Home / Browse projects / Pune, Maharashtra / GURUPRASAD KUNJ
GURUPRASAD KUNJ
By Kotibhaskar Infrastructures &Developers Pvt.Ltd.
RG-MH-69377 · RERA P52100054449 · Last updated on MahaRERA portal: 31 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 5 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GURUPRASAD KUNJ is a Residential / Group Housing project by Kotibhaskar Infrastructures &Developers Pvt.Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100054449 on 25 Jan 2024. Possession is promised by 30 Oct 2026. The completion date has moved by 5 months from the original filing. 3 of the 12 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameGURUPRASAD KUNJ
- TypeResidential / Group Housing
- Location
- Prabhat Road
- Pune
- Pune (M Corp.)
- Pune City
- 411004
- Pincode411004
- RERA no.P52100054449
- ReraGenie IDRG-MH-69377
Builder
- NameKotibhaskar Infrastructures &Developers Pvt.Ltd.
- Entity typeCompany
- CINU45209PN2011PTC140254
- GSTIN27AAQCS2145B1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorsDilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar
- ChairpersonsChidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar
- Other registrations27 more →
- Completed15 of 28
- No longer live1 lapsed, de-registered or revoked
- Past their filed date2
- Declared earlier projects11 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Jan 2024
- Promised completion30 Oct 2026
- Revised completionRevised to 30 Oct 2026 (originally 1 May 2026)
- Buildings1 building record
- Documents filed101 files
Current status
Figures as on 31 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GURUPRASAD KUNJ | NA | 7 | 6 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GURUPRASAD KUNJ: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed53
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| GURUPRASAD KINJ | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GURUPRASAD KUNJ | NA | Rs 10.09 cr | Rs 11.27 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shinde Joshi & Associates |
| Engineer | Shridhar M Shet |
| Engineer | VIRENDRA SHRIMANT DAINGADE |
| Chartered Accountant | Omkar Chandak |
| Chartered Accountant | AMIT ANIL SHENDE |
| Partner | Role in project |
|---|---|
| Kotibhaskar Infrastructures &Developers Pvt.Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Construction of the project is completed only finishing work of the project is remaining. We have obtained Part Occupancy Certificate dated 02.03.2026 bearing no. OCC/1297/25 issued by Pune Municipal Corporation, Pune. We will require additional time to receive Full Occupancy Certificate from Pune Municipal Corporation for the said project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Dec 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jul 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2026
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Guruprasad Kunj Form 2A_0001.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form 1- 30062026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form 2 30062026_0001.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form 3 30062026_0001_11zon.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-31032026.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj- Form 2-30032026.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj- Form-3-30032026.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-30092025-signed.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-30092025-Signed.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3-300092025-Signed.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3-31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3-31122025.pdf | 29 Jan 2026 |
| Form 5 (FY 2024-2025)File: Guruprasad kunj-Form-5-2024-25.pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-30062025.pdf | 6 Oct 2025 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-30062025.pdf | 6 Oct 2025 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3 06-10-2025_0001.pdf | 6 Oct 2025 |
| Withdrawal Update Form 1File: Guruprasad Kunj Form-1-30062025.pdf | 22 Jul 2025 |
| Withdrawal Update Form 2File: Guruprasad Kunj Form-2-30062025.pdf | 22 Jul 2025 |
| Withdrawal Update Form 3File: Guruprasad Kunj Form-3-30062025.pdf | 22 Jul 2025 |
| Commencement certificateFile: doc10083520250624062529.pdf | 11 Jul 2025 |
| Building plan approvalFile: 1.pdf | 11 Jul 2025 |
| Building plan approvalFile: 2.pdf | 11 Jul 2025 |
| Building plan approvalFile: 3.pdf | 11 Jul 2025 |
| Building plan approvalFile: 1.pdf | 1 Jul 2025 |
| Building plan approvalFile: 2.pdf | 1 Jul 2025 |
| Building plan approvalFile: 3.pdf | 1 Jul 2025 |
| Form 2A (FY 2024-2025)File: Guruprasad Kunj Form 2A_0001.pdf | 12 Jun 2025 |
| Form 1File: Guruprasad Kunj Form-1-31032025.pdf | 2 Jun 2025 |
| Form 2File: Guruprasad Kunj-Form 2-29032025.pdf | 2 Jun 2025 |
| Form 3File: Guruprasad Kunj Form-3-29032025.pdf | 2 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Guruprasad Kunj-Sold Unsold-29032025.pdf | 2 Jun 2025 |
| Form 2A (FY 2023-2024)File: Guruprasad Kunj Form 2 A-23-24.pdf | 2 Jun 2025 |
| Form 5 (FY 2023-2024)File: Guruprasad Kunj Form-5_0001.pdf | 2 Jun 2025 |
| Building plan approvalFile: Plan 1.pdf | 30 May 2025 |
| Building plan approvalFile: Plan 2.pdf | 30 May 2025 |
| Form 1File: LG_Guruprasad Kunj Form 1-31032024.pdf | 12 May 2025 |
| Form 3File: LG_Guruprasad Kunj Form 1-31032024.pdf | 12 May 2025 |
| Form 1File: LG-Guruprasad Kunj- Form 3-30062024.pdf | 12 May 2025 |
| Form 2File: LG-Guruprasad Kunj Form-1-30062024.pdf | 12 May 2025 |
| Disclosure of Sold and Booked InventoryFile: LG-Guruprasad Kunj Form-2-30062024.pdf | 12 May 2025 |
| Form 1File: LG-Guruprasad Kunj Form-1-30062024.pdf | 12 May 2025 |
| Form 2File: LG_Guruprasad Kunj Form 1-31032024.pdf | 12 May 2025 |
| Form 3File: LG-Guruprasad Kunj Form-2-30062024.pdf | 12 May 2025 |
| Disclosure of Sold and Booked InventoryFile: LG-Guruprasad Kunj- Form 3-30062024.pdf | 12 May 2025 |
| Form 1File: LG-Guruprasad Kunj Form-1-30062024.pdf | 12 May 2025 |
| Form 2File: LG_Guruprasad Kunj Form 1-31032024.pdf | 12 May 2025 |
| Form 3File: LG-Guruprasad Kunj- Form 3-30062024.pdf | 12 May 2025 |
| Disclosure of Sold and Booked InventoryFile: LG-Guruprasad Kunj Form-2-30062024.pdf | 12 May 2025 |
| Building plan approvalFile: Plan 1_11zon (1).pdf | 6 May 2025 |
| Building plan approvalFile: Plan 2_11zon (1).pdf | 6 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Guruprasad CC - 02072024_11zon.pdf | 6 May 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1_11zon (1).pdf | 6 May 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2_11zon (1).pdf | 6 May 2025 |
| Declaration about Commencement CertificateFile: Guruprasad Kunj- Declaration_0001.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Guruprasad Kunj Form-1-31032025.pdf | 12 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Guruprasad Kunj Form-2_0001.pdf | 29 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Guruprasad Kunj- Sold- Unsold Inventory_0001.pdf | 29 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Guruprasad Kunj Form-3_0002.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GURUPRASAD.pdf | 17 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Guruprasad Kunj Form-5_0001.pdf | 13 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Guruprasad Kunj Form 2 A_0001.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Guruprasad Kunj Form-3_0001.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Guruprasad Kunj Form-2_0001.pdf | 25 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Guruprasad Kunj- Sold-Unsold Inventory_0001.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LG-Guruprasadkunj Form 1-30092024.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Guruprasad Kunj Form-2_0001.pdf | 2 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Guruprasad Kunj_0001.pdf | 2 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Guruprasad Kunj- Form 3_0001.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Guruprasad Kunj Form-1_0001.pdf | 12 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: LG-Guruprasad Kunj-Soldunsold-31032024.pdf | 25 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LG-Guruprasad Kunj Form-2-30032024.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Guruprasad Kunj Form 3-30032024.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LG_Guruprasad Kunj Form 1-31032024.pdf | 20 Apr 2024 |
Promoter's earlier projects11
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| INDUKIRAN CO-OP HOUSING SOCIETY LIMITEDP52100046237 | KOTHRUD, Pune | 1 | Jun 2022 | Completed | Nov 2025 | Oct 2024 |
| SARITA CHSLP52100034229 | KOTHRUD, Pune | 70 | Mar 2022 | Completed | Oct 2025 | May 2025 |
| Purva HeightsP53100034113 | Warnali, Sangli | 36 | Mar 2022 | Completed | Sep 2025 | Mar 2025 |
| PRABHAKAR CHSLP52100049315 | Pune, Pune | - | Feb 2023 | Completed | Jul 2025 | Apr 2025 |
| Kajal Co operative Housing Society LtdP52100032652 | Kothrud, Pune | 67 | Jan 2022 | Ongoing | Dec 2024 | Not delivered |
| MUKUNDP52100045860 | MAHARSHI KARVENAGAR, Pune | - | Jun 2022 | Completed | May 2024 | Late, Jun 2024 |
| SHUBHASHREEP52100045350 | PUNE, Pune | - | May 2022 | Completed | Mar 2024 | Late, Jun 2024 |
| Annapurna | Hingane Budruk Haveli Pune | 5 | - | Completed | Dec 2017 | Jun 2017 |
| Ankoorshree Co-operative Housing Society | Happy Colony Lane 3 Kothrud Pune | 21 | - | Completed | Oct 2017 | May 2017 |
| Snehvardhan Co-operative Housing Society | Patwardhan Co-operative Housing Society | 20 | - | Completed | May 2017 | Jan 2017 |
| Chinar Co-operative Housing Society | Kothrud Pune | 24 | - | Completed | Mar 2014 | Mar 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 27 other registrations, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GURUPRASAD KUNJ on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pune13,700+ in Pune
VENKATESH ERANDWANE CENTRAL - BUILDING-B1 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C. Road Phase 3
PALASH REALTORS LLP
45 NIRVAANA HILL - C2 WING
SINEW DEVELOPERS PRIVATE LIMITED
VENKATESH ERANDWANE CENTRAL - BUILDING-B2 - PH
SHREE VENKATESH BUILDCON PVT LTD
VENKATESH ERANDWANE CENTRAL - BUILDING-B3 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C Road Phase 2
PALASH REALTORS LLP
Builder: Kotibhaskar Infrastructures &Developers Pvt.Ltd.
Kotibhaskar Infrastructures &Developers Pvt.Ltd. has 28 registrations on MahaRERA, including Sugam Cooperative Housing Society Limited and Vasant Vihar Co-operative Housing Society. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GURUPRASAD KUNJ is delayed beyond 30 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GURUPRASAD KUNJ?
The registered promoter entity is Kotibhaskar Infrastructures &Developers Pvt.Ltd., a company as per the filing. Its CIN U45209PN2011PTC140254 and GSTIN 27AAQCS2145B1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GURUPRASAD KUNJ?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GURUPRASAD KUNJ?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GURUPRASAD KUNJ?
The professionals named in the filing: Architect: Shinde Joshi & Associates; Engineer: Shridhar M Shet; Engineer: VIRENDRA SHRIMANT DAINGADE; Chartered Accountant: Omkar Chandak; Chartered Accountant: AMIT ANIL SHENDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GURUPRASAD KUNJ?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback