Home / Browse projects / Satara, Maharashtra / INDRADHANU PARK

Completed No litigation declared Residential / Group Housing project

INDRADHANU PARK

By coldstardevelopers

RG-MH-09682 · RERA P52700002422 · Last updated on MahaRERA portal: 28 Nov 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 22 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Nov 2025Possession promisedregistration recorded completed
216 of 308Construction stages doneacross 28 buildings; furthest along: Slabs of Super Structure, 60%
13 of 28Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 209 documents Report an error

INDRADHANU PARK is a Residential / Group Housing project by coldstardevelopers in Satara, Maharashtra, registered with MahaRERA as P52700002422 on 1 Aug 2017. The registration is recorded completed; possession was promised by 30 Nov 2025. The completion date has moved by 22 months from the original filing. 15 of the 28 units on this registration are recorded sold or booked, and 216 of 308 construction stages are filed complete.

At a glance

Project

  • NameINDRADHANU PARK
  • TypeResidential / Group Housing
  • Location
    • wai mandherdevi road
    • village bopardi
    • Bopardi
    • Wai
    • Satara
    • 412803
  • Pincode412803
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700002422
  • ReraGenie IDRG-MH-09682

Builder

  • Namecoldstardevelopers
  • Entity typePartnership
  • PartnersLaxmikant Prabhakar Dandawate, Sandeep Yashvant Mahadik, Amruta Anil Shende, Dhanashree Anand Kulkarni, Anand Arun Kulkarni

Key dates

this monthRegisteredAug 2017First promiseJan 2024Revised toNov 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Aug 2017
  • Promised completion30 Nov 2025
  • Revised completionRevised to 30 Nov 2025 (originally 30 Jan 2024)
  • Buildings28 building records
  • Documents filed209 files

Current status

54%15 of 28 units booked
97.6%Work done, per cost certificate

Figures as on 28 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
101NA22101
102NA22101
103NA22101
104NA22101
105NA22101
106NA22101
107NA22101
108NA22101
109NA22101
110NA22101
111NA22101
112NA22101
113NA22101
114NA22101
201NA22101
202NA22101
203NA22101
204NA22101
205NA22101
206NA22101
207NA22101
208NA22101
209NA22101
210NA22101
211NA22101
212NA22101
213NA22101
214NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 28 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 28 buildings; the table lists the first 20.

216 of 308 construction stages are filed complete across 28 buildings. The stage furthest along is Slabs of Super Structure, at 60%.

10182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10473%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10573%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10773%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10873%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
10973%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11073%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11278%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11473%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
20173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
20273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
2030%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
20473%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
20564%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
20673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,200 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Oct 2025

Approvals and building plan

Sanctioning authoritytown planning office satara
Permissible FSI2434.22
Proposed, not sanctioned2,434 sq m
Buildings approved28
Buildings sanctioned28

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2065 , SADASHIV PETH , SANE GURUJI MARG , GANGAVTARAN APPARTMANT , NEAR SP COLLEGE ,PUNE , MAHARASHT
Estimated costRs 8.06 cr
Cost incurredRs 7.87 cr
Work done97.64%
BuildingWingEstimatedIncurred
-NARs 1.03 crRs 92.91 lakh
106NARs 36.20 lakhRs 36.20 lakh
108NARs 36.20 lakhRs 36.20 lakh
109NARs 36.20 lakhRs 36.20 lakh
110NARs 36.20 lakhRs 33.30 lakh
111NARs 36.20 lakhRs 33.30 lakh
112NARs 36.20 lakhRs 33.30 lakh
105NARs 30.73 lakhRs 30.73 lakh
103NARs 28.73 lakhRs 28.73 lakh
104NARs 28.73 lakhRs 28.73 lakh
107NARs 28.73 lakhRs 28.73 lakh
101NARs 24.16 lakhRs 24.16 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectanand kulkarni
ArchitectANAND a KULKARNI
Engineermitesh suresh kengar
Chartered Accountantdinesh jayant bhave
Chartered AccountantAMAR M ITAGI
PartnerRole in project
coldstardevelopers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700018871Jan 2024 → Jan 2025

Reason as filed by the promotertotal project comprised of 28 units , out of that 18 are completed , 5 units are under construction, site development , water ,drainage, transformer & roads are complete, need extension since there is no booking for the units due to which difficult to complete by 30/01/2024

EXT52700025935Jan 2024 → Nov 2025

Reason as filed by the promoterTotal sanctioned units are 27 as per revised plan approval dt :- 5-04-2022. out of 27 units 21 units work totally completed .. balance 6 units brickwork plaster, plumbing electrical work is complete.. we are giving choice for flooring and toilet tiles to each buyer as pe their choice since as per basic specifications the flooring is 600x600 and the changes in the interior work as per their requirements+ additional electrical work. we have installed transformer on site ( order from mseb to charge the transformer is attached ) , meter installation is in process . all the site development is comp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed209

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 209 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: INDRADHANU COMPLETION CERTIFICATE.pdf28 Nov 2025
Withdrawal Update Form 1File: FORM 2 - ENGINEERS CERTIFICATE-25-11-07-N.pdf25 Nov 2025
Withdrawal Update Form 1File: FORM 1-ARCHITECTS-25-11-07-N.pdf25 Nov 2025
Withdrawal Update Form 2File: FORM 2 - ENGINEERS CERTIFICATE-25-11-07-N.pdf25 Nov 2025
Withdrawal Update Form 2File: FORM 2 - ENGINEERS CERTIFICATE-25-11-07-N.pdf25 Nov 2025
Withdrawal Update Form 3File: form - 3 CA certificate 2025-11-17.pdf25 Nov 2025
Withdrawal Update Form 3File: form - 3 CA certificate 2025-11-17.pdf25 Nov 2025
Form 1File: ARCHITECTS LETTER.pdf21 Nov 2025
Form 2File: ENGINEERS CERTIFICATE.pdf21 Nov 2025
Form 3File: CA LETTER1.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 09-2017.pdf21 Nov 2025
Form 1File: rera -architect letter-mar2018.pdf21 Nov 2025
Form 2File: rera engineerletter-mar2018-min.pdf21 Nov 2025
Form 3File: ca data 03-2018.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 03-2018.pdf21 Nov 2025
Form 1File: rera -architect letter-mar2018.pdf21 Nov 2025
Form 2File: rera engineerletter-mar2018-min.pdf21 Nov 2025
Form 3File: ca data 03-2018.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 03-2018.pdf21 Nov 2025
Form 1File: rera -architect letter-mar2018.pdf21 Nov 2025
Form 2File: rera engineerletter-mar2018-min.pdf21 Nov 2025
Form 3File: ca data 03-2018.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 03-2018.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-2-nov-2021.pdf21 Nov 2025
Form 2File: FORM 2 - ENGINEERS CERTIFICATE-oct-2021.pdf21 Nov 2025
Form 3File: ca letter 3 Nov 2021.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold - booked inventory 21-11-02.pdf21 Nov 2025
Form 1File: FORM 1-ARCHITECTS-22-07-05.pdf21 Nov 2025

How this compares with Satara

54%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 22 months
35%of Satara registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep INDRADHANU PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near village bopardi1,100+ in Satara

Builder: coldstardevelopers

coldstardevelopers has 1 registration on MahaRERA, including INDRADHANU PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if INDRADHANU PARK is delayed beyond 30 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDRADHANU PARK?

The registered promoter entity is coldstardevelopers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDRADHANU PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INDRADHANU PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDRADHANU PARK?

The professionals named in the filing: Architect: anand kulkarni; Architect: ANAND a KULKARNI; Engineer: mitesh suresh kengar; Chartered Accountant: dinesh jayant bhave; Chartered Accountant: AMAR M ITAGI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDRADHANU PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDRADHANU PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDRADHANU PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.