KANAKIA SPACES REALTY PRIVATE LIMITED: RERA track record
CIN U70109MH2019PTC331509 · Company · attribution by exact filing name, entity resolution in progress
KANAKIA SPACES REALTY PRIVATE LIMITED has 11 registrations on MahaRERA, including KANAKIA MIAMI and KANAKIA WALLSTREET WING A. Its filings disclose 15 earlier MahaRERA projects: declares 5 of 15 past projects completed on time.
Projects by this developer
Showing all 11 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Kanakia Future City BP51800018113 | POWAI, Mumbai Suburban, 400076 | - | - | 10 Oct 2018 | Completed |
| KANAKIA FUTURE CITY DP51800017413 | POWAI, Mumbai Suburban, 400076 | - | - | 9 Aug 2018 | Completed |
| KANAKIA HOLLYWOODP51800000123 | Andheri, Mumbai Suburban, 400061 | - | - | 5 Jul 2017 | Completed |
| KANAKIA LEVELSP51800000223 | Borivali, Mumbai Suburban, 400097 | - | - | 10 Jul 2017 | Completed |
| KANAKIA MIAMIP51900000206 | 400016 | - | - | 10 Jul 2017 | Completed |
| KANAKIA PARISP51800000122 | Andheri, Mumbai Suburban, 400052 | - | - | 5 Jul 2017 | Completed |
| KANAKIA RAINFORESTP51800000224 | Andheri, Mumbai Suburban, 400059 | - | - | 10 Jul 2017 | Completed |
| KANAKIA SEVENSP51800000388 | Andheri, Mumbai Suburban, 400059 | - | - | 15 Jul 2017 | Completed |
| KANAKIA WALLSTREET WING AP51800000121 | Andheri, Mumbai Suburban, 400093 | - | - | 5 Jul 2017 | Completed |
| KANAKIA ZENWORLD PHASE IP51800008343 | KANJURMARG, Mumbai Suburban, 400042 | - | - | 18 Aug 2017 | Completed |
| KANAKIA ZENWORLD PHASE IIP51800022936 | KANJURMARG, Mumbai Suburban, 400042 | - | - | 5 Nov 2019 | Completed |
What this promoter declares as its own experience
KANAKIA SPACES REALTY PRIVATE LIMITED declares experience on 15 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| BOOMERANG PHASE 1 | 30 Apr 2010 | 26 Aug 2010 | +4 months |
| WESTERN EDGE II | 31 Dec 2011 | 30 Jul 2012 | +7 months |
| ANANTA | 30 Jun 2012 | 5 Dec 2012 | +5 months |
| 351 ICON | 30 Sep 2013 | 10 Jul 2013 | On time |
| SAMARPAN EXCOTICA | 30 Apr 2014 | 10 Jun 2014 | +1 months |
| SAMARPAN EXOTICA | 30 Apr 2014 | 10 Jun 2014 | +1 months |
| ATRIUM II | 31 Dec 2014 | 5 Jan 2015 | On time |
| ZILLION PHASE 1 | 31 Dec 2014 | 14 Aug 2014 | On time |
| ATRIUM 2 | 31 Dec 2014 | 5 Jan 2015 | On time |
| BOOMERANG PHASE 2 | 30 Jun 2015 | 5 May 2016 | +10 months |
| ZILLION PHASE 2 | 31 Dec 2016 | 3 Jan 2017 | On time |
| KANAKIA AROHA | 31 Dec 2017 | 4 Mar 2017 | On time |
Frequently asked questions
How do I verify KANAKIA SPACES REALTY PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70109MH2019PTC331509 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with KANAKIA SPACES REALTY PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.