013Jul 2013
ANANTABEVERLY PARK MIRA ROAD EAST THANE 40110756CompletedJun 2012Late, Dec 2012
WESTERN EDGE IIWESTERN EXPRESS HIGHWAY BORIVALI EAST MUMBAI 400066152CompletedDec 2011Late, Jul 2012
BOOMERANG PHASE 1MAIN CHANDIVALI FARM ROAD NEAR POWAI ANDHERI EAST MUMBAI 400072159CompletedApr 2010Late, Aug 2010

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANAKIA LEVELS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmKANAKIA LEVELSCompleted 129Lapsed / revoked 84Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 346 registered projects within 2 km.

Builder: KANAKIA SPACES REALTY PRIVATE LIMITED

KANAKIA SPACES REALTY PRIVATE LIMITED has 11 registrations on MahaRERA, including KANAKIA MIAMI and KANAKIA WALLSTREET WING A. Its filings disclose 15 earlier MahaRERA projects: declares 5 of 15 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if KANAKIA LEVELS is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANAKIA LEVELS?

The registered promoter entity is KANAKIA SPACES REALTY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANAKIA LEVELS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KANAKIA LEVELS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KANAKIA LEVELS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANAKIA LEVELS?

The professionals named in the filing: Architect: RUSHIKESH HADNOORKAR; Architect: Mr.Vishwas Satodia; Architect: Mr. Supasit; Architect: MR CHARUDATTA V SAMANT; Engineer: Mr.Nikhil Shanghavi; Engineer: MR CHARUDATTA V SAMANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANAKIA LEVELS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANAKIA LEVELS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANAKIA LEVELS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.