Home / Browse projects / Palghar, Maharashtra / IPSIT NAVODAY PHASE 4

Registration lapsed No litigation declared Others project

IPSIT NAVODAY PHASE 4

By IPSIT ENTERPRISE

RG-MH-21302 · RERA P99000005724 · Last updated on MahaRERA portal: 7 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 60 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
30 of 44Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 75%
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

IPSIT NAVODAY PHASE 4 is a Others project by IPSIT ENTERPRISE in Palghar, Maharashtra, registered with MahaRERA as P99000005724 on 11 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 60 months from the original filing.

At a glance

Project

  • NameIPSIT NAVODAY PHASE 4
  • TypeOthers
  • Location
    • OFF OLD SATPATI MARG
    • PALGHAR
    • Shirgaon
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000005724
  • ReraGenie IDRG-MH-21302

Builder

  • NameIPSIT ENTERPRISE
  • Entity typePartnership
  • PartnerSUMATI DATTATRAY GADKARI
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live5 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Dec 2018)
  • Buildings4 building records
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 3NA60000
BUILDING NO 4NA60000
BUILDING NO 7NA60000
BUILDING NO 8NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 7 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 75%.

BUILDING NO 371%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 479%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
BUILDING NO 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
BUILDING NO 877%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16
BuildingClosed/CoveredTotal
BUILDING NO 344
BUILDING NO 444
BUILDING NO 744
BUILDING NO 844

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,313 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5191.52
Proposed, not sanctioned5,192 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBLUE GALAXY C S ROAD NEAR JARI MARI GARDEN DAHISAR EAST MUMBAI 400068

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU SHILP
PartnerRole in project
IPSIT ENTERPRISE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000001320Dec 2018 → Dec 2021

Reason as filed by the promoterDue to Shortage of sand and Raw Material and Non-Release of part payment from NBFC'S Bank from 4 months which was beyond our control. We were unable to give possession on the promised date. We request you to please grant us extension till 31st October 2019.

EXT99000005832Dec 2018 → Dec 2021

Reason as filed by the promoterDUE TO SHORTAGE OF SAND AND RAW MATERIAL AND FINANCIAL CRISES WE WERE UNABLE TO COMPLETE THE PROJECT ON TIME. WE WOULD LIKE TO REQUEST MAHARERA THAT WE WILL BE REQUIRING EXTENSION TILL DEC 2021. WE HAVE TAKEN CONSENT FROM THE SOLD ALLOTTES.

EXT99000016870Dec 2018 → Dec 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jun 2024

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Navoday Bld No 8 1st To 4th.pdf7 Jun 2024
Layout approvalFile: B no 7 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Layout approvalFile: B no 4 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Copy of Layout Approval (in case of layout)File: Navoday Bld No 8 1st To 4th.pdf7 Jun 2024
Copy of Layout Approval (in case of layout)File: B no 7 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Copy of Layout Approval (in case of layout)File: B no 4 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Navoday Bld No 8 1st To 4th.pdf7 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B no 7 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B no 4 Ground floor plan and 1st to 4th floor.pdf7 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PHASE 4.pdf14 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf12 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2-form 5 2021 to 2022.pdf8 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3-engineer form 2A 2021-22 final.pdf8 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2-form 5 2021 to 2022.pdf8 Jul 2023
Declaration about Commencement CertificateFile: 2-cc declaration.pdf17 Jun 2023
Disclosure of sold/ booked inventoryFile: 3-sold unsold inventory.pdf17 Jun 2023
CERSAI detailsFile: 1-Cersai.pdf17 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annexure F 2020 to 2021.pdf16 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf7 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf5 Jun 2023
Certificates of CA (Form 3)File: Form 3 Navoday Phase 4-30092021.pdf15 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: PHASE 4.pdf7 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Navoday Phase 4.pdf7 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PHASE - 4.pdf4 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: phase 4 july21 to sep21.pdf2 Oct 2021
Certificates of CA (Form 3)File: Form 3 Navoday Phase 4-30062021.pdf30 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SITE SUPERVISOR PHASE 4.pdf26 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 4 (1)_compressed.pdf24 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Navoday Bldg 03 04 0.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 PHASE 4.pdf26 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PHASE 4.pdf18 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG PHASE 4.pdf18 Sep 2019
Certificates of CA (Form 3)File: CA PHASE 4.pdf18 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: IPSIT NAVODAY PHASE 4 ( ARC ) ok.pdf5 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: IPSIT NAVODAY PHASE 4 ( ENG ) ok.pdf5 Apr 2019
Certificates of CA (Form 3)File: IPSIT NAVODAY PHASE -4 ( C A ) OK.pdf5 Apr 2019
Certificates of CA (Form 3)File: n 4.pdf22 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: navoday phase 4 comp.pdf12 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P4 COMP.pdf17 Nov 2018
Certificates of CA (Form 5)File: form.pdf8 Oct 2018
Certificates of CA (Form 3)File: IPSIT NAVODAY PHASE 4.pdf10 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NAVODAY PHASE IV.pdf20 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG NAVO PHASE IV.pdf20 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH P4.pdf22 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG P4.pdf22 Jun 2018
Certificates of CA (Form 3)File: CA P4 COMP.pdf22 Jun 2018
Certificates of CA (Form 3)File: N4.pdf13 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAVODAY compressed FINAL.pdf3 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: compressed PHASE 4 ARC.pdf25 Dec 2017
Details of encumbrancesFile: no encumbrance.pdf22 Dec 2017
Declaration in FORM BFile: form B phase 4 compressed.pdf22 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PHASE 4 ENG.pdf21 Dec 2017
Certificates of CA (Form 3)File: phase 4 build no 3,4,7,8 CA.pdf21 Dec 2017
Proforma of Allotment letterFile: maha rera navoday.pdf17 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: COMPRESSED ENGG (1).pdf29 Jul 2017
Certificates of CA (Form 3)File: ca phase 4.pdf29 Jul 2017
Proforma of Allotment letterFile: allotment.pdf28 Jul 2017
Proforma of Allotment letterFile: Maha Rera agreement-Umesh Jain-Ipsit Navoday-21-7-17 phase IV.pdf28 Jul 2017
Layout approvalFile: layout plan ipsit.pdf27 Jul 2017
Building plan approvalFile: compressed plans phase 4.pdf27 Jul 2017
PAN CardFile: IE PAN CARD.pdf27 Jul 2017
Copy of the legal title reportFile: navoday title.pdf27 Jul 2017
Details of encumbrancesFile: p4 dec.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: layout plan ipsit.pdf27 Jul 2017
Building Plan Approval (IOD)File: compressed plans phase 4.pdf27 Jul 2017
Declaration in FORM BFile: p4 dec.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p4 archi.pdf27 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 60 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IPSIT NAVODAY PHASE 4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR3,200+ in Palghar

2 kmIPSIT NAVODAY PHASE 4Completed 15Lapsed / revoked 23Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: IPSIT ENTERPRISE

IPSIT ENTERPRISE has 8 registrations on MahaRERA, including IPSIT NAVODAY PHASE 1 and IPSIT NAVODAY PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that IPSIT NAVODAY PHASE 4 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IPSIT NAVODAY PHASE 4 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IPSIT NAVODAY PHASE 4?

The registered promoter entity is IPSIT ENTERPRISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IPSIT NAVODAY PHASE 4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for IPSIT NAVODAY PHASE 4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IPSIT NAVODAY PHASE 4?

The professionals named in the filing: Architect: VASTU SHILP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IPSIT NAVODAY PHASE 4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IPSIT NAVODAY PHASE 4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IPSIT NAVODAY PHASE 4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.