Hubtown Seasons - Ardennes
By Joynest Premises Private Ltd
RG-MH-30615 · RERA P51800032784 · Last updated on MahaRERA portal: 30 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Hubtown Seasons - Ardennes is a Residential / Group Housing project by Joynest Premises Private Ltd in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032784 on 29 Jan 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 56 of the 59 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameHubtown Seasons - Ardennes
- TypeResidential / Group Housing
- Location
- R C Marg
- Chembur East
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- RERA no.P51800032784
- ReraGenie IDRG-MH-30615
Builder
- NameJoynest Premises Private Ltd
- Entity typeCompany
- CINU45202MH2008PTC183715
- DirectorsKhilen Shah, Jayeshkumar Mukesh Jain
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Jan 2022
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed99 files
Current status
Figures as on 30 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Seasons A wing | NA | 15 | 14 | 59 | 0 | 59 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
Seasons A wing: 72% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 94% |
Progress on shared amenities15
As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 60% |
| Solid Waste Management And Disposal | Yes | 20% |
| Water conservation /Rain water harvesting | Yes | 20% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Seasons A wing | NA | Rs 36.37 cr | Rs 30.13 cr |
| - | NA | Rs 8.80 cr | Rs 1.56 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AAKAR ARCHITECT (Mr. Amit Pawar) |
| Architect | ARCHITECT HAFEEZ CONTRACTOR |
| Architect | Citygold Management Services Pvt.Ltd |
| Engineer | Rajivan Paramban |
| Chartered Accountant | Anand A Yadav & Associates |
| Chartered Accountant | Sanket Shah |
| Chartered Accountant | Maloo Rathod and Companny |
| Chartered Accountant | Amit Sheth |
| Partner | Role in project |
|---|---|
| Joynest Premises Private Ltd | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed99
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form I P51800032784 - SEASONS A WING (Ardennes).pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: Form II Engineers Certificate - Seasons A wing - March 26.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: SEASONS A WING- Form III signed.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: FORM_1_P51800032784 - SEASONS A WING (Ardennes).pdf | 16 Mar 2026 |
| Withdrawal Update Form 2File: FORM_2_P51800032784 - SEASONS A WING (Ardennes).pdf | 16 Mar 2026 |
| Withdrawal Update Form 3File: FORM III Hubtown Seasons-A 020326 sign (3).pdf | 16 Mar 2026 |
| Withdrawal Update Form 1File: P51800032784 - SEASONS A WING (Ardennes).pdf | 25 Nov 2025 |
| Withdrawal Update Form 2File: ENGINEERIN CERTIFICATE JOYNEST - A wing.pdf | 25 Nov 2025 |
| Withdrawal Update Form 3File: Form-3 Seasons - Ardennes 241125.pdf | 25 Nov 2025 |
| Form 5 (FY 2024-2025)File: A.pdf | 1 Oct 2025 |
| Form 1File: Arch Certificate_Seasons A Wing_June 25.pdf | 16 Aug 2025 |
| Form 2File: Engg Certificate_Seasons A Wing_June 25.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory_ A wing _June 25.pdf | 16 Aug 2025 |
| Form 3File: CA Form III_A Wing_June 25.pdf | 16 Aug 2025 |
| Form 1File: P51800032784 - SEASONS A WING (Ardennes).pdf | 10 Jul 2025 |
| Form 2File: Engineers Certificate Seasons A wing_Mar 25 (1).pdf | 10 Jul 2025 |
| Form 3File: HUBTOWN SEASONS ARDENNES.pdf | 10 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclousre of booked inventory_Mar 25.pdf | 10 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: HUBTOWN SEASONS - ECUADOR CLOUD (1).pdf | 20 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate A wing Seasons.pdf | 17 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING (Ardennes) (1).pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate A wing - Dec 24.pdf | 1 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: WING A.pdf | 29 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Season B wing full CC upto top of 14th floor.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING (Ardennes).pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE A WING.pdf | 21 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate_A Wing_Sept 24.pdf | 21 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE A WING.pdf | 21 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate_A Wing_Sept 24.pdf | 21 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing September 2024.pdf | 8 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - A wing March 2024.pdf | 26 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING (Ardennes).pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - Seasons Wing - A ( 2nd To 13th floor).pdf | 22 Jul 2024 |
| Building plan approvalFile: Sale Wing ABC IOD-28042023.pdf | 9 May 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Sale Wing ABC IOD-28042023.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERIN CERTIFICATE JOYNEST - A wing.pdf | 6 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA Certificate_Seasons A wing_Mar 24.pdf | 6 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing March 2024.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING.pdf | 30 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: B wing FurtherCC-signed.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGEENIRING CERTIFICATE- A wing - Sep 23.pdf | 29 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE -SEASONS - A WING - DEC 23.pdf | 29 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing December 2023.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING (2).pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - A wing March 2023.pdf | 27 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing June 2023.pdf | 2 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing September 2023.pdf | 2 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING.pdf | 17 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering certificate Seasons A wing March 23.pdf | 10 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate - Seasons A wing - June 23.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_QA Certificate_Seasons A Wing_Mar 22.pdf | 10 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING.pdf | 17 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: WING A.pdf | 17 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE A WING - SEASONS SEP 22.pdf | 22 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginners certificate Seasons A wing Dec 22.pdf | 22 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing December 2022.pdf | 21 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 2366641-FurtherCC-signed (1).pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - SEASONS A WING.pdf | 11 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 2366641-FurtherCC-signed.pdf | 8 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Seasons A wing.pdf | 3 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - A wing March 2022.pdf | 31 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 -Seasons Wing A - 2nd to 13th floor.pdf | 30 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing September 2022.pdf | 30 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate - A wing - June 22.pdf | 26 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing June 2022.pdf | 23 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800032784 - Seasons Wing-A.pdf | 8 Nov 2022 |
| Copy of the legal title reportFile: Legal Title Report 21102021 in Form A.pdf | 23 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - A wing March 2022_compressed.pdf | 30 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Seasons A Resi_Arch Cert_Mar 22_0001.pdf | 25 Apr 2022 |
| Layout approvalFile: Layout - wing 'A' in Blue-min.pdf | 19 Jan 2022 |
| Building plan approvalFile: iod hubtown.pdf | 19 Jan 2022 |
| Layout approvalFile: page 2.pdf | 19 Jan 2022 |
| Layout approvalFile: page 3.pdf | 19 Jan 2022 |
| Layout approvalFile: page 4.pdf | 19 Jan 2022 |
| Layout approvalFile: page 5.pdf | 19 Jan 2022 |
| Layout approvalFile: page 6 new-min.pdf | 19 Jan 2022 |
| Layout approvalFile: page 7 new-min.pdf | 19 Jan 2022 |
| Layout approvalFile: page 8 new.pdf | 19 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Layout - wing 'A' in Blue-min.pdf | 19 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: page 2.pdf | 19 Jan 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 99 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Hubtown Seasons - Ardennes on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur East6,700+ in Mumbai Suburban
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Joynest Premises Private Ltd
Joynest Premises Private Ltd has 1 registration on MahaRERA, including Hubtown Seasons - Ardennes. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Hubtown Seasons - Ardennes shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Hubtown Seasons - Ardennes is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Hubtown Seasons - Ardennes?
The registered promoter entity is Joynest Premises Private Ltd, a company as per the filing. Its CIN U45202MH2008PTC183715 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Hubtown Seasons - Ardennes?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Hubtown Seasons - Ardennes?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Hubtown Seasons - Ardennes?
The professionals named in the filing: Architect: AAKAR ARCHITECT (Mr. Amit Pawar); Architect: ARCHITECT HAFEEZ CONTRACTOR; Architect: Citygold Management Services Pvt.Ltd; Engineer: Rajivan Paramban; Chartered Accountant: Anand A Yadav & Associates; Chartered Accountant: Sanket Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Hubtown Seasons - Ardennes?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback