Home / Browse projects / Mumbai Suburban, Maharashtra / MAULI PRIDE

Registered Litigation declared Residential / Group Housing project

MAULI PRIDE

By MAULI SAI DEVELOPERS PVT LTD

RG-MH-10073 · RERA P51800001199 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 6 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 54 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 54 months from the original
25 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
420 of 496Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 124 documents Report an error

MAULI PRIDE is a Residential / Group Housing project by MAULI SAI DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001199 on 27 Jul 2017. Possession is promised by 8 Jul 2027. The completion date has moved by 54 months from the original filing. 76 of the 496 units on this registration are recorded sold or booked, and 25 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAULI PRIDE
  • TypeResidential / Group Housing
  • Location
    • DAFTARY ROAD
    • KURAR VILLAGE
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001199
  • ReraGenie IDRG-MH-10073

Builder

  • NameMAULI SAI DEVELOPERS PVT LTD
  • Entity typeCompany
  • CINU45201MH2004PTC144062
  • GSTIN27AAECM0577F1ZI
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorSUNIL TUKARAM BHARADKAR
  • Other registrations3 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseJan 2023Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2017
  • Promised completion8 Jul 2027
  • Revised completionRevised to 8 Jul 2027 (originally 8 Jan 2023)
  • Buildings3 building records
  • Documents filed124 files

Current status

15%76 of 496 units booked
63.6%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRIDE BUILDING NO 3NA24242279236
PRIDE BUILDING NO 2ABCNA26261070107
PRIDE BUILDING NO 1ANA24241467153

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

PRIDE BUILDING NO 358%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises12%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PRIDE BUILDING NO 2ABC91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PRIDE BUILDING NO 1A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed189

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots189
Closed/Covered189
BuildingClosed/CoveredTotal
PRIDE BUILDING NO 31515
PRIDE BUILDING NO 2ABC108108
PRIDE BUILDING NO 1A6666

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,807 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jun 2026

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI102639.18
Proposed, not sanctioned26,280 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP 1-4, MONICA ARCADE, SUBHASH LANE MALAD EAST MUMBAI 400 097
Estimated costRs 100.90 cr
Cost incurredRs 64.22 cr
Work done63.65%
BuildingWingEstimatedIncurred
PRIDE BUILDING NO 3NARs 33.63 crRs 21.41 cr
PRIDE BUILDING NO 2ABCNARs 33.63 crRs 21.41 cr
PRIDE BUILDING NO 1ANARs 33.63 crRs 21.41 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRASIK HINGOO
ArchitectVarun Kadam
ArchitectMANGESH GOSAVI
EngineerHARESH PATEL
EngineerVINOD CHALKE
Engineerjacob dsouza
EngineerClint Dos Santos
Chartered AccountantHSP&ASSOCIATES
Chartered AccountantDilip
PartnerRole in project
MAULI SAI DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009367Jan 2023 → Jan 2024

Reason as filed by the promoterTHE PROJECT HAS BEEN AMENDED FOR 3 BUILDINGS AS PER DCPR-2034 ON DATED 05.03.2021 BY WAY OF ADDING 1 MORE BUILDING AND EXTENSION IN EXISTING BUILDING NO. 3. AS PER OLD COMPLETION DATE 08.01.2023, 3 BUILDINGS ARE ON THE URGE OF COMPLETION BY SEPTEMBER 2021. WE ARE DELAYED IN COMPLETION OF ONLY 1 BUILDING DUE TO LITIGATION OF 1 SLUM DWELLER EXACTLY AT THE PLINTH AREA OF THAT BUILDING. SECONDLY, CONSIDERING COVID 19 PANDEMIC FROM LAST 1 YEAR WE ARE JUST REQUESTING FOR EXTENSION OF ONE AND HALF YEAR I.E. UPTO 08.07.2024. AS PER NORMS ONLY 1 YEAR EXTENSION IS PERMITTED BUT KINDLY DO EXTENSION FOR O

EXT51800026068Jan 2023 → Jul 2027

Reason as filed by the promoterIn alignment with the updated provisions and functionalities of the new RERA website and regulations, we have devised a strategje plan to leverage the option of deregistration and ro registration for our multi-phase project. Given that this is a multi-phase project, the timelines required to complete it exceed those mentioned in our current extension request. To address this challenge effectively, after securing the requested extension. we plan to deregister the project and subsequently register it in a phased manner, either phase-wise or wing-wise. This strategic approach will allow us to foc

Litigation declared6

CaseCourtStatus
2109/2015City Civil Court DindoshiCLOSED
1211/2016CITY CIVIL COURT DINDOSHIPENDING NEXT DATE GIVEN
AT006000000154544/2023RERA Appellate TribunalOngoing
AT006000000174640/2023RERA Appellate TribunalOngoing
2765/2024Bo,bay High CourtOngoing
3456/2023Bombay City Civil CourtOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000197429YOGESH JOSHIMAULI SAI DEVELOPERS PVT LTD28/06/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Jan 2025

Documents filed124

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: FORM 2A Mauli Pride.pdf19 Aug 2026
Withdrawal Update Form 1File: form 1.pdf6 Aug 2026
Withdrawal Update Form 2File: form 2.pdf6 Aug 2026
Withdrawal Update Form 3File: form 3_compressed (1).pdf6 Aug 2026
Form 1File: FORM 1_Pride 2ABC_June 2025.pdf22 Jun 2026
Form 2File: Form 2 Mauli Pride June 25_0001.pdf22 Jun 2026
Form 3File: Form 3_Pride 2ABC_June 2025_0001.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Inventory.pdf22 Jun 2026
Form 1File: FORM 1_Pride 2ABC_SEPT 2025 (1).pdf22 Jun 2026
Form 2File: Form 2 Mauli Pride Sep 25_0001.pdf22 Jun 2026
Form 3File: Form 3_Pride 2ABC_Sept 2025_0001.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Inventory.pdf22 Jun 2026
Form 1File: FORM 1_Pride 2ABC_DEC 2025.pdf22 Jun 2026
Form 2File: Form 2 Mauli Pride Dec 25_0001.pdf22 Jun 2026
Form 3File: Form 3_Pride 2ABC_Dec 2025_0001.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Inventory.pdf22 Jun 2026
Form 1File: FORM 1_Pride 2ABC_MARCH 2026.pdf22 Jun 2026
Form 2File: Form 2 Mauli Pride March 26 1_0001.pdf22 Jun 2026
Form 3File: Form 3_Pride 2ABC_March 2026_0001.pdf22 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Inventory.pdf22 Jun 2026
Disclosure of sold/ booked inventoryFile: Inventory disclosure.pdf18 Mar 2025
Declaration in FORM BFile: Form B.pdf12 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf12 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: Architect form 4 and OC declaration.pdf11 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Architect form 4 and OC declaration.pdf10 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form -4 scan_final.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf1 Feb 2025
Certificates of CA (Form 3)File: form 3 (3).pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf31 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 PRIDE.pdf4 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc.pdf4 Jan 2025
Certificates of CA (Form 3)File: FORM 3.pdf12 Dec 2024
Certificates of CA (Form 3)File: FORM 3 FINAL.pdf12 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Form B_ Bank Letter.pdf12 Dec 2024
Declaration in FORM BFile: FORM B.pdf6 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31 MARCH 2024.pdf6 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30 JUNE 24.pdf6 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30 SEPT 24.pdf6 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30 SEPT 2024.pdf6 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30 JUNE 24.pdf6 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 31 MARCH 2024.pdf6 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: PRIDE CC.pdf6 Dec 2024
Declaration about Commencement CertificateFile: DECLARATION OF CC.pdf6 Dec 2024
CERSAI detailsFile: CERSAI LETTER.pdf6 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A BANK LETTER.pdf6 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf6 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B_Bank Letter.pdf6 Dec 2024
Building plan approvalFile: 2_rotated.pdf17 May 2024
Building plan approvalFile: 3_rotated.pdf17 May 2024
Building plan approvalFile: 4_rotated.pdf17 May 2024
Building plan approvalFile: 5_rotated.pdf17 May 2024
Building plan approvalFile: 6_rotated.pdf17 May 2024
Building plan approvalFile: 7_rotated.pdf17 May 2024
Building plan approvalFile: 8_rotated.pdf17 May 2024
Layout approvalFile: 1_rotated.pdf17 May 2024
Building plan approvalFile: IOA 2021 BLDG-2.pdf17 May 2024
Copy of Layout Approval (in case of layout)File: 1_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: IOA 2021 BLDG-2.pdf17 May 2024
Building Plan Approval (IOD)File: 2_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 3_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 4_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 5_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 6_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 7_rotated.pdf17 May 2024
Building Plan Approval (IOD)File: 8_rotated.pdf17 May 2024
Disclosure of sold/ booked inventoryFile: revised disclosure inventory_11zon.pdf17 May 2024
Certificates of CA (Form 3)File: Form 3_pride_11zon.pdf17 May 2024
Declaration about Commencement CertificateFile: Declaration about CC- Pride.pdf14 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf14 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Supervisor Certificate.pdf14 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A- Interest of Parties.pdf14 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Seperate Bank Account.pdf14 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PRIDE CLOSURE.pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: FINAL PRIDE INVENTORY_11zon.pdf24 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PRIDE OC.pdf24 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_1.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: sold unsold Mauli Pride 1ABCDE.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Mauli Pride 2ABC.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: sold unsold Mauli Pride Bldg no 3 1.pdf31 Oct 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MAULI OMKARP51800001198TRIVENI NAGAR, Mumbai Suburban185Jul 2017OngoingJul 2024Registered original: Jul 2023Not delivered
MAULI CLASSICMAULI CLASSIC HAWA MANGAL BAUG NEAR HAWA HRIA MAHAL COLONY PUSHPA PARK DAFTARY ROAD MALAD EAST MUMBAI 400 09766-CompletedFeb 2014Late, Apr 2014

How this compares with Mumbai Suburban

15%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAULI PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KURAR VILLAGE6,700+ in Mumbai Suburban

2 kmMAULI PRIDECompleted 120Lapsed / revoked 85Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 334 registered projects within 2 km.

Builder: MAULI SAI DEVELOPERS PVT LTD

MAULI SAI DEVELOPERS PVT LTD has 4 registrations on MahaRERA, including MAULI OMKAR and MAULI PRIDE. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MAULI PRIDE is delayed beyond 8 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAULI PRIDE?

The registered promoter entity is MAULI SAI DEVELOPERS PVT LTD, a company as per the filing. Its CIN U45201MH2004PTC144062 and GSTIN 27AAECM0577F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAULI PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAULI PRIDE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAULI PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAULI PRIDE?

The professionals named in the filing: Architect: RASIK HINGOO; Architect: Varun Kadam; Architect: MANGESH GOSAVI; Engineer: HARESH PATEL; Engineer: VINOD CHALKE; Engineer: jacob dsouza. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAULI PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAULI PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAULI PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.