ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / JAI BLISS

Registered No litigation declared Residential / Group Housing project

JAI BLISS

By JAI CONSTRUCTIONS

RG-MH-16852 · RERA P52100027040 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 30 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 91%
16 of 36Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

JAI BLISS is a Residential / Group Housing project by JAI CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100027040 on 10 Nov 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 20 of the 36 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameJAI BLISS
  • TypeResidential / Group Housing
  • Location
    • -
    • RAVET
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027040
  • ReraGenie IDRG-MH-16852

Builder

  • NameJAI CONSTRUCTIONS
  • Entity typePartnership
  • PartnersMANISH REWACHAND WADHIYA, DILIP REWACHAND WADHIYA

Key dates

this monthRegisteredNov 2020First promiseJun 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Nov 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed86 files

Current status

56%20 of 36 units booked
52.4%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA5528028
BUILDING BNA43808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 91%.

BUILDING A67%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises91%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.87%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING B61%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.55%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17
BuildingClosed/CoveredTotal
BUILDING A1212
BUILDING B55

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,899 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jul 2025
LandownerVillageDistrict
MRS. SUJATA NILESH BORATEWadgaon BkPune
MR. BHAGWAT ZAGU THOKEPimpri Chinchawad (M Corp.)Pune
MRS. SADHANA BHAGWAT THOKEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal corporation
Permissible FSI3033.13
Proposed, not sanctioned1,533 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPIMPRI-CHINCHWAD, PUNE
Estimated costRs 8.50 cr
Cost incurredRs 4.45 cr
Work done52.35%
BuildingWingEstimatedIncurred
BUILDING ANARs 3.75 crRs 2.02 cr
BUILDING BNARs 3.75 crRs 2.02 cr
-NARs 1.00 crRs 41.17 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISION ASSOCIATES
EngineerDELTACOM STRUCTURES CONSULTANAT
EngineerNikhil Khandge
EngineerVijay Khandge
EngineerVicky Pawar
Chartered AccountantANAND JETHANI AND CO
Chartered AccountantNPSR and Associates
Chartered AccountantGanesh sunil Mandlecha
PartnerRole in project
JAI CONSTRUCTIONS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024105Jun 2024 → Jun 2025

Reason as filed by the promoterWe mentioned date of Completion of the project as 30.06.2024, we would like to correct it as 29.06.2025. Hence we are applying for making suitable changes to our project details.

EA07082502321Jun 2024 → Dec 2026

Reason as filed by the promoterWe, Jai Construction, respectfully submit this request for an extension of till 31.12.2026 for the completion of our project, Jai Bliss, registered under MahaRERA No. P52100027040. As per the directives received, we are attaching CPM and PERT under document tab.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000258909BHAGWAT ZAGU THOKEM/S JAI CONSTRUCTION25/05/2023
CC12600378Soni Satish RohraJAI CONSTRUCTIONS20/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Q1 (2).pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q1.pdf18 Jul 2026
Withdrawal Update Form 3File: FORM 3 WITH SIGN Q1_removed (1).pdf18 Jul 2026
Withdrawal Update Form 1File: FORM 1 Q3.pdf16 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q3.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q4.pdf16 Jul 2026
Withdrawal Update Form 3File: FORM 3 WITH SIGN Q3_removed.pdf16 Jul 2026
Withdrawal Update Form 3File: FORM 3 WITH SIGN Q4_removed.pdf16 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf15 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q2.pdf15 Jul 2026
Withdrawal Update Form 3File: FORM 3 WITH SIGN Q2..pdf15 Jul 2026
Form 5 (FY 2024-2025)File: form 5 with sign.pdf29 Sep 2025
Form 2A (FY 2020-2021)File: Form 2A (2020-21).pdf16 Aug 2025
Form 2A (FY 2021-2022)File: Form 2A (2021-22).pdf16 Aug 2025
Form 2A (FY 2023-2024)File: Form 2A (2023-24).pdf16 Aug 2025
Form 2A (FY 2022-2023)File: Form 2A (2022-23).pdf16 Aug 2025
Form 2A (FY 2024-2025)File: Form 2A (2024-25).pdf16 Aug 2025
Form 5 (FY 2020-2021)File: Form 5 Jai Constructions 1-4-20 To 31-4-21 sign.pdf16 Aug 2025
Form 5 (FY 2021-2022)File: Form 5 Jai Constructions 1-4-21 To 31-3-22 sign.pdf16 Aug 2025
Form 5 (FY 2022-2023)File: Form 5 Jai Constructions 1-4-22 To 31-3-23 sign.pdf16 Aug 2025
Form 5 (FY 2023-2024)File: Form 5 Jai Constructions 1-4-23 To 31-3-24 sign.pdf16 Aug 2025
Form 1File: ARCHITECT LETTER _ 31-12-2024.pdf5 Aug 2025
Form 2File: Form 2 Engineer Certificate Q3.pdf5 Aug 2025
Form 3File: FORM 3 Q3 2024-25 with sign_11zon.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Doscloser of statement of sold and unsold as on 30-06-2025.pdf5 Aug 2025
Form 1File: ARCHITECT LETTER _ 31-03-2025.pdf5 Aug 2025
Form 2File: Form 2 Engineer Certificate Q4.pdf5 Aug 2025
Form 3File: FORM 3 Q4 2024-25 with sign_11zon.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Doscloser of statement of sold and unsold as on 30-06-2025.pdf5 Aug 2025
Form 1File: form 1 30-6-2024.pdf30 Jul 2025
Form 2File: Form 2 Engineer Certificate Q1 30062024.pdf30 Jul 2025
Form 3File: Form 3 30 06 2024.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Doscloser of statement of sold and unsold as on 30-6-2024.pdf30 Jul 2025
Form 1File: Form 1.pdf21 Jul 2025
Form 2File: Form 2 Engineer Certificate Q2 30092024.pdf21 Jul 2025
Form 3File: Form 3 30 09 2024.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: Doscloser of statement of sold and unsoled..pdf21 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 06 2024_compressed.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 09 2024_compressed.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Q1 30062024.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Q2 30092024.pdf4 Apr 2025
Declaration in FORM BFile: Form B_compressed.pdf26 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE with sign.pdf26 Jun 2024
CERSAI detailsFile: CERSAI_Search_Report_200311520428_For_Asset_Based_Search_26_06_2024_15_26_28_327.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Jai Constructions 1-4-20 To 31-4-21 sign.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Jai Constructions 1-4-21 To 31-3-22 sign.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Jai Constructions 1-4-22 To 31-3-23 sign.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Jai Constructions 1-4-23 To 31-3-24 sign.pdf26 Jun 2024
Layout approvalFile: Main Layout.pdf24 Jun 2024
Building plan approvalFile: Building A Layout.pdf24 Jun 2024
Building plan approvalFile: Building B Layout.pdf24 Jun 2024
Building plan approvalFile: Building Layout.pdf24 Jun 2024
Copy of Layout Approval (in case of layout)File: Main Layout.pdf24 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Building A Layout.pdf24 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Building B Layout.pdf24 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Layout.pdf24 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate V1.pdf24 Jun 2024
Declaration about Commencement CertificateFile: Format D - Commencement-done.pdf24 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Q4.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineer Certificate for Quality Assurance 21.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineer Certificate for Quality Assurance 22.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineer Certificate for Quality Assurance.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineer Certificate for Quality Assurance 23.pdf24 Jun 2024
Disclosure of sold/ booked inventoryFile: Format Statement Sold_Unsold Inventory.pdf24 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Final_compressed.pdf24 Jun 2024
Proforma of Agreement for saleFile: Agreement.pdf24 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Bank Account-Done.pdf24 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with Allotment letter-done.pdf24 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf7 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR CERTIFICATE.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAI BLISS - CA Certificate_compressed.pdf9 Nov 2020
Declaration in FORM BFile: Promoter Declaration.pdf8 Nov 2020
Layout approvalFile: A building plan_compressed.pdf7 Nov 2020
Building plan approvalFile: B building.pdf7 Nov 2020
PAN CardFile: jai constructions pan.pdf7 Nov 2020
Copy of the legal title reportFile: Search and Title Report 1-8.pdf7 Nov 2020
Copy of the legal title reportFile: Search and Title Report 9-17.pdf7 Nov 2020
Copy of the legal title reportFile: Title declaration.pdf7 Nov 2020

How this compares with Pune

56%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JAI BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

2 kmJAI BLISSCompleted 89Lapsed / revoked 48Other 86Dot size: filed unitsN

Filed coordinates, straight-line distance. 223 registered projects within 2 km.

Builder: JAI CONSTRUCTIONS

JAI CONSTRUCTIONS has 1 registration on MahaRERA, including JAI BLISS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if JAI BLISS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JAI BLISS?

The registered promoter entity is JAI CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JAI BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against JAI BLISS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for JAI BLISS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JAI BLISS?

The professionals named in the filing: Architect: VISION ASSOCIATES; Engineer: DELTACOM STRUCTURES CONSULTANAT; Engineer: Nikhil Khandge; Engineer: Vijay Khandge; Engineer: Vicky Pawar; Chartered Accountant: ANAND JETHANI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAI BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAI BLISS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAI BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.