Red flags

  • Completion date moved by 13 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2019Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 18 documents Report an error

Hayaat Tower is a Residential / Group Housing project by Sky Developers in Palghar, Maharashtra, registered with MahaRERA as P99000003783 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Apr 2019. The completion date has moved by 13 months from the original filing.

At a glance

Project

  • NameHayaat Tower
  • TypeResidential / Group Housing
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000003783
  • ReraGenie IDRG-MH-45888

Builder

  • NameSky Developers
  • Entity typePartnership
  • PartnersMahibulla Khan, Niyazahmed Khan, Rawabali Faridan Khan
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseMar 2018Revised toApr 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Apr 2019
  • Revised completionRevised to 30 Apr 2019 (originally 31 Mar 2018)
  • Buildings2 building records
  • Documents filed18 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA80000
B WingNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

A Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
A Wing11
B Wing11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,229 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1967.57
Proposed, not sanctioned1,968 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVasai East

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Wade & Associates
PartnerRole in project
Sky Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000001424Mar 2018 → Apr 2019

Reason as filed by the promoterProject work is 100% complete and application for OC has been filed. But the OC has not been received. The application for OC is attached for your reference.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Oct 2021

Documents filed18

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Sold Declaration.pdf4 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - Hayaat Tower_compressed.pdf4 Oct 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Hayaat Tower.pdf4 Oct 2021
OtherFile: OC - Hayaat Tower_compressed.pdf29 Jul 2019
Certificates of CA (Form 5)File: Form 5 - Signed - Hayaat Tower.pdf24 Apr 2019
Building plan approvalFile: Floor Plan-ilovepdf-compressed.pdf31 Jul 2017
Layout approvalFile: Layout Plan-ilovepdf-compressed.pdf31 Jul 2017
PAN CardFile: Sky Developer Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: Title report.pdf31 Jul 2017
Details of encumbrancesFile: Encumrances declaration.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan-ilovepdf-compressed.pdf31 Jul 2017
Building Plan Approval (IOD)File: Floor Plan-ilovepdf-compressed.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C 1 - 2 Copy.pdf31 Jul 2017
Declaration in FORM BFile: Form B Declaration Tower.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificare signed.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT HAYAATTOWER PDF.pdf31 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Hayaat PalaceP99000008597Vasai-Virar City (M Corp), Palghar-Aug 2017CompletedAug 2023Registered original: Sep 2020Sep 2020
Hayaat HeightWaliv Vasai East27-CompletedDec 2012Late, May 2013

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 13 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hayaat Tower on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmHayaat TowerCompleted 34Lapsed / revoked 17Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: Sky Developers

Sky Developers has 10 registrations on MahaRERA, including Hayaat Palace and Hayaat Tower. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Hayaat Tower is delayed beyond 30 Apr 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hayaat Tower?

The registered promoter entity is Sky Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hayaat Tower?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Hayaat Tower?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hayaat Tower?

The professionals named in the filing: Architect: Ajay Wade & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hayaat Tower?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hayaat Tower. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hayaat Tower to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.