ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / BHADRESHWAR CITY

Registration lapsed No litigation declared Residential / Group Housing project

BHADRESHWAR CITY

By JYOTI CONSTRUCTIONS

RG-MH-24097 · RERA P52700009613 · Last updated on MahaRERA portal: 16 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 17 complaints at MahaRERA
  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
17 of 44Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 90%
144 of 277Units unsoldnot recorded sold or booked
17Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

BHADRESHWAR CITY is a Residential / Group Housing project by JYOTI CONSTRUCTIONS in Satara, Maharashtra, registered with MahaRERA as P52700009613 on 22 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 26 months from the original filing. 133 of the 277 units on this registration are recorded sold or booked, and 17 of 44 construction stages are filed complete. 17 complaints are on record with the regulator.

At a glance

Project

  • NameBHADRESHWAR CITY
  • TypeResidential / Group Housing
  • Location
    • Wai (Rural)
    • Wai
    • Satara
    • 412803
  • Pincode412803
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700009613
  • ReraGenie IDRG-MH-24097

Builder

  • NameJYOTI CONSTRUCTIONS
  • Entity typePartnership
  • PartnerJYOTI NITIN JAGTAP
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseOct 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Oct 2021)
  • Buildings4 building records
  • Documents filed34 files

Current status

48%133 of 277 units booked

Figures as on 16 Mar 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVSHANKAR APARTMENTNA5454054
TRYAMBKESHWAR APARTMENTNA6570070
SADASHIV APARTMENTNA6567067
MAHADEV APARTMENTNA65642286

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 16 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 90%.

SHIVSHANKAR APARTMENT81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
TRYAMBKESHWAR APARTMENT65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
SADASHIV APARTMENT27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MAHADEV APARTMENT0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes31%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4
BuildingClosed/CoveredTotal
SHIVSHANKAR APARTMENT11
TRYAMBKESHWAR APARTMENT11
SADASHIV APARTMENT11
MAHADEV APARTMENT11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,014 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9722.98
Proposed, not sanctioned9,723 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWAI SATARA

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASAD D KASTURE
PartnerRole in project
JYOTI CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700011547Oct 2021 → Dec 2023

Reason as filed by the promoterTWO BUILDING ARE HAND OVER TO CUSTOMER AND REMAING TWO BUILDING WORK IS NEARLY TO COMPLETE FOR HAND OVER AND SOCITY FORMETION WE REQURIRD THIS TIME

Complaints filed with MahaRERA17

Case no.ComplainantRespondentFiled
CC005000000085448Ajit Jagannath KarneNitin Subhedar Jagtap15/04/2021
CC005000000085654Apoorva Labhubhai SanghviJyoti Construction Wai09/06/2021
CC005000000085656Apoorva Labhubhai SanghviJyoti Construction Wai12/06/2021
CC005000000085657Apoorva Labhubhai SanghviJyoti Construction Wai12/06/2021
CC005000000085658Apoorva Labhubhai SanghviJyoti Construction Wai12/06/2021
CC005000000085661Saurin Narotamdas ShahJyoti Construction Wai15/06/2021
CC005000000085662Saurin Narotamdas ShahJyoti Construction Wai15/06/2021
CC005000000085663Saurin Narotamdas ShahJyoti Construction Wai15/06/2021
CC005000000085664Saurin Narotamdas ShahJyoti Construction Wai15/06/2021
CC005000000085665Parag Jitendra GandhiJyoti Construction Wai11/06/2021
CC005000000085666Rupesh Krishnabhi MehtaJyoti Construction Wai11/06/2021
CC005000000085671Karim Shujatali VakilJyoti Construction Wai11/06/2021
CC005000000085672Sandhya Gandhi VakilJyoti Construction Wai11/06/2021
CC005000000198012RAJANIKANT DASHARATHA JAWALAKARJYOTI CONSTRUCTIONS29/12/2022
CC005000000279925Mr. Rajesh Tukaram DhamdhereJyoti Construction Through its Partners a) Mr. Nitin Subhedar Jagtap b) Mrs. Jyoti Nitin Jagtap22/12/2023
CC005000000279926Mrs. Manisha Sunil JagtapJyoti ConstructionThrough its Partners a) Mr. Nitin Subhedar Jagtap b) Mrs. Jyoti Nitin Jagtap22/12/2023
CC005000000279927Mr. Prashant Yashwant IngawaleJyoti ConstructionThrough its Partners a) Mr. Nitin Subhedar Jagtap b) Mrs. Jyoti Nitin Jagtap22/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: SOLD 1.pdf16 Mar 2023
Proforma of Agreement for saleFile: model form of agreement ind.pdf16 Mar 2023
Details of encumbrances concerned to FinanceFile: ENCU.pdf15 Mar 2023
Details of encumbrances concerned to LegalFile: ENCU.pdf15 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf15 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG.pdf15 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 19-20.pdf15 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 20-21.pdf15 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21-22.pdf15 Mar 2023
CERSAI detailsFile: DEC CERSAI.PDF15 Mar 2023
Certificates of CA (Form 3)File: CA.pdf15 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DEC INT.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM NO 5 17-18.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM NO 5 18-19.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM NO 5 19-20.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM NO 5 20-21.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM NO 5 21-22.pdf15 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACC.PDF15 Mar 2023
Deviation Report with respect to Allotment letterFile: DEC DEVI ALLOTMENT.PDF15 Mar 2023
Deviation Report with respect to model copy of AgreementFile: DEC DEVI AGREEMENT.PDF15 Mar 2023
Declaration about Commencement CertificateFile: DEC.pdf24 Nov 2021
Building plan approvalFile: PLAN IOD FINAL.pdf31 Jul 2017
Layout approvalFile: PLAN 5 PDF.pdf31 Jul 2017
PAN CardFile: Pancard 1.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE REPORT PDF.pdf31 Jul 2017
Details of encumbrancesFile: ENCOMBER CERT.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN 5 PDF.pdf31 Jul 2017
Building Plan Approval (IOD)File: PLAN IOD FINAL.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: N A ORDER PDF 3.pdf31 Jul 2017
Declaration in FORM BFile: FORM B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERT.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA CERT.pdf31 Jul 2017
Proforma of Allotment letterFile: PROFORMA OF AGREEMENT.pdf31 Jul 2017

How this compares with Satara

48%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 26 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep BHADRESHWAR CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wai (Rural)1,100+ in Satara

Builder: JYOTI CONSTRUCTIONS

JYOTI CONSTRUCTIONS has 4 registrations on MahaRERA, including BHADRESHWAR CITY and SADANAND RESIDENCY. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that BHADRESHWAR CITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHADRESHWAR CITY is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHADRESHWAR CITY?

The registered promoter entity is JYOTI CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHADRESHWAR CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BHADRESHWAR CITY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BHADRESHWAR CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHADRESHWAR CITY?

The professionals named in the filing: Architect: PRASAD D KASTURE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHADRESHWAR CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHADRESHWAR CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHADRESHWAR CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.