Home / Browse projects / Satara, Maharashtra / SAKSHISHILP
SAKSHISHILP
RG-MH-10796 · RERA P52700002835 · Last updated on MahaRERA portal: 30 Aug 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- Completion date moved by 21 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAKSHISHILP is a Residential / Group Housing project by SAKSHI SAMUH DEVELOPERS in Satara, Maharashtra, registered with MahaRERA as P52700002835 on 4 Aug 2017. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 21 months from the original filing. 91 of the 136 units on this registration are recorded sold or booked, and 70 of 77 construction stages are filed complete.
At a glance
Project
- NameSAKSHISHILP
- TypeResidential / Group Housing
- Location
- -
- Songirwadi (Rural) (CT)
- Wai
- Satara
- 412803
- Pincode412803
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700002835
- ReraGenie IDRG-MH-10796
Builder
- NameSAKSHI SAMUH DEVELOPERS
- Entity typePartnership
- PartnersANIL LAXMAN SAWANT, SARITA ANIL SAWANT, SACHIN DHONDIBA BELOSHE, ANITA SACHIN BELOSHE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Aug 2017
- Promised completion31 Mar 2024
- Revised completionRevised to 31 Mar 2024 (originally 30 Jun 2022)
- Buildings7 building records
- Documents filed71 files
Current status
Figures as on 30 Aug 2023, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHAKSHISHILP BUILDING C | NA | 6 | 5 | 16 | 0 | 16 |
| SAKSHISHILP BUILDING D | NA | 6 | 5 | 16 | 0 | 16 |
| SAKSHISHILP BUILDING E | NA | 6 | 5 | 16 | 0 | 16 |
| SAKSHISHILP BUILDING F | NA | 6 | 5 | 16 | 0 | 16 |
| SAKSHISHILP BUILDING H | NA | 6 | 5 | 24 | 0 | 24 |
| SAKSHISHILP BUILDING I | NA | 6 | 5 | 24 | 0 | 24 |
| SAKSHISHILP BUILDING G | NA | 6 | 5 | 24 | 0 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 30 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
70 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Podiums (if any), at 0%.
SHAKSHISHILP BUILDING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING F91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING H91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAKSHISHILP BUILDING G91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed7
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SHAKSHISHILP BUILDING C | 1 | 1 |
| SAKSHISHILP BUILDING D | 1 | 1 |
| SAKSHISHILP BUILDING E | 1 | 1 |
| SAKSHISHILP BUILDING F | 1 | 1 |
| SAKSHISHILP BUILDING H | 1 | 1 |
| SAKSHISHILP BUILDING I | 1 | 1 |
| SAKSHISHILP BUILDING G | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRASAD D KASTURE D KASTURE |
| Engineer | SHIVCHAITANYA CONSTRUCTIONS AND ASSOCIATES |
| Engineer | NILESH SAWANT |
| Chartered Accountant | KHAIRE LOKHANDE AND COMPANY LLP |
| Partner | Role in project |
|---|---|
| SAKSHI SAMUH DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter100 % Construction work is completed but around 9 agreement to sale are pending due to expiry of RERA validity. Kindly approve request of extension.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer_Certificate_31-03-2023_Form_2A.pdf | 30 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_June-23_compressed.pdf | 28 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_Form2_June-2023_compressed.pdf | 28 Aug 2023 |
| Certificates of CA (Form 3)File: CA_Certificate_June-2023_compressed.pdf | 28 Aug 2023 |
| Certificates of CA (Form 3)File: 30-06-2022 from 3 _compressed.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: 30-09-2022 from 3 _compressed.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: 31-12-2022 from 3 _compressed.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2023 from 3 _compressed.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2018 from 3 _compressed.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2019 from 3 _compressed.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2020 from 3 _compressed.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2021 from 3 _compressed.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: 31-03-2022 from 3 _compressed.pdf | 3 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2018 from 1 _compressed 02.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2019 from 1 _compressed-03.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21-03-2020 from 1 _compressed-04.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2021 from 1 _compressed-05.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2022 form 1 _compressed-06.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2022 from 1 _compressed-066.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-06-2022 from 1 _compressed-07.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-09-2022 from 1 _compressed-08.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-12-2022 from 1 _compressed-09.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2023 from 1 _compressed-10.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 18_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 19_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 20_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 21_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 22_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sep 22_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate June 22_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec 22_compressed.pdf | 2 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 23_compressed.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 31-03-2018 Form 2A 2017-18.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 31-03-2019 Form 2A 2018-19.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 31-03-2020 Form 2A 2019-20.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate 31-03-2021 Form 2A 2020-21.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Certificate 31-03-2022 Form 2A 2021-22.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate 31-03-2023 Form 2A 2022-23.pdf | 2 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_Inventery_Samuh.pdf | 2 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form_5_2017-2018.pdf | 2 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form_5_2018-2019.pdf | 2 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form_5_2019-2020.pdf | 2 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form_5_2020-2021.pdf | 2 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form_5_2021-2022.pdf | 2 Aug 2023 |
| Declaration in FORM BFile: ilovepdf_jpg_to_pdf(1).pdf | 31 Jul 2017 |
| Declaration in FORM BFile: ilovepdf_jpg_to_pdf(2).pdf | 31 Jul 2017 |
| Declaration in FORM BFile: ilovepdf_jpg_to_pdf(3).pdf | 31 Jul 2017 |
| Declaration in FORM BFile: ilovepdf_jpg_to_pdf.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: MOTG 1.PDF | 27 Jul 2017 |
| Details of encumbrancesFile: MATG 2.PDF | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG SAKSHI 1.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG SAKSHI 2.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA SAKSHI 1.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA SAKSHI 2.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Final for Scanning ALLOTMENT LETTER and agreement.pdf | 27 Jul 2017 |
| Building plan approvalFile: 01-04.pdf | 22 Jul 2017 |
| Building plan approvalFile: 02-04.pdf | 22 Jul 2017 |
| Building plan approvalFile: 03-04.pdf | 22 Jul 2017 |
| Building plan approvalFile: 04-04.pdf | 22 Jul 2017 |
| Layout approvalFile: 01-04.pdf | 22 Jul 2017 |
| PAN CardFile: PAN SAKSHI.PDF | 22 Jul 2017 |
| Copy of the legal title reportFile: search report.PDF | 22 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 01-04.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 01-04.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 02-04.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 03-04.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 04-04.pdf | 22 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SAKSHISHILP on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -1,100+ in Satara
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
SEVEN HILLS
VENKATESWARAA DEVELOPERS PVT LTD
BHADRESHWAR CITY
JYOTI CONSTRUCTIONS
SAKSHI VISHWA PHASE II
M/S SAKSHI NINE BLOSSOM DEVELOPERS
SAKSHI NISARG
SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT
Soil Villa
Soil Properties & Infra India Ltd.
MAITRI TOWER
Maitri Constructions
See every Satara project, with the district possession charts
Builder: SAKSHI SAMUH DEVELOPERS
SAKSHI SAMUH DEVELOPERS has 1 registration on MahaRERA, including SAKSHISHILP. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What does it mean that SAKSHISHILP shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAKSHISHILP is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAKSHISHILP?
The registered promoter entity is SAKSHI SAMUH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAKSHISHILP?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAKSHISHILP?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAKSHISHILP?
The professionals named in the filing: Architect: PRASAD D KASTURE D KASTURE; Engineer: SHIVCHAITANYA CONSTRUCTIONS AND ASSOCIATES; Engineer: NILESH SAWANT; Chartered Accountant: KHAIRE LOKHANDE AND COMPANY LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAKSHISHILP?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.