Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
May 2019Possession promisedregistration recorded completed
140 of 154Construction stages doneacross 14 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

Gundecha Woods Phase 1 is a Others project by GundechaConstructionPvtLtd in Palghar, Maharashtra, registered with MahaRERA as P99000003314 on 5 Aug 2017. The registration is recorded completed; possession was promised by 31 May 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGundecha Woods Phase 1
  • TypeOthers
  • Location
    • Nandore
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000003314
  • ReraGenie IDRG-MH-25906

Builder

  • NameGundechaConstructionPvtLtd
  • Entity typeCompany
  • ChairpersonPARAS DEVRAJ GUNDECHA
  • Managing DirectorsDEEPAK PARAS GUNDECHA, POONAM PARAS GUNDECHA
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseMay 2018Revised toMay 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion31 May 2019
  • Revised completionRevised to 31 May 2019 (originally 31 May 2018)
  • Buildings14 building records
  • Documents filed100 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GULMOHAR ANA60000
GULMOHAR BNA60000
GULMOHAR CNA60000
GULMOHAR DNA60000
GULMOHAR ENA60000
PINE ANA60000
PINE BNA60000
PINE CNA60000
PALM ANA60000
PALM BNA60000
PALM CNA60000
FERN ANA60000
FERN BNA60000
FERN CNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building14

As on 20 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

140 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Podiums (if any), at 0%.

GULMOHAR A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
GULMOHAR B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
GULMOHAR C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
GULMOHAR D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
GULMOHAR E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PINE A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PINE B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PINE C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PALM A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PALM B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PALM C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
FERN A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
FERN B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
FERN C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14
BuildingClosed/CoveredTotal
GULMOHAR A11
GULMOHAR B11
GULMOHAR C11
GULMOHAR D11
GULMOHAR E11
PINE A11
PINE B11
PINE C11
PALM A11
PALM B11
PALM C11
FERN A11
FERN B11
FERN C11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,126 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14502.71
Proposed, not sanctioned12,102 sq m
Buildings approved14
Buildings sanctioned14

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAGAR AVENUE GROUND FLOOR S V ROAD ANDHERI WEST MUMBAI 400058

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYOGESH K MHATRE
PartnerRole in project
GundechaConstructionPvtLtd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000000327May 2018 → May 2019

Reason as filed by the promoterWe have completed the entire work mentioned in phase I which is registered with Maha RERA Authority, and accordingly we have received Occupation Certificate for Gulmohar wing B, C, D, Pine wing B, C, Palm wing A, B, and Fern wing B, C. As per the policy of Gram Panchayat they will issue Occupation Certificate of the balance wing only when the entire wing is completed and because of this even though we have completed the entire work as per approved plan of Gulmohar A, E, Pine A, Palm C and Fern A still the Occupation Certificate is not received. We have started completing the work of Phase II o

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500643Mitesh Shyamsunder VarshneyGundechaConstructionPvtLtd24/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Nov 2019

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form - 4 Architects Certificate.pdf20 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Cert Form5.pdf20 Dec 2021
OtherFile: Gundecha woods Society Registration Certificate.pdf21 Jul 2021
Architect’s Certificate on Completion of Project (Form 4)File: Gundecha Woods Arch Cert Plot-1 Form4.pdf7 Sep 2020
Architect’s Certificate on Completion of Project (Form 4)File: Gundecha Woods Arch Cert Plot-2 Form4.pdf7 Sep 2020
Architect’s Certificate on Completion of Project (Form 4)File: Gundecha Woods Arch Cert Plot-3 Form4.pdf7 Sep 2020
Architect’s Certificate on Completion of Project (Form 4)File: Gundecha Woods Arch Cert Plot-9 Form4.pdf7 Sep 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Collector Bhogavata Order plot no 1.pdf13 Nov 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Collector Bhogavata Order plot no 2.pdf13 Nov 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Collector Bhogavata Order plot no 3.pdf13 Nov 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Collector Bhogavata Order plot no 9.pdf13 Nov 2019
OtherFile: Collector Bhogavata Order plot no 1.pdf13 Nov 2019
Certificates of CA (Form 5)File: Form 5 CA Cert Gundecha Woods.pdf12 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(1) 2013.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(1) 2017.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(2) 2013.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(2) 2017.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(3) 2013.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(3) 2017.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(9) 2013.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NAPermission Woods 145(9) 2017.pdf10 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gundecha Woods Plot-1 Arch Cert Form1.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gundecha Woods Plot-2 Arch Cert Form1.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gundecha Woods Plot-3 Arch Cert Form1.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gundecha Woods Plot-9 Arch Cert Form1.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gundecha Woods Plot-1 Engg Cert Form2.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gundecha Woods Plot-2 Engg Cert Form2.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gundecha Woods Plot-3 Engg Cert Form2.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gundecha Woods Plot-9 Engg Cert Form2.pdf30 Oct 2017
Certificates of CA (Form 3)File: Gundecha Woods CA Cert Form-3.pdf30 Oct 2017
OtherFile: OC PLOT 1.pdf30 Oct 2017
OtherFile: OC PLOT 2.pdf30 Oct 2017
OtherFile: OC Plot 3.pdf30 Oct 2017
OtherFile: OC PLOT 9.pdf30 Oct 2017
Building plan approvalFile: PLOT 3 PROPOSED BLOCK PLAN.pdf28 Jul 2017
Building plan approvalFile: PLOT 1 PROPOSED BLOCK PLAN.pdf28 Jul 2017
Building plan approvalFile: PLOT 2 PROPOSED BLOCK PLAN.pdf28 Jul 2017
Building plan approvalFile: PLOT 9 PROPOSED BLOCK PLAN.pdf28 Jul 2017
Layout approvalFile: COPY OF LAYOUT APPROVAL.pdf28 Jul 2017
Building plan approvalFile: IOD Plot No 3.pdf28 Jul 2017
Building plan approvalFile: IOD Plot No 1.pdf28 Jul 2017
Building plan approvalFile: IOD Plot No 2.pdf28 Jul 2017
Building plan approvalFile: Plot 1 Type E3.pdf28 Jul 2017
Building plan approvalFile: IOD Plot No 9.pdf28 Jul 2017
Building plan approvalFile: Plot 1 Type A1.pdf28 Jul 2017
Building plan approvalFile: LAYOUT PLAN sector a.pdf28 Jul 2017
Building plan approvalFile: LAYOUT PLAN SECTOR A B C.pdf28 Jul 2017
Building plan approvalFile: Plot 9 Type E10.pdf28 Jul 2017
Building plan approvalFile: Plot 3 Type E8.pdf28 Jul 2017
Building plan approvalFile: Plot 9 Type F3.pdf28 Jul 2017
Building plan approvalFile: Plot 9 Type E11.pdf28 Jul 2017
Building plan approvalFile: Plot 1 Type E5.pdf28 Jul 2017
Building plan approvalFile: Plot 1 Type E6.pdf28 Jul 2017
Building plan approvalFile: Plot 1 Type E7.pdf28 Jul 2017
Building plan approvalFile: Plot 2 Type D1.pdf28 Jul 2017
Building plan approvalFile: Plot 3 Type D4.pdf28 Jul 2017
Building plan approvalFile: Plot 2 Type D2 SR 129.pdf28 Jul 2017
Building plan approvalFile: Plot 2 Type E8.pdf28 Jul 2017
Building plan approvalFile: Plot 2 Type D2 SR 106.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf28 Jul 2017
Details of encumbrancesFile: NO ENCUMBRANCE.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: COPY OF LAYOUT APPROVAL.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Plot No 1.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Plot No 2.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Plot No 3.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Plot No 9.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 1 Type A1.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 1 Type E3.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 1 Type E5.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 1 Type E6.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 1 Type E7.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 2 Type D1.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 2 Type D2 SR 106.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 2 Type D2 SR 129.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 2 Type E8.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 3 Type D4.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 3 Type E8.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 9 Type E10.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 9 Type E11.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plot 9 Type F3.pdf28 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ZenithPK Road Near Kalidas Auditorium Mulund West Mumbai 400080244CompletedJun 2016Late, Nov 2016

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gundecha Woods Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nandore3,200+ in Palghar

2 kmGundecha Woods Phase 1Completed 10Lapsed / revoked 4Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: GundechaConstructionPvtLtd

GundechaConstructionPvtLtd has 2 registrations on MahaRERA, including Gundecha Woods Phase 1 and GUNDECHA-KBK-MAGNUM PHASE I. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Gundecha Woods Phase 1 is delayed beyond 31 May 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gundecha Woods Phase 1?

The registered promoter entity is GundechaConstructionPvtLtd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gundecha Woods Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gundecha Woods Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gundecha Woods Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gundecha Woods Phase 1?

The professionals named in the filing: Architect: YOGESH K MHATRE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gundecha Woods Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gundecha Woods Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gundecha Woods Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.