Home / Browse projects / Palghar, Maharashtra / HAYAAT RELIABLE

Registered No litigation declared Residential / Group Housing project

HAYAAT RELIABLE

By M M LIFESTYLE

RG-MH-93334 · RERA P99000047763 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Internal walls, 60%
164 of 197Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

HAYAAT RELIABLE is a Residential / Group Housing project by M M LIFESTYLE in Palghar, Maharashtra, registered with MahaRERA as P99000047763 on 28 Nov 2022. Possession is promised by 31 Dec 2028. 33 of the 197 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameHAYAAT RELIABLE
  • TypeResidential / Group Housing
  • Location
    • PELHAR
    • VASAI FATA
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000047763
  • ReraGenie IDRG-MH-93334

Builder

  • NameM M LIFESTYLE
  • Entity typePartnership
  • PartnersMAHIBULLAH MOHAMMAD SHAFI KHAN, RAWABALI FARIDAN KHAN, MOHD SWALEH MOHD YAMIN QURAISHI, MUSHIR MEHMOOD ANSARI, MEHMOOD MOHIUDDIN ANSARI, RAZIA KHATOON ASZAD HUSSAIN KHAN, FIROZ SHAUKAT ALI KHAN, ASHRAF GULMOHD KHAN
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2022PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2022
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed99 files

Current status

17%33 of 197 units booked

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D WINGNA23221943197

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

D WING: 51% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
LIFTYes0%

Parking filed242

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots242
Open Space242

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,365 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RELIABLE PRISM CONSTRUCTION COMPANYVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityMUNIR AHMED MOHAMMAD SAEED KHAN
Permissible FSI12011.15
Proposed, not sanctioned12,011 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOmkar Building, Waliv, Vasai East, Palghar, 401208

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHYAM R KASHID
EngineerS S & ASSOCIATES
EngineerFARAZ AHMED SHAHEEDUDDIN SHAH
Chartered AccountantRAHUL PANDEY
Chartered AccountantShital Vagadargi
Chartered AccountantNamrata Sharma
PartnerRole in project
M M LIFESTYLE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form-1.pdf23 Jun 2026
Form 2File: FORM -2.pdf23 Jun 2026
Form 3File: FORM 3 SIGN_compressed.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf23 Jun 2026
Form 1File: Form-1.pdf23 Jun 2026
Form 2File: Form-2 with sign.pdf23 Jun 2026
Form 3File: FORM 3 SIGN_compressed.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf23 Jun 2026
Form 1File: Form-1.pdf23 Jun 2026
Form 2File: MM Lifestyle Q3 Form-2.pdf23 Jun 2026
Form 3File: FORM 3 SIGN_compressed.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf23 Jun 2026
Form 1File: MM Lifestyle Q4 Form-1.pdf23 Jun 2026
Form 2File: MM Lifestyle Q4 Form-2.pdf23 Jun 2026
Form 3File: FORM 3 SIGN_compressed.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf23 Jun 2026
Form 5 (FY 2024-2025)File: Form 5.pdf30 Sep 2025
Disclosure of Sold and Booked InventoryFile: Inventorty Details F (1).pdf17 Sep 2025
Form 3File: Form 3 Q1 F .pdf17 Sep 2025
Form 1File: Architect certificate 2223.pdf17 Sep 2025
Form 2File: Engineer Certificate 2223.pdf17 Sep 2025
Form 3File: CA Certificate form 3.pdf17 Sep 2025
Form 1File: Architect Certificate_.pdf17 Sep 2025
Form 2File: Engineer Certificate.pdf17 Sep 2025
Disclosure of Sold and Booked InventoryFile: Inventorty Details F (1).pdf17 Sep 2025
Form 1File: Architect Certificate Q3.pdf17 Sep 2025
Form 2File: Engineer Certificate Q3.pdf17 Sep 2025
Form 3File: CA Certificate F3.pdf17 Sep 2025
Disclosure of Sold and Booked InventoryFile: Inventorty Details F (1).pdf17 Sep 2025
Form 1File: Architect Certificate Q4_.pdf17 Sep 2025
Form 2File: Engineer Certificate Q4.pdf17 Sep 2025
Form 3File: Form 3 Q4.pdf17 Sep 2025
Disclosure of Sold and Booked InventoryFile: Engineer Certificate Q4.pdf17 Sep 2025
Form 1File: Engineer Certificate_Q3_2223.pdf15 Aug 2025
Form 2File: Architect Certificate.pdf15 Aug 2025
Form 3File: Form 3 Q3C.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Inventorty Details F.pdf15 Aug 2025
Form 1File: Architect certificate 2223 Q4.pdf15 Aug 2025
Form 2File: Engineer Certificate 2223 Q4.pdf15 Aug 2025
Form 3File: Form 3_compressed.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Inventorty Details F.pdf15 Aug 2025
OthersFile: M M LIFE STYLE - form 5 FY 22-23.pdf15 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Hayaat Signed.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Hayyat Reliable - Q4 F.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Hayaat Signed.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Hayaat Reliable.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 28-01-2025 SIGN.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 29-01-2025 SIGN.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-01-2025 SIGN.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 29-01-2025 SIGN.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MM Lifestyle Architect Certificate Q1.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_MM LIfestyle_23-24_Q4_.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MM Lifestyle Engineer Certificate Q1.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MM LIFESTYLE FORM 5 23-24.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q3_.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q4_.pdf6 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q3.pdf6 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q4.pdf6 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3_Q3_.pdf6 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3_Q3_.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_.pdf23 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf23 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Q2_.pdf22 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: M M LIFE STYLE_.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf13 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 2223 Q4_.pdf13 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Q3_2223.pdf13 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_.pdf13 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 2223 Q4_.pdf13 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Engineer Certificate 2223 Q4.pdf13 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf14 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Q3_2223.pdf14 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Format A.pdf10 Jan 2023
Details of encumbrances concerned to LegalFile: LETTER OF ENCUMBRANCE LEGAL.pdf21 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_200247137072_For_Asset_Based_Search_14_09_2022_17_59_20_115.pdf21 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Sep 2022
Proforma of Agreement for saleFile: AFS (REVISED.pdf21 Sep 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER NEW_compressed.pdf21 Sep 2022
Proforma of Allotment letterFile: AGREEMENT FOR SALE_RERA MODEL Revised.pdf21 Sep 2022
Proforma of Agreement for saleFile: ilovepdf_merged (2).pdf21 Sep 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Hayaat Galaxy IIP99000030622Waliv, Palghar85Sep 2021OngoingNov 2026Not due yet
HAYAAT GALAXY IIS.50 H NO 10 VILLAGE WALIV VASAI EAST85-OngoingNov 2026Nov 2026

How this compares with Palghar

17%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HAYAAT RELIABLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI FATA3,200+ in Palghar

2 kmHAYAAT RELIABLECompleted 124Lapsed / revoked 57Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 316 registered projects within 2 km.

Builder: M M LIFESTYLE

M M LIFESTYLE has 1 registration on MahaRERA, including HAYAAT RELIABLE. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if HAYAAT RELIABLE is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAYAAT RELIABLE?

The registered promoter entity is M M LIFESTYLE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAYAAT RELIABLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAYAAT RELIABLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HAYAAT RELIABLE?

The professionals named in the filing: Architect: SHYAM R KASHID; Engineer: S S & ASSOCIATES; Engineer: FARAZ AHMED SHAHEEDUDDIN SHAH; Chartered Accountant: RAHUL PANDEY; Chartered Accountant: Shital Vagadargi; Chartered Accountant: Namrata Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAYAAT RELIABLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAYAAT RELIABLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAYAAT RELIABLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.