Home / Browse projects / Thane, Maharashtra / JVM FLORENCIA

Completed No litigation declared Others project

JVM FLORENCIA

By JVM REALTY

RG-MH-24616 · RERA P51700005589 · Last updated on MahaRERA portal: 5 Oct 2021

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

JVM FLORENCIA is a Others project by JVM REALTY in Thane, Maharashtra, registered with MahaRERA as P51700005589 on 11 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameJVM FLORENCIA
  • TypeOthers
  • Location
    • Parkwood road
    • Kasarvadavli
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700005589
  • ReraGenie IDRG-MH-24616

Builder

  • NameJVM REALTY
  • Entity typePartnership
  • PartnersJIGNESH ASHWIN KHILANI, BHADRESH SHANLARLAL KATIRA
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JVM FLORENCIANA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

JVM FLORENCIA: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered20
Open Space3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area750 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1275.0
Proposed, not sanctioned1,274 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHANE WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHIT CONSULTANT
EngineerEPICON CONSULTANTS PVT LTD
PartnerRole in project
JVM REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700005044Dec 2018 → Dec 2020

Reason as filed by the promoterFlorencia project has been developed in accordance with the scheme sanctioned u/s. 20 of ULC Act. The Government of Maharashtra has recently framed rules for exemption of conditions u/s. 20 of ULC Act and further revision in the rules for levy of penalty for extension of time limit are expected in the recent future. The delay in completion of project is due to the policy issues. We are ready to obtain necessary permission at the earliest once the proposed revision in the extension policy becomes applicable. We therefore propose to extend the registration of the project for another period of 1

EXT51700001075Dec 2018 → Dec 2020

Reason as filed by the promoterThe Construction of the Project is fully completed . Accordingly Architect has made application for Completion Certificate on 27th April 2018 with the competent authorities stating that 100 % work has been completed . However, Occupancy Certificate is received for part of the Project on 31/05/2018. This is because full Occupancy Certificate is held up for the reason of ULC order which are as follows: 1. Government of Maharashtra has not scraped ULC Section 20,21. 2. As per our ULC order dt:02/03/2012 we were supposed to handover one flat to ULC Government of Maharashtra. 3. We have already sub

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Feb 2021

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Adobe Scan Sep 29, 2021 (1)_compressed.pdf5 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Adobe Scan Sep 29, 2021_compressed.pdf5 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - Florencia.pdf16 Feb 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Florencia.pdf16 Feb 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy of florencia.pdf29 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Florencia (2).pdf23 Dec 2019
Certificates of CA (Form 5)File: Form 5 Florencia.pdf30 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 Florencia.pdf8 Nov 2019
Certificates of CA (Form 5)File: Form5_Florencia.pdf27 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate Florencia.pdf26 Dec 2018
OtherFile: 0c florencia.pdf18 Jun 2018
OtherFile: Florencia oc Plan.pdf18 Jun 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration for Florencia Soc.pdf26 Apr 2018
Certificates of CA (Form 3)File: RERA Form 3 Florencia.pdf28 Jul 2017
Building plan approvalFile: Florenica Building Approval Plan.pdf27 Jul 2017
Layout approvalFile: Florenica Building Approval Plan.pdf27 Jul 2017
PAN CardFile: PAN JVM Realty.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate (Florencia)121017.pdf27 Jul 2017
Details of encumbrancesFile: No Encumbrance Declaration Florencia Final.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Florenica Building Approval Plan.pdf27 Jul 2017
Building Plan Approval (IOD)File: Florenica Building Approval Plan.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Florencia CC 29042017.pdf27 Jul 2017
Declaration in FORM BFile: Form B Florencia Final.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate Florenica.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer's Certificate Florencia.pdf27 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Florencia RERA.pdf27 Jul 2017
Proforma of Allotment letterFile: Florencia RERA Draft Agreement.pdf27 Jul 2017
OtherFile: Authority Letter Form B Florencia Final.pdf27 Jul 2017
OtherFile: Declaration of Parking FLORENCIA Final.pdf27 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JVM FLORENCIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kasarvadavli7,600+ in Thane

2 kmJVM FLORENCIACompleted 78Lapsed / revoked 26Other 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: JVM REALTY

JVM REALTY has 2 registrations on MahaRERA, including JVM FLORENCIA and JVMs Equinox. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if JVM FLORENCIA is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JVM FLORENCIA?

The registered promoter entity is JVM REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JVM FLORENCIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JVM FLORENCIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JVM FLORENCIA?

The professionals named in the filing: Architect: ARCHIT CONSULTANT; Engineer: EPICON CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JVM FLORENCIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JVM FLORENCIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JVM FLORENCIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.