Home / Browse projects / Palghar, Maharashtra / IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B
IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B
By SHREE SAI SAMARTH BUILDERS AND DEVELOPERS
RG-MH-52013 · RERA P99000009483 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 52 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B is a Residential / Group Housing project by SHREE SAI SAMARTH BUILDERS AND DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000009483 on 22 Aug 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 52 months from the original filing. 15 of the 37 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameIDEAL AVENUE BUILDING NO 3 TYPE B1D WING B
- TypeResidential / Group Housing
- Location
- MAIN ROAD
- UMROLI
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000009483
- ReraGenie IDRG-MH-52013
Builder
- NameSHREE SAI SAMARTH BUILDERS AND DEVELOPERS
- Entity typePartnership
- PartnersRAJENDRA DEV JAGAT BHUSAN TIWARI, UMA DEVI RAJENDRA DEV TIWARI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2017
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed92 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 3 WING B | NA | 5 | 5 | 24 | 13 | 37 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.
BUILDING NO 3 WING B: 40% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| IDEAL PROPERTIES | Vasai-Virar City (M Corp) | Palghar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 3 WING B | NA | Rs 1.92 cr | Rs 1.79 cr |
| - | NA | Rs 24.00 lakh | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH SATGHARE |
| Architect | RENDER POINT |
| Engineer | Paresh Unnarkar |
| Engineer | MESHRAM & THUKRAL |
| Engineer | CENTRELINE ENGINEERS & CONSULTANTS |
| Chartered Accountant | VIKAS SHUKLA & COMPANY |
| Chartered Accountant | Rinky Gupta & Company |
| Chartered Accountant | AJAYSHUKLA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHREE SAI SAMARTH BUILDERS AND DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs project is not completed we need extension for completion of our project it will be appreciated if you give us a extension period so i can complete my work and i can give possession before expiry date. The Reason for delay was COVID-19 the workers were not available and few workers were available after covid 19 but the work was very slow, so we need extension certificate to complete our project work
Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Also due to Covid project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the p
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Nov 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Nov 2023
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form-2 June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Form-3 June 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 March 2026 (4).pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form-2 March 2026 (3).pdf | 12 May 2026 |
| Withdrawal Update Form 3File: Form 3 March 2026 (1).pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Form-1 Dec 2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 2File: Form-2 Dec 2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 3File: Form-3 Dec 2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 19 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 19 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 24 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 22 Oct 2025 |
| Withdrawal Update Form 1File: form 1.pdf | 22 Oct 2025 |
| Withdrawal Update Form 1File: form 1.pdf | 22 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 Oct 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 22 Oct 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 22 Oct 2025 |
| Withdrawal Update Form 3File: form 320251017_13261584.pdf | 22 Oct 2025 |
| Withdrawal Update Form 3File: form 3.pdf | 22 Oct 2025 |
| Withdrawal Update Form 3File: form 3.pdf | 22 Oct 2025 |
| Form 5 (FY 2024-2025)File: form 5.pdf | 22 Oct 2025 |
| Form 1File: form1.pdf | 16 Oct 2025 |
| Form 2File: form2.pdf | 16 Oct 2025 |
| Form 3File: FORM 3 PDF20241108_15160271.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold and booked20251015_11234058.pdf | 16 Oct 2025 |
| Form 1File: form 1.pdf | 16 Oct 2025 |
| Form 2File: form -2.pdf | 16 Oct 2025 |
| Form 3File: form 320251016_11354381.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold and booked20251015_11234058.pdf | 16 Oct 2025 |
| Form 1File: form 1.pdf | 16 Oct 2025 |
| Form 2File: form-2.pdf | 16 Oct 2025 |
| Form 3File: form 320251016_11405709.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold and booked20251015_11234058.pdf | 16 Oct 2025 |
| Form 1File: form1.pdf | 15 Oct 2025 |
| Form 2File: form2.pdf | 15 Oct 2025 |
| Form 3File: FORM 3 PDF20241108_15092054.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold and booked20251015_11234058.pdf | 15 Oct 2025 |
| Certificates of CA (Form 3)File: FORM 3 PDF20241108_15092054.pdf | 8 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 PDF20241108_15160271.pdf | 8 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form1.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form1.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 31 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 31 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE.pdf | 31 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 PDF.pdf | 31 May 2024 |
| Certificates of CA (Form 3)File: FORM 03_compressed.pdf | 23 Mar 2024 |
| Layout approvalFile: BLUE PRINT.pdf | 16 Nov 2023 |
| Layout approvalFile: Development Agreement 4th Floor.pdf | 16 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: BLUE PRINT.pdf | 16 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: Development Agreement 4th Floor.pdf | 16 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 16 Nov 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect CERTIFICATE.pdf | 16 Nov 2023 |
| Other - LegalFile: Power of Attorney 4th Floor.pdf | 16 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect CERTIFICATE.pdf | 4 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER S CERTIFICATE.pdf | 4 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Quality Assurance Certificate.pdf | 4 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5.pdf | 4 Nov 2023 |
| Declaration about Commencement CertificateFile: Scan20230329202942.pdf | 29 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_11zon.pdf | 29 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (1)_11zon.pdf | 29 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 201920_11zon.pdf | 29 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 202021 (1)_11zon.pdf | 29 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 201920_11zon.pdf | 29 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 202021_11zon.pdf | 29 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate_11zon.pdf | 29 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Scan20230329204651.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 517-18_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 518-19_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 518-19_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 519-20_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 520-21_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 521-22_11zon.pdf | 29 Mar 2023 |
| Copy of the legal title reportFile: Title report 2.pdf | 14 Aug 2017 |
| Copy of the legal title reportFile: Title report 3.pdf | 14 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg certificate.pdf | 14 Aug 2017 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 14 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near UMROLI3,200+ in Palghar
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: SHREE SAI SAMARTH BUILDERS AND DEVELOPERS
SHREE SAI SAMARTH BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B?
The registered promoter entity is SHREE SAI SAMARTH BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B?
The professionals named in the filing: Architect: RAJESH SATGHARE; Architect: RENDER POINT; Engineer: Paresh Unnarkar; Engineer: MESHRAM & THUKRAL; Engineer: CENTRELINE ENGINEERS & CONSULTANTS; Chartered Accountant: VIKAS SHUKLA & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback