Home / Browse projects / Palghar, Maharashtra / HDIL PARADISE CITY SECTOR 2
HDIL PARADISE CITY SECTOR 2
By HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
RG-MH-11297 · RERA P99000012539 · Last updated on MahaRERA portal: 9 Apr 2019
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 85 months past the filed date
- 14 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HDIL PARADISE CITY SECTOR 2 is a Others project by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD in Palghar, Maharashtra, registered with MahaRERA as P99000012539 on 1 Sep 2017. Possession was promised by 30 Sep 2019 and is now 85 months past that date. The completion date has moved by 12 months from the original filing. 14 complaints are on record with the regulator.
At a glance
Project
- NameHDIL PARADISE CITY SECTOR 2
- TypeOthers
- Location
- MAHIM
- PALGHAR(WEST)
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000012539
- ReraGenie IDRG-MH-11297
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion30 Sep 2019
- Revised completionRevised to 30 Sep 2019 (originally 30 Sep 2018)
- Buildings20 building records
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 2 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 3 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 4 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 5 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 6 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 7 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 8 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 9 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 10 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 11 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 12 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 13 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 14 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 15 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 16 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 17 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 18 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 19 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING NO 20 | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 9 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
60 of 220 construction stages are filed complete across 20 buildings. The stage furthest along is Slabs of Super Structure, at 80%.
BUILDING NO 150%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 246%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 348%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 448%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 550%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 652%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 5% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 739%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 824%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 924%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1043%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 1% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1124%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1227%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1324%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1446%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 1% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1524%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1645%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 1% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1724%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1824%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1924%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 2045%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING NO 1 | 13 | 13 |
| BUILDING NO 2 | 9 | 9 |
| BUILDING NO 3 | 2 | 2 |
| BUILDING NO 4 | 2 | 2 |
| BUILDING NO 5 | 9 | 9 |
| BUILDING NO 6 | 4 | 4 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SAPPHIRE LAND DEVELOPMENT PRIVATE LTD | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE & ASSOCITES |
| Engineer | SHAH GATTANI CONSULTANTS |
| Partner | Role in project |
|---|---|
| HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterMore than 50% of construction work at the project site has been completed in Sector 2. Out of 20 buildings in Sector 2 - 9 buildings work till terrace slab along with brick work completed, 1 building till 4th slab completed, 1 building with 1st slab is completed & only 9 buildings plinth is completed.Secondly because of black cotton soil the work can not progress during monsoon.However we will try to catch with the schedule by fastening the work activities to the extent possible. Hence we are looking for applying for updating the revised project completion date.
Complaints filed with MahaRERA14
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001492 | Shobha Sudhakar Kanchan | HDIL | 13/11/2017 |
| CC006000000001827 | Rupa Vora | HOUSING DEVELOPMENT AND INFRASTRUCTURE LIMITED | 18/11/2017 |
| CC006000000078633 | Ravindra Ashok Mishra | Housing Development and Infrastructure Limited | 27/03/2019 |
| CC006000000023620 | DWIJENDRA MOHAN GANGAPRASAD MISHRA | M/s. HDIL | 06/03/2018 |
| CC006000000056015 | Dilip Yerunkar | Housing Development And Infrastructure Ltd | 10/09/2018 |
| CC006000000056125 | Dharmendra Makwana | HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD | 07/09/2018 |
| CC006000000056946 | merai meenaxi jayesh and merai jayesh | housing development infrastructure ltd | 20/12/2018 |
| CC006000000057538 | Priyanka Shashank Fadia & Uma SHashank Fadia | Housing Development & Infrastructure Limited | 04/01/2019 |
| CC006000000078312 | Yusuf Sonawala | Housing Development and Infrastructure Limited | 01/03/2019 |
| CC006000000078577 | Dayesh Mavjibhai Parmar | Housing Development and Infrasctructure Ltd. | 27/03/2019 |
| CC006000000161228 | NITESH SITARAM MANE | HOUSING DEVELOPMENT & INFRASTRUCTURE LIMITED | 17/10/2019 |
| CC006000000161265 | SUNITA SHESHNATH CHAUHAN | HOUSING DEVELOPMENT & INFRASTRUCTURE LIMITED | 16/10/2019 |
| CC006000000197786 | Durga Amitava Ghosh Amitava Ghosh | Housing Development and infrastructure Ltd. | 28/07/2021 |
| CC006000000197885 | Durga Amitava Ghosh Amitava GhoshG | Housing Development and infrastructure Ltd. | 04/08/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 5)File: Paradise City,Sector 2 - Form 5.pdf | 9 Apr 2019 |
| Proforma of Allotment letterFile: Agreement Paradise City 16082017 Sector 2.pdf | 12 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ArchCertSector 2.pdf | 18 Jan 2018 |
| Details of encumbrancesFile: No Encumbrance Cerificate Paradise City Sec 2,4,5AND6.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B - Sector 2 28072017.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sector 2.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA_Cer_Paradise City - Sector 2_1.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA_Cer_Paradise City - Sector 2_2.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA_Cer_Paradise City - Sector 2_3.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA_Cer_Paradise City - Sector 2_4.pdf | 31 Jul 2017 |
| PAN CardFile: PANCARD.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TC-Paradise_City_Part-1.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TC-Paradise_City_Part-2.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TC-Paradise_City_Part-3.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TC-Paradise_City_Part-4.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TC-Paradise_City_Part-5.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2-1SECTOR-2 - Part-1.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2-2SECTOR-2 - Part-2.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: AL_AFS_Paradise City - Sector-2.pdf | 30 Jul 2017 |
| Layout approvalFile: 03 LAYOUT 2017.pdf | 29 Jul 2017 |
| Layout approvalFile: 02 LAYOUT 2011.pdf | 29 Jul 2017 |
| Building plan approvalFile: 00 N A ORDER PALGHAR 6 6 2011.pdf | 29 Jul 2017 |
| Building plan approvalFile: 01 NA ORDER PALGHAR 20 1 2017.pdf | 29 Jul 2017 |
| Layout approvalFile: 18 TYPE 21A WINGB.pdf | 29 Jul 2017 |
| Layout approvalFile: 17 TYPE 21.pdf | 29 Jul 2017 |
| Layout approvalFile: 13 Type 6A N.pdf | 29 Jul 2017 |
| Layout approvalFile: 14 Type 6B N.pdf | 29 Jul 2017 |
| Layout approvalFile: 15 Type 6C N.pdf | 29 Jul 2017 |
| Layout approvalFile: 04 Type 1A N.pdf | 29 Jul 2017 |
| Layout approvalFile: 05 Type 1C N.pdf | 29 Jul 2017 |
| Layout approvalFile: 06 Type 1D N.pdf | 29 Jul 2017 |
| Layout approvalFile: 07 Type 2A N.pdf | 29 Jul 2017 |
| Layout approvalFile: 08 Type 5 N.pdf | 29 Jul 2017 |
| Layout approvalFile: 08 Type 5 N.pdf | 29 Jul 2017 |
| Layout approvalFile: 10 TYPE 6.pdf | 29 Jul 2017 |
| Layout approvalFile: 11 Type 6 N.pdf | 29 Jul 2017 |
| Layout approvalFile: 12 TYPE 6A.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 02 LAYOUT 2011.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 03 LAYOUT 2017.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 04 Type 1A N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 05 Type 1C N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 06 Type 1D N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 07 Type 2A N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 08 Type 5 N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 08 Type 5 N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 10 TYPE 6.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 11 Type 6 N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 12 TYPE 6A.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 13 Type 6A N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 14 Type 6B N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 15 Type 6C N.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 17 TYPE 21.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 18 TYPE 21A WINGB.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: 00 N A ORDER PALGHAR 6 6 2011.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: 01 NA ORDER PALGHAR 20 1 2017.pdf | 29 Jul 2017 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| HDIL INDUSTRIAL PARK | BESIDES LAXMI MARBLES CHANDANSAR ROAD VILLAGE CHANDANSAR VIRAR EAST | 627 | Completed | Apr 2017 | Late, Jul 2017 |
| PREMIER EXOTICA II | PREMIER AUTO KIROL ROAD KURLA WEST MUMBAI 400070 | 83 | Completed | Jun 2013 | Late, Jun 2017 |
| HARMONY | NEW LINK ROAD GOREGAON WEST MUMBAI 400104 | 221 | Completed | Jun 2013 | Late, Jul 2017 |
| PREMIER RESIDENCES | PREMIER AUTO KURLA WEST MUMBAI - 400070 | 1,087 | Completed | Dec 2012 | Late, Mar 2017 |
| GALAXY APARTMENTS WING ABE | BHANDARY ESTATE KURLA EAST MUMBAI 400024 | 314 | Completed | Dec 2011 | Late, Jun 2017 |
| HDIL RESIDENCY PARK | OPP YAZOO PARK NARANGI BYPASS ROAD VILLAGE DONGRE VIRAR WEST | 1,199 | Completed | Aug 2011 | Late, Oct 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 13 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep HDIL PARADISE CITY SECTOR 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PALGHAR(WEST)3,200+ in Palghar
Filed coordinates, straight-line distance. 130 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD has 14 registrations on MahaRERA, including THE NEST and PREMIER EXOTICA I. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that HDIL PARADISE CITY SECTOR 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if HDIL PARADISE CITY SECTOR 2 is delayed beyond 30 Sep 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HDIL PARADISE CITY SECTOR 2?
The registered promoter entity is HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HDIL PARADISE CITY SECTOR 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HDIL PARADISE CITY SECTOR 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HDIL PARADISE CITY SECTOR 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HDIL PARADISE CITY SECTOR 2?
The professionals named in the filing: Architect: AJAY WADE & ASSOCITES; Engineer: SHAH GATTANI CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HDIL PARADISE CITY SECTOR 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback