Home / Browse projects / Mumbai Suburban, Maharashtra / Janki Heritage
Janki Heritage
By Heritage Lifestyles & Developers Pvt. Ltd.
RG-MH-42575 · RERA P51800046052 · Last updated on MahaRERA portal: 28 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
- Rs 22.75 crore secured on the land, in favour of Aditya Birla Finance Ltd
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Janki Heritage is a Residential / Group Housing project by Heritage Lifestyles & Developers Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046052 on 15 Jun 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 17 of the 52 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameJanki Heritage
- TypeResidential / Group Housing
- Location
- Postal Colony
- Chembur
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800046052
- ReraGenie IDRG-MH-42575
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Jun 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed88 files
Current status
Figures as on 28 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Janki Heritage | NA | 12 | 11 | 52 | 0 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Janki Heritage: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 28 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 85% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 95% |
| Water conservation /Rain water harvesting | Yes | 95% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Girish P Gangwani & Pradeep S Shetty | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 23.00 cr | Rs 21.29 cr |
| Janki Heritage | NA | Rs 13.52 cr | Rs 7.69 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Constructive India |
| Engineer | Vishwakarma Enterprises |
| Chartered Accountant | Shayam C. Agarwal & Co. |
| Chartered Accountant | N.K KALRA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Heritage Lifestyles & Developers Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAPPLING FOR OCCUPANCY CERTIFICATE
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503960 | Sutha Rajaram Reddiar | Heritage Lifestyles & Developers Pvt. Ltd. | 11/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 JANKI HERITAGE.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: form 2 janki_compressed.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: JANKI 3 QPR_compressed.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: JANKI 3 QPR_compressed.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: JANKI HERITAGE ANNEXURE A FORM `1 ARCHITECT CERTIFICATE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 1File: JANKI HERITAGE ANNEXURE A FORM `1 ARCHITECT CERTIFICATE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 1File: JANKI HERITAGE ANNEXURE A FORM `1 ARCHITECT CERTIFICATE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: FORM 2 JANKI HERITAGE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: FORM 2 JANKI HERITAGE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: FORM 2 JANKI HERITAGE.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: Janki CA july- sept.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: Janki CA july- sept.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: Janki CA july- sept.pdf | 18 Nov 2025 |
| Form 3File: JANKI HERITAGE CA CERTIFICATE Q4_compressed.pdf | 10 Jul 2025 |
| Form 1File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE Q4.pdf | 10 Jul 2025 |
| Form 2File: JANKI HERITAGE ANNEXURE B FORM 2.pdf | 10 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY q4.pdf | 10 Jul 2025 |
| Form 3File: janki.pdf | 10 Jul 2025 |
| Form 2File: JANKI HERITAGE ANNEXURE B FORM 2 ENGINEER'S CERTIFICATE_1.pdf | 10 Jul 2025 |
| Form 1File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE (2).pdf | 10 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORYq3.pdf | 10 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE Q4.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JANKI HERITAGE CA CERTIFICATE Q4_compressed.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JANKI HERITAGE ANNEXURE B FORM 2.pdf | 19 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: JANKI HERITAGE.PDF | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: JANKI HERITAGE ANNEXURE C FORM 2A.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE (2).pdf | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: janki.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JANKI HERITAGE ANNEXURE B FORM 2 ENGINEER'S CERTIFICATE_1.pdf | 3 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Janki.pdf | 22 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A.pdf | 21 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: 1589391227NoteSheet_18309_signed janki.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY (2).pdf | 15 Jan 2025 |
| Declaration in FORM BFile: form B NEW.pdf | 3 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE.pdf | 5 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant's Certificate (Form-3) Janki Heritage_compressed.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JANKI CA.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JANKI HERITAGE ANNEXURE B FORM 2 ENGINEER CERTIFICATE.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PDF.pdf | 5 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: janki further CC.pdf | 5 Dec 2024 |
| Building plan approvalFile: Drawing 14-09-2023.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing 14-09-2023.pdf | 12 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: final full CC (2) JANKI.pdf | 10 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANNEXURE B FORM 2 ENGINEERS CERTIFICATE.pdf | 4 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant's Certificate (Form-3) Janki Heritage.pdf | 4 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Janki Heritage.pdf | 30 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE JANKI.pdf | 14 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE JANKI.pdf | 14 Feb 2024 |
| CERSAI detailsFile: CERSAI MORTGAGE.pdf | 9 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JANKI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf | 27 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Janki Heritage Engineer Certificate.pdf | 27 Jan 2024 |
| Proforma of Agreement for saleFile: agreement for sale janki.pdf | 2 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 11 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS CERTIFICATE.pdf | 11 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JANKI HERTAGE CA CERTIFICATE.pdf | 11 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - JANKI_.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Janki Heritage - Encumbrance Certificate.pdf | 23 Nov 2022 |
| Details of encumbrances concerned to LegalFile: Janki Heritage - Encumbrance Certificate.pdf | 23 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANNEXURE A FORM 1 ARCHITECT CERTIFICATE JANKI HERITAGE.pdf | 31 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B FORM-2 ENGINEER'S CERTIFICATE.PDF | 31 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Annexure C FORM-2-A ENGINEER'S CERTIFICATE.PDF | 31 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Janki Heritage_.pdf | 31 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANNEXURE A FORM 1 ARCHITECT CERTIFICATE (3).pdf | 13 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.PDF | 13 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Janki Heritage CA Certificate.pdf | 13 Aug 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 2328705_FirstCC_signed (1).pdf | 1 Jun 2022 |
| Declaration about Commencement CertificateFile: Format - D.pdf | 1 Jun 2022 |
| Layout approvalFile: IOD LETTER JANKI HERITAGE.pdf | 20 May 2022 |
| Building plan approvalFile: JANKI IOD APPROVED Drawing JANKI HERITAGE_page-0001.pdf | 20 May 2022 |
| Building plan approvalFile: JANKI IOD APPROVED Drawing JANKI HERITAGE_page-0002.pdf | 20 May 2022 |
| PAN CardFile: HLDPL PAN.pdf | 20 May 2022 |
| Copy of the legal title reportFile: Legal Title Report - Plot No 29.pdf | 20 May 2022 |
| Copy of the legal title reportFile: Legal Title Report - Plot No 30A.pdf | 20 May 2022 |
| Copy of the legal title reportFile: Legal Title Report - Plot No 30B.pdf | 20 May 2022 |
| Details of encumbrancesFile: Self Declaration Regarding Encumbrance.pdf | 20 May 2022 |
| Copy of Layout Approval (in case of layout)File: IOD LETTER JANKI HERITAGE.pdf | 20 May 2022 |
Promoter's earlier projects10
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Redevelopment of Apsara CHSL | Plot No 117 Road No 21 Chembur East Mumbai 400071 | 32 | Completed | Dec 2019 | Late, Feb 2022 |
| Redevelopment of GKW SE CHSL | PLOT NO 02 Off Khandelwal Marg Opp Usha Nagar Post Office Bhandup West Mumbai 400078 | 102 | Completed | May 2019 | Late, Dec 2020 |
| Redevelopment of TSN CHSL | Plot Nos 24 and 41 Padmavati Devi Marg Opp IIT Market Gate Powai Mumbai 400070 | 37 | Completed | Mar 2019 | Late, Dec 2020 |
| Redevelopment of Chembur Sandhya CHSL | Plot No 57 B Road No 2 Pestom Sagar Chembur Mumbai 400089 | 21 | Completed | Dec 2018 | Late, Aug 2021 |
| Redevelopment of Bhishen Bharti | Plot No 538 11th Road Chembur Mumbai 400 071 | 10 | Completed | Sep 2018 | Late, Dec 2018 |
| Heritage Castle | Plot No 121 Sindhi Society Chembur Mumbai400071 | 21 | Completed | Sep 2016 | Late, Nov 2016 |
| Mahalaxmi Heritage | Plot No 159 A Central Avenue Road Chembur mumbai 400 071 | 26 | Completed | Dec 2015 | Late, Feb 2016 |
| Amar Villa Heritage | Plot No 375 Road No 9 Chembur Mumbai 400071 | 20 | Completed | Dec 2015 | Feb 2011 |
| Krishna Heritage | Plot no 146 Road No 14 Chembur Mumbai 400071 | 14 | Completed | Oct 2015 | Late, Dec 2015 |
| Sringar Heritage | Plot no 209 11th Road Chembur Mumbai 400071 | 24 | Completed | May 2010 | Late, Jul 2010 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Janki Heritage on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 467 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Heritage Lifestyles & Developers Pvt. Ltd.
Heritage Lifestyles & Developers Pvt.Ltd. has 5 registrations on MahaRERA, including Redevelopment of Apsara CHS Ltd. and Redevelopment of Tirandaz Subha Niketan CHS Ltd.. Its filings disclose 18 earlier MahaRERA projects: declares 0 of 18 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Janki Heritage shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Janki Heritage is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Janki Heritage?
The registered promoter entity is Heritage Lifestyles & Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Janki Heritage?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Janki Heritage?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Janki Heritage?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Janki Heritage?
The professionals named in the filing: Architect: Constructive India; Engineer: Vishwakarma Enterprises; Chartered Accountant: Shayam C. Agarwal & Co.; Chartered Accountant: N.K KALRA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Janki Heritage?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.