SAKSHI NISARG

By SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT

RG-MH-71386 · RERA P52700047852 · Last updated on MahaRERA portal: 1 Sep 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedno revision filed
54 of 198Construction stages doneacross 18 buildings; furthest along: External plumbing and external plaster, 80%
193 of 238Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

SAKSHI NISARG is a Others project by SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT in Satara, Maharashtra, registered with MahaRERA as P52700047852 on 28 Nov 2022. Possession is promised by 1 Oct 2027. 45 of the 238 units on this registration are recorded sold or booked, and 54 of 198 construction stages are filed complete.

At a glance

Project

  • NameSAKSHI NISARG
  • TypeOthers
  • Location
    • MAUJE SONGIRWADI
    • Songirwadi (Rural) (CT)
    • Wai
    • Satara
    • 412803
  • Pincode412803
  • RERA no.P52700047852
  • ReraGenie IDRG-MH-71386

Builder

  • NameSAKSHI CONSTRUCTION ANIL LAXMAN SAWANT
  • Entity typeIndividual

Key dates

this monthRegisteredNov 2022PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2022
  • Promised completion1 Oct 2027
  • Revised completionNone
  • Buildings18 building records
  • Documents filed103 files

Current status

19%45 of 238 units booked
31.2%Work done, per cost certificate

Figures as on 1 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW 1NA22101
BUNGALOW 2NA22101
BUNGALOW 3NA22101
BUNGALOW 4NA22101
BUNGALOW 5NA22101
BUNGALOW 6NA22101
BUNGALOW 7NA22101
BUNGALOW 8NA22101
BUNGALOW 9NA22101
BUNGALOW 10NA22101
BUNGALOW 11NA22101
BUNGALOW 12NA22101
BUNGALOW 13NA22101
BUNGALOW 14NA22101
WING ANA9042951
WING BNA101054963
WING CNA11101090109
BANGALOW 15NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building18

As on 1 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 198 construction stages are filed complete across 18 buildings. The stage furthest along is External plumbing and external plaster, at 80%.

BUNGALOW 132%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 232%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 348%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 448%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 548%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 636%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 744%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 848%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 948%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 1048%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 1132%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 1232%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 1332%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 1428%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING A45%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BANGALOW 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed193

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots193
Closed/Covered175
Open Space18
BuildingClosed/CoveredOpen SpaceTotal
WING A57966
WING B57966
WING C61061

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,816 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Aug 2025
LandownerVillageDistrict
SWAPNIL SOPAN SONAWANEPune (CB)Pune

Approvals and building plan

Sanctioning authorityPLANNING TOWN SATARA
Permissible FSI20544.43
Proposed, not sanctioned18,400 sq m
Buildings approved18
Buildings sanctioned18

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP WAI POLICE STATION SONGIRWADI WAI
Estimated costRs 36.60 cr
Cost incurredRs 11.41 cr
Work done31.17%
BuildingWingEstimatedIncurred
WING CNARs 14.00 cr-
WING BNARs 8.43 crRs 1.18 cr
WING ANARs 7.52 crRs 6.78 cr
-NARs 1.79 crRs 26.91 lakh
BANGALOW 15NARs 79.35 lakhRs 12.70 lakh
BUNGALOW 1NARs 29.00 lakhRs 14.79 lakh
BUNGALOW 2NARs 29.00 lakhRs 14.79 lakh
BUNGALOW 3NARs 29.00 lakhRs 29.00 lakh
BUNGALOW 4NARs 29.00 lakhRs 29.00 lakh
BUNGALOW 5NARs 29.00 lakhRs 29.00 lakh
BUNGALOW 6NARs 29.00 lakhRs 14.79 lakh
BUNGALOW 7NARs 29.00 lakhRs 29.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASAD D KASTURE D KASTURE
EngineerAMOL RAOSAHEB KHOTLANDE
EngineerNILESH NARAYAN SAWANT
Chartered AccountantVINAY ARVIND LOKHANDE
Chartered AccountantVINAYAK KHARE & ASSOCIATES
PartnerRole in project
SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 1 Oct 2027

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf1 Sep 2026
Withdrawal Update Form 2File: FORM 2 (2).pdf1 Sep 2026
Withdrawal Update Form 3File: FORM 3 FINAL.pdf1 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A_FY 25-26.pdf27 Aug 2026
Withdrawal Update Form 1File: Sakshi Construction - Architects Certificates Form-1.pdf23 Jul 2026
Withdrawal Update Form 2File: Sakshi Construction - Engineers Certificates Form-2.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf23 Jul 2026
Form 2A (FY 2023-2024)File: Engineer Certificate (Form 2A) 31-03-2024.pdf9 Feb 2026
Form 2A (FY 2024-2025)File: Engineer Certificate (Form 2A) 31-03-2025.pdf9 Feb 2026
Withdrawal Update Form 1File: Form 1 Architect s Certificate Sakshi NisargDec-2025.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Sakshi NisargDec-2025.pdf7 Feb 2026
Withdrawal Update Form 3File: Form -3 CA Sakshi NisargDec-2025.pdf7 Feb 2026
Withdrawal Update Form 1File: Form -1 Architects Certificate Sakshi Nisarg June 2025.pdf5 Feb 2026
Withdrawal Update Form 1File: Form -1 Architect Certificate Sakshi Nisarg Sep 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: Form -2 Engineers Certificate Sakshi Nisarg June 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: Form -2 Engineer Certificate Sakshi Nisarg Sep 2025.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 CA Sakshi Nisarg June 2025.pdf5 Feb 2026
Withdrawal Update Form 3File: Form -3 CA Sakshi Nisarg Sep 2025.pdf5 Feb 2026
Form 1File: FORM 1 31-03-2025.pdf28 May 2025
Form 2File: FORM 2.pdf28 May 2025
Form 3File: FORM 3 31-03-2025_11zon.pdf28 May 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf28 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENG CERTIFICATE.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY_11zon.pdf19 Apr 2025
Declaration about Commencement CertificateFile: Sakshi Nisarg CC Declaration.pdf17 Apr 2025
Layout approvalFile: 1.pdf12 Apr 2025
Layout approvalFile: 2.pdf12 Apr 2025
Building plan approvalFile: 3.pdf12 Apr 2025
Building plan approvalFile: 4.pdf12 Apr 2025
Building plan approvalFile: 5.pdf12 Apr 2025
Building plan approvalFile: 6.pdf12 Apr 2025
Building plan approvalFile: 7__1__rotated_compressed.pdf12 Apr 2025
Copy of Layout Approval (in case of layout)File: 1.pdf12 Apr 2025
Copy of Layout Approval (in case of layout)File: 2.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 7__1__rotated_compressed.pdf12 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Nisarga Dec2024.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Nisarga Dec2024.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Nisarga Dec2024.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Nisarga Sep2024.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Nisarga Sep2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Nisarga Sep2024.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JUNE 2024 NISARG.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23 NISARG.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE NISARG.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE NISARG.pdf12 Aug 2024
Disclosure of sold/ booked inventoryFile: INVENTORY JUNE NISARG.pdf12 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FROM 2A NISARG.pdf27 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM1 MARCH-24_11zon.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2 MARCH-24_11zon.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: INVENTRY MARCH-24_11zon.pdf22 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MARCH-24_11zon.pdf22 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: from 1 nisarg Dec-2023_.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 Nisarg dec-2023.pdf30 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: from 2A Nisarg.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: inve nisarg dec-2023.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: inve nisarg dec-2023.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From_3_nisarg_Dec-2023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NISARG FORM 1 SEP-23.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NISARG FORM 2 SEP-23.pdf10 Nov 2023
Disclosure of sold/ booked inventoryFile: Nisarg_Sold_Inventory_Sep-2023.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nisarg_Form-3_Sep-2023.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_FORM_1_June-2023.pdf14 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate_ June-2023.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: INVENTORY_JUNE-23.pdf14 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_FORM_3_June-2023.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-ARCHITECT_compressed.pdf14 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-ARCHITECT_compressed.pdf14 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-ENGINEER_compressed.pdf14 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER.pdf14 Jun 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf14 Jun 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf14 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (1).pdf14 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA_compressed (1).pdf14 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised CA Certificate - Sakshi Nisarg.pdf19 Oct 2022

How this compares with Satara

19%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep SAKSHI NISARG on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAUJE SONGIRWADI1,100+ in Satara

Builder: SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT

SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT has 1 registration on MahaRERA, including SAKSHI NISARG. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if SAKSHI NISARG is delayed beyond 1 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAKSHI NISARG?

The registered promoter entity is SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAKSHI NISARG?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAKSHI NISARG?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAKSHI NISARG?

The professionals named in the filing: Architect: PRASAD D KASTURE D KASTURE; Engineer: AMOL RAOSAHEB KHOTLANDE; Engineer: NILESH NARAYAN SAWANT; Chartered Accountant: VINAY ARVIND LOKHANDE; Chartered Accountant: VINAYAK KHARE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAKSHI NISARG?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAKSHI NISARG. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAKSHI NISARG to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.