Home / Browse projects / Palghar, Maharashtra / IMPERIAL REGENCY

Registration lapsed No litigation declared Residential / Group Housing project

IMPERIAL REGENCY

By Shree Ganesh Coporation

RG-MH-70616 · RERA P99000034165 · Last updated on MahaRERA portal: 25 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 55%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

IMPERIAL REGENCY is a Residential / Group Housing project by Shree Ganesh Coporation in Palghar, Maharashtra, registered with MahaRERA as P99000034165 on 24 Mar 2022. Possession was promised by 30 Jun 2025 and is now 16 months past that date.

At a glance

Project

  • NameIMPERIAL REGENCY
  • TypeResidential / Group Housing
  • Location
    • Waliv
    • Vasai East
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000034165
  • ReraGenie IDRG-MH-70616

Builder

  • NameShree Ganesh Coporation
  • Entity typePartnership
  • PartnersSanjay Baijnath Gupta, Ajay Baijnath Gupta, Parth Dhananjay Gupta, Prathmesh Sanjay Gupta, Mobataram Lilaji Choudhary, Mohd Afzal Haji Mohd Khan, Masroof Ahmed Rafique Ahmed Shaikh, Naresh Gangaram Mukund, Munir Ahmed Khan, Mahibulla Shaffi Khan, Gangaram Rajlingam Mukund, Mahendra Purohit
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredMar 2022PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Mar 2022
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA60000
B WingNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 55%.

A wing27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Wing87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.55%

Progress on shared amenities15

As on 25 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed112

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots112
Closed/Covered2
Open Space110
BuildingClosed/CoveredOpen SpaceTotal
A wing25557
B Wing05555

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,247 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Tarabai Harishchandra DhumalVasai-Virar City (M Corp)Palghar
Santosh Harishchandra DhumalVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI2644.4
Proposed, not sanctioned2,644 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNalasopara Link road

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHimesh Gupta &Associates
EngineerSeemu Consultancy
Chartered AccountantKothari Jain & Associates
PartnerRole in project
Shree Ganesh Coporation-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Nov 2024

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure -Regency.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure -Regency.pdf25 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shree Ganesh Corporation_Mar24.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - March 2024 SGC March 24.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - June 2024 SGC June 24.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form -2 jan to march.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form -2 sgv june 24.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: sgv disclosure.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: sgv disclosure .pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sgv form-3 _11zon.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3 sgv_11zon.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed _ Imperial Regency.pdf11 Mar 2022
Layout approvalFile: Layout_compressed.pdf9 Mar 2022
Building plan approvalFile: Typical Floor_compressed.pdf9 Mar 2022
PAN CardFile: Co PAN.pdf9 Mar 2022
Copy of the legal title reportFile: Search Report Rera Format _compressed.pdf9 Mar 2022
Details of encumbrancesFile: Encumbrance Declaration .pdf9 Mar 2022
Copy of Layout Approval (in case of layout)File: Layout_compressed.pdf9 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Typical Floor_compressed.pdf9 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 30-12-2021_compressed.pdf9 Mar 2022
Declaration about Commencement CertificateFile: CC Declaration.pdf9 Mar 2022
Declaration in FORM BFile: Form B.pdf9 Mar 2022
CERSAI detailsFile: CERSAI Certificate.pdf9 Mar 2022
Proforma of Allotment letterFile: Imperial Regency Draft.pdf9 Mar 2022
Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf9 Mar 2022

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IMPERIAL REGENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai East3,200+ in Palghar

Builder: Shree Ganesh Coporation

Shree Ganesh Coporation has 2 registrations on MahaRERA, including Imperial Residency and IMPERIAL REGENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that IMPERIAL REGENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IMPERIAL REGENCY is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IMPERIAL REGENCY?

The registered promoter entity is Shree Ganesh Coporation, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IMPERIAL REGENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for IMPERIAL REGENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IMPERIAL REGENCY?

The professionals named in the filing: Architect: Himesh Gupta &Associates; Engineer: Seemu Consultancy; Chartered Accountant: Kothari Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IMPERIAL REGENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IMPERIAL REGENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IMPERIAL REGENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.