ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KALPATARU AVENUE

Registration lapsed No litigation declared Others project

KALPATARU AVENUE

By SHRINATH REALTORS

RG-MH-26268 · RERA P99000008892 · Last updated on MahaRERA portal: 29 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 24 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

KALPATARU AVENUE is a Others project by SHRINATH REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000008892 on 19 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameKALPATARU AVENUE
  • TypeOthers
  • Location
    • Chandrapada
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000008892
  • ReraGenie IDRG-MH-26268

Builder

  • NameSHRINATH REALTORS
  • Entity typePartnership
  • PartnersRAMCHANDRA MAHADEO MHATRE, DEVENDRA KHIMRAJ JAIN, KRANTI TUKARAM GAWAD
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WINGS C, D, ENA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

WINGS C, D, E: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 29 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered1
Open Space7

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,850 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PARSHURAM SHAMRAO PATILVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI3850.0
Proposed, not sanctioned3,380 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAKWANA COMPLEX, V S ROAD VIRAR E

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY NARANG
EngineerSANJAY NARANG
PartnerRole in project
SHRINATH REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000017280Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO BULLET TRAIN PASSING SOME PART OF LAND ACQUIRED BY BULLET TRAIN PROJECT.WE HAVE BY ATTACHED THE COPY OF NEW COMMENCEMENT CERTIFICATE AND LAYOUT WITH OUR APPLICATION.WE HERE BY ALSO ATTACHED THE COPY OF CLEARANCE COPY OF CONSTRUCTION.

EXT99000019119Dec 2022 → Dec 2024

Reason as filed by the promoterDUE TO BULLET TRAIN PROJECT PASSING SOME PART OF OUR LAND ACQUIRED BY BULLET TRAIN PROJECT THEREFORE WE HAVE NOT RECEIVED OC FOR PUR PROJECT KALPATARU AVENUE BUT WE HAVE COMPLETED 100% WORK OF CONSTRUCTION ,SO I REQUEST YOU TO PLEASE GRANT ME EXTENSION CERTIFICATE UPTO 31/12/2024.WE NEED THIS EXTENSION FOR AQUIRE OC FROM GOVERMENT AUTHORITY.I REQUEST YOU TO PLEASE GRANT ME EXTENSION CERTIFICATE AS SOON AS POSSIBLE.

EXT99000013165Dec 2022 → Jun 2023

Reason as filed by the promoterDue to bullet train passing some part of land acuired by bullet train project we have received the new COMMENCEMENT CERTIFICATE On (17/05/2022).therefore we request you to to grant Extension for our project Kalpataru avenue,survey no:6/1/B/2 Upto 30/06/2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23_compressed.pdf29 Jun 2024
Certificates of CA (Form 3)File: form 3 new_compressed.pdf15 Jun 2024
Declaration in FORM BFile: FORM B_compressed.pdf11 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf11 May 2024
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD INVENTORY.pdf11 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf20 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: FORM 2A.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE.pdf20 Jan 2023
Certificates of CA (Form 3)File: FORM 3.pdf20 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf20 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf6 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3.pdf6 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2.pdf6 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4.pdf6 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1-30092021.pdf20 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2_30092021.pdf20 Feb 2022
Certificates of CA (Form 3)File: FORM_3-30092021.pdf20 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-DT-30_06_2021_.pdf6 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2-DT-30_06_2021.pdf12 Jan 2022
Certificates of CA (Form 3)File: FORM-3-DT-30_06_2021.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SHRINATH REALTORS_form5_31_03_20.pdf28 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SHRINATH REALTORS_form5_31_03_21.pdf28 Nov 2021
Certificates of CA (Form 3)File: SHRINATH REALTORS-FORM-3.pdf25 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf24 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf24 Jun 2021
Certificates of CA (Form 3)File: FORM-3.pdf24 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf23 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2-31_12_2019.pdf23 Feb 2021
Certificates of CA (Form 3)File: FORM-3.pdf23 Feb 2021
Certificates of CA (Form 3)File: FORM-3.pdf23 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ShrinathReRA_F5_31_3_2019.pdf6 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: SHRINATHRERA_F5_31_3_2018.pdf4 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MARCH2018_FORMNO_2.pdf13 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MARCH2019_FORMNO_2.pdf13 Oct 2019
Certificates of CA (Form 3)File: MARCH2018_FORMNO_3.pdf13 Oct 2019
Certificates of CA (Form 3)File: MARCH2019_FORMNO_3.pdf13 Oct 2019
Certificates of CA (Form 3)File: from 3.pdf29 Jul 2017
Building plan approvalFile: cc.pdf28 Jul 2017
Layout approvalFile: Plan - LAYOUT.pdf28 Jul 2017
Copy of the legal title reportFile: TITLE CLEA.pdf28 Jul 2017
Details of encumbrancesFile: TITLE CLEA.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan - LAYOUT.pdf28 Jul 2017
Building Plan Approval (IOD)File: cc.pdf28 Jul 2017
Declaration in FORM BFile: FORM B-AFFIDAVIT.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITEC.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG.pdf28 Jul 2017
Proforma of Allotment letterFile: FLAT AGREEMENT.PDF28 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALPATARU AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chandrapada3,200+ in Palghar

2 kmKALPATARU AVENUECompleted 34Lapsed / revoked 20Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: SHRINATH REALTORS

SHRINATH REALTORS has 2 registrations on MahaRERA, including KALPATARU AVENUE and NAKODA HEIGHTS 4. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that KALPATARU AVENUE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KALPATARU AVENUE is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALPATARU AVENUE?

The registered promoter entity is SHRINATH REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALPATARU AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KALPATARU AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALPATARU AVENUE?

The professionals named in the filing: Architect: SANJAY NARANG; Engineer: SANJAY NARANG. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALPATARU AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALPATARU AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALPATARU AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.